| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 23 Apr 2026 | Completed | 494,285,070.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 23 Apr 2026 | Completed | 694,544,069.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 21 Apr 2026 | Ongoing | 270,000,000.00 | 40.0% |
No enough funds
|
more funds be allocated for completion
|
66KV Power lines to KLIP suststion is 99% complete
|
| 10 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
There is no budgetary allocation in FY 2025/26
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
There is no budgetary allocation in FY 2025/26
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
There is no budgetary allocation in FY 2025/26
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
There is no budgetary allocation in FY 2025/26
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
There is no budgetary allocation in the FY 2025/26
|
| 24 Nov 2025 | Ongoing | 0.00 | 50.0% |
N/A
|
N/A
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 8,000,000,000.00 | 85.0% |
Exchequer release coupled with inadequate budgetary allocation that has lead to huge pending bills that has been accumulating over time
|
There is need for a special fund to be established for this programme which has a high impact on food security
|
High registration of farmers also led to high uptake
|
| 10 Feb 2026 | Ongoing | 8,000,000,000.00 | 10.0% |
Inadeguate budgetary allocation coupled with exchequer delays leading to huge pending bills
|
Given the high impact of the fertilizer subsidy programmee as evidenced in increased food security in the Country, there is need for creation of a special fund to support the programme
|
The demand for the subsidised fertiliser more than doubled
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
No budgetary allocation
|
| 04 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Inadequate budgetary allocation
|
| 04 Nov 2025 | Stalled | 0.00 | 10.0% |
N/A
|
N/A
|
No budgetary allocation
|
| 04 Nov 2025 | Ongoing | 0.00 | 50.0% |
N/A
|
N/A
|
There is strategic government intervention hence the high achievement. High registration of farmers also leading to high uptake
Note: This target is not broken into quarters. It is a continuous exercise
|
| 07 Oct 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Funds not allocated
|
| 07 Oct 2025 | Ongoing | 0.00 | 10.0% |
Lack of funds for the project
|
Exchequer release
|
Funds were not released
|
| 07 Oct 2025 | Ongoing | 0.00 | 50.0% |
N/A
|
N/A
|
Target achieved
|
| 09 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Target Achieved
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 10 Feb 2026 | Ongoing | 15,970,573.00 | 10.0% |
N/A
|
N/A
|
Delayed procurement process due to migration to e-GP
|
| 29 Jan 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Delayed procurement process due to migration to e-GP
|
| 04 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
There were procurement delays and so distribution is currently ongoing for capture of numbers in subsequent quarters
|
| 04 Nov 2025 | Ongoing | 0.00 | 50.0% |
N/A
|
N/A
|
100MT of sunflower procured. Distribution currently ongoing
|
| 08 Oct 2025 | Ongoing | 0.00 | 50.0% |
N/A
|
N/A
|
556 MT of sunflower seeds, 23 MT of Canola seeds, 13 MT of Soya seeds and 13,000 coconut
|
| 08 Oct 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
target achieved
|
| 08 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
270 MT were availed to 51,250 farmers. The 46 MT procured in the third will be distributed in the fourth quarter
|
| 08 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Target will be achieved during the long rains season
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Seedlings will be availed in the next quarter
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 7,765,560.00 | 10.0% |
Limited certified seeds in the country
|
Research institutions to invest more in the production of certified seeds
|
Procurement and distribution of certified cotton seeds will be done in subsequent quarters
|
| 10 Feb 2026 | Ongoing | 7,765,560.00 | 10.0% |
N/A
|
N/A
|
Procurement and distribution of certified cotton seeds will be done in subsequent quarters
|
| 04 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 04 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Procurement and distribution of certified cotton seeds will be done in Q2
|
| 08 Oct 2025 | Ongoing | 0.00 | 10.0% |
No funds
|
SD for agriculture to allocate funds
|
Funds were not allocated
|
| 08 Oct 2025 | Ongoing | 0.00 | 10.0% |
Lack of funds
|
Exchequer release funds for the project
|
Funds were not allocated
|
| 09 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
No funds
|
SD for Agriculture to allocate funds
|
Funds were not allocated
|
| 09 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
No funds
|
SD for Agriculture to provide funds for the program
|
No funds allocated
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Funds were not allocated
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Funds were not allocated
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 06 May 2026 | Ongoing | 8,500,000,000.00 | 50.0% |
Some counties the contractors are slow
|
The counties to do more supervision of the project
|
The construction varies in percentage in different counties. The priority counties are almost complete with percentages ranging from 61%-99%. The phase two counties are also in the progressing on well with the construction
|
| 11 Feb 2026 | Ongoing | 4,175,480,064.00 | 0.0% |
Delay of release of funds
|
Parliament to fast track the pass the bill
|
The county additinal allocation of revenue bill had not been passed thus no funds were released in the 2nd quarter.
|
| 11 Feb 2026 | Ongoing | 0.00 | 21.0% |
Delay in relase of funds
|
Fast tract the passage of county additional allocation of revenue bill.
|
The project is ongoing and the target is 47 counties. However 14 were prioritized as per the IBEC Meeting.. The 14 are almost complete apart from Meru which is through and ready for launch and onboarding investors. This financial year 20 more will be onboarded.
|
| 11 Feb 2026 | Ongoing | 4,334,617,600.00 | 71.0% |
Some counties had no allocation of kshs 250M from their budget
|
Prioritize Funding the remaining counties
|
Target not fully met due budgetary constraints. During the FY 2023/24 we disbursed Kshs. 1.52 Billion Instead of Kshs. 4.5 billion. In the FY 2024/25 the counties implementing CAIPs increased to 21. However during the IBEC meeting it was agreed that we focus on high performing counties in terms of completion rate of 35%. The counties meeting the criteria were 13. By the end of FY 2024/25 we disbursed full amount of Kshs 250 million to 10 counties.
The amount spend is what the 14 counties have so far paid to contractors
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
targetted for in quarter 4
|
| 10 Feb 2026 | Ongoing | 11,152,000,000.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
CAIPS construction is on progress
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
Delays in disbursent of funds
|
Counties to fast tract the construction of CAIPs
|
Not targeted in the quarter
|
| 26 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
budgetary allocation
|
Timely provision
|
Delay in budgetary allocation
|
| 25 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of funds
|
Timely provision of funds
|
Lack of funds
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 10 Feb 2026 | Ongoing | 4,247.00 | 85.0% |
N/A
|
Request for more funding from the Exchequer to cater for the growing demand
|
Target For FY2025/26 Changed from 2.5 Billion to 4 Billion per Quarter. The state Department introduced 'Bridge Loan' Product to cater for demand. This requires provision of more funding
|
| 09 Feb 2026 | Ongoing | 4,177.55 | 50.0% |
N/A
|
N/A
|
Targets surpassed due increased borrowing of the loan products by MSMEs
|
| 08 Oct 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Total amounts disbursed in Q1 and Q2
|
| 06 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
There were no funds from Exchequer to be disbursed to MSMEs in the fourth quarter, the whole amount was offered in quarters 1 and 2
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
The fund received only one Billion from the exchequer which is below the expected target
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Target achieved
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Target achieved
|
| 25 Feb 2025 | Ongoing | 2,500,000,000.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Target achieved
|
| 20 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
On track
|
Target Achieved
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 54,389,752.00 | 100.0% |
Limited Budget to Refurbish and Renovate More CIDCs Serving MSMEs
|
Allocation of more funding(KSh 200 million) for the renovation and Equipping of more CIDCs Countrywide. (Total CIDCs 210).
|
6 CIDCs were equipped or renovated in the Second Quarter; the CIDCs include :
1 in Tharaka Nithi
1 in Uasin Gishu
1 in Kisumu County
1 in Busia County
2 in Meru County
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
Lack of Budget
|
Provision of more Budget for the establishment of the Industrial Parks and Business incubation centers
|
No MSMEs Industrial Parks and Business Incubation Centres were established due to lack of Budget
|
| 24 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Inadequate budgetary allocation
|
| 24 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Inadequate budgetary allocation
|
| 24 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
5 CIDCs identified for equipping in the priority value chains- None were equipped in quarter one due to inadequate budget
|
| 08 Oct 2025 | Ongoing | 0.00 | 50.0% |
N/A
|
Expedite completion of the projects
|
8 CIDCs refurbished to provide decent workspaces and common user facilities provided in the respective value chains.
1. Marimanti
2. Muranga Town
3. Nyamaia CIDC
4. Nandi Hills CIDC
5. Funyula CIDC
6. Ikolomani CIDC
7. Khwisero CIDCs
8. Runyenjes CIDC
13 CIDCs operationalized by equipping with machines in the priority value chains
1. Textile- Kisii CIDC, Saboti CIDC, Moiben CIDC, Kawangware CIDC, Kabujoi CIDC and Homa bay CIDC
2. Construction- Homabay CIDC, Timau CIDC, Kimana CIDC, Funyula CIDC and Khwisero CIDC
3. Dairy –Garrisa town CIDC and Londiani CIDC
|
| 09 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 06 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of funds
|
Exchequer to release the funds for the project
|
No CIDCs were established because of inadequate funds
|
| 06 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
8 CIDCs refurbished to provide decent workspaces and common user facilities provided in the respective value chains.
1. Marimanti
2. Muranga Town
3. Nyamaia CIDC
4. Nandi Hills CIDC
5. Funyula CIDC
6. Ikolomani CIDC
7. Khwisero CIDCs
8. Runyenjes CIDC
13 CIDCs operationalized by equipping with machines in the priority value chains
1. Textile- Kisii CIDC, Saboti CIDC, Moiben CIDC, Kawangware CIDC, Kabujoi CIDC and Homa bay CIDC
2. Construction- Homabay CIDC, Timau CIDC, Kimana CIDC, Funyula CIDC and Khwisero CIDC
3. Dairy –Garrisa town CIDC and Londiani CIDC
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of budget
|
Allocate funds
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 22 Apr 2026 | Ongoing | 43,750,000.00 | 85.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 22 Apr 2026 | Ongoing | 43,750,000.00 | 65.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 22 Apr 2026 | Ongoing | 43,750,000.00 | 75.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 22 Apr 2026 | Ongoing | 43,750,000.00 | 75.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 22 Apr 2026 | Ongoing | 43,750,000.00 | 75.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 11 Feb 2026 | Ongoing | 5,875,000.00 | 4.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
Land dispute
|
There is need for dispute expedited dispute dissolution to unlock the challenge.
|
The two projects in Egerton Nakuru and Samburu Kwale have on going land disputes.
|
| 11 Feb 2026 | Ongoing | 43,750,000.00 | 65.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
Land dispute
|
There is need for dispute expedited dispute dissolution to unlock the challenge.
|
The two projects in Egerton Nakuru and Samburu Kwale have on going land disputes.
|
| 11 Feb 2026 | Ongoing | 43,750,000.00 | 65.0% |
Inadequate budget funding
|
Sufficient Budgetary allocation and timely disbursement
|
Funds for the quarter spent
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 06 May 2026 | Ongoing | 0.00 | 100.0% |
No major challenges
|
N/A
|
N/A
|
| 06 May 2026 | Ongoing | 0.00 | 9.0% |
limited capital and delays in acquisition of inputs
|
Increase capital and hasten the process of acquiring parts
|
N/A
|
| 06 May 2026 | Ongoing | 0.00 | 67.0% |
Less orders were placed
|
Increase visibility of the Company
|
All orders were serviced
|
| 23 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
No target for the quarter
|
| 23 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
No target for the quarter
|
| 23 Apr 2026 | Stalled | 0.00 | 0.0% |
No funding
|
The project be funded when funds are available
|
N/A
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
SD for Industry to expedite the commencement of the Project
|
N/A
|
| 11 Feb 2026 | Ongoing | 33,958,588.00 | 23.0% |
Delays in e-GP
The budget was rationalized downwards
|
Efficiency of e-GP to be improved
|
The target was reviewed downward
During the period under review,20,255 parts were produced against a target of 87,751 parts achieving 23% of the target.
|
| 11 Feb 2026 | Ongoing | 0.00 | 52.0% |
The budget was rationalized downwards
|
N/A
|
Target reviewed to match the budget
|
| 11 Feb 2026 | Ongoing | 0.00 | 9.0% |
The budget was rationalized downwards
|
N/A
|
The target were reviewed downwrds
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 23 Apr 2026 | Ongoing | 0.00 | 0.0% |
No budget allocated to the project hence has made it lagged behind
|
It should be given priority in the next FY 2026/27
|
N/A
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
no budgetary allocation
|
To be prioritized in the next FY 2026/27
|
Yet to commence
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
Lengthy opproval process
|
To be fast track for approval
|
CAB MEMO in place awaiting start of the Project
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
no funds allocated
|
To be conciderd for funding
|
yet to commence
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
No budget allocation
|
To be considered in the next FY 2024/25
|
Yet to commence
|
| 10 Feb 2026 | Ongoing | 0.00 | 10.0% |
The project has not received any funding in the cuurent MTEF period
|
Prioritize this project in the next FY2026/2027 budget.
|
The CAB MEMO on the same has been developed by the technical teams in the state department awaiting futher process and onward submission to the Cabinet for Approval.
|
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
SD EAC to fast track the Cabinet Memo approval and commencement of the project
|
The Target has not been achieved. However, a Concept Note has been developed and validated; and a Cabinet Memo developed, signed by the Cabinet Secretary and forward for signing by the other signatories (i.e. Prime Cabinet Secretary and the Cabinet Secretary for Foreign and Diaspora Affairs, Attorney General and Cabinet Secretary for the National Treasury).
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
The program is to start in FY 2025/26
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 25,000,000.00 | 0.0% |
There are questions regarding the feasibility of New KCC business model that risks affecting implementation of this project
|
The Cabinet to provide directions regarding the future of New KCC to facilitate implementation of the project deliverables.
|
Land was secured in Narok County and the title is under processing. The feasibility of the factory is also ongoing.
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
Project site was not feasible
|
Redesign the project to include only feasible sites
|
The project scope was revised and this site is no longer part of the project
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
The factory site is not feasible
|
Re-design the project with feasible sites and adjust the scope
|
Project scope changed and this site is no longer part of the project
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
The proposed site is not feasible given the current business model of NKCC- establishing more factories is increasing the operational cost of the enterprise.
|
Re-design the project and revise the project concept note
|
Project scope was revised and this site is not part of the project
|
| 11 Feb 2026 | Stalled | 0.00 | 10.0% |
No allocation was made for this project
|
Allocation made for 25/26, and feasibility will be conducted
|
No allocation was made for this project
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
The proposed site is not feasible given the current business model of NKCC- establishing more factories is increasing the operational cost of the enterprise.
|
Re-design the project and revise the project concept note
|
Project scope was revised and this site is not part of the project
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
Project site was not feasible
|
Redesign the project to include only feasible sites
|
The project scope was revised and this site is no longer part of the project
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
Project site was not feasible
|
Project site was not feasible
|
The project scope changed and this is not part of the project
|
| 11 Feb 2026 | Ongoing | 125,000,000.00 | 0.0% |
Land identification process by the County Government is delayed
|
Fast-track the process of land acquisition at Narok County
|
Process of acquiring land delayed and pre-feasibility ongoing
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
The factory site is not feasible
|
Re-design the project with feasible sites and adjust the scope
|
Project scope changed and this site is no longer part of the project
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 21 Apr 2026 | Stalled | 0.00 | 0.0% |
The company is under different ownership
|
No recommentation since the company is no longer under state department for industry
|
East African Portland Cement is no longer under the State Department for Industry
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
No budgetary allocation
|
N/A
|
N/A
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
No funding
|
N/A
|
0
|
| 11 Feb 2026 | Ongoing | 0.00 | 0.0% |
No funding for the project
|
To be considered basing on availability of funds
|
The project was to start in FY 24/25
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
The project not stated
|
| 10 Feb 2026 | Stalled | 0.00 | 0.0% |
N/A
|
N/A
|
No budgetary allocation
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
No funds allocated
|
N/A
|
N/A
|
| 04 Nov 2025 | Stalled | 0.00 | 10.0% |
N/A
|
N/A
|
No budgetary allocation
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 22 Apr 2026 | Stalled | 0.00 | 0.0% |
Lack of budget Provision
|
Provide budget to develop the Marshalling Yard
|
The Project was to establish a Marshalling Yard at the Lamu Port to facilitate export of Livestock, however due to lack of budget provisions the project has stalled
|
| 22 Apr 2026 | Stalled | 0.00 | 0.0% |
Lack of funding
|
Consider the PPP model
|
The Project has not received budget provision for the last four financial years
|
| 22 Apr 2026 | Stalled | 0.00 | 0.0% |
Slow process of privatization and long process of stakeholder engagement.
The facilities is facing vandalism from human and animals.
|
Fast-track the PPP model of engagement
|
The Project has not received funding and process of PPP ongoing. The evaluation of Expression of Interest (EOI) was done in January 2026 but did not yield adequate number of Bids. Re-advertisement done in February 2026 and subsequently Request for Proposal (RFP) done on the 8th of March 2026. The Evaluation of the RFP ongoing.
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
The project could not start due to fiscal space challenge within the State Department
|
Expedite alternative sources of funding especially the PPP model to finalize and operationalize.
|
The project was to establish a Bio-Security/ quarantime facility at Bargani in Lamu County to support the livestock exports at Lamu Port.
The designs for the facility were done but the financial resource limitation stalled the project implementation.
|
| 11 Feb 2026 | Stalled | 0.00 | 5.0% |
The project was affected by lack of budgetary resources
|
PPP Model to be considered in the project
|
The designs for the marshaling yard were completed but the project was affected by non-budgetary provision issues.
|
| 11 Feb 2026 | Ongoing | 0.00 | 56.0% |
The lack of activities at the site has created some issues such as destruction of Bio-security wall by the animals especially (Elephants) and also human interference
|
The process of engaging PPP model was terminated by court, citing lack of public participation. To adhere to the ruling Public participation was redone and procurement process started afresh.
A call for Expression of Interest (EOI) was redone in December 2025.
|
The Finalization and operationalization of Bio secured Livestock Zone established at Bachuma in Taita Taveta County has stalled, however, the PPP Model was introduced.
This is to finalize and operationalize the LEZ.
|
| 11 Feb 2026 | Ongoing | 0.00 | 56.0% |
Court ruling stopped the procurement of a PPP investor/s
|
Re-start the PPP procuring process in line with the court ruling
|
The procurement of PPP Model of investment ongoing
|
| 11 Feb 2026 | Stalled | 0.00 | 0.0% |
The process of establishment was hampered by budget realignment.
|
Consider PPP model to develop and operate
|
The establishment of a bio-secured livestock finishing Disease free holding ground (LEZ)at Bargoni Holding ground has not started. The designs for the LEZ were developed.
|
| 11 Feb 2026 | Ongoing | 3,000,000.00 | 56.0% |
N/A
|
N/A
|
N/A
|
| 10 Feb 2026 | Ongoing | 0.00 | 56.0% |
No funding
|
SD for Livestock Development to expedite alternative sources of funding including PPP
|
• Requests for Proposals (RFP) were sent to the 4 successful bidders in March 2025 and all were responsive and now pending evaluation.
• This is being implemented under the Land Commercialization Initiative (LCI)
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 10 Feb 2026 | Stalled | 0.00 | 0.0% |
N/A
|
Fast track the PCN processing in line with PIM Regulations
|
The implementation of the Project has not started yet
|
| 09 Feb 2026 | Stalled | 0.00 | 0.0% |
N/A
|
N/A
|
No budgetary allocation for FY 2025/26
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
No funds
|
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
|
Project yet to start
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
No funds
|
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
|
Project yet to start
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
No funds
|
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
|
Project yet to commence
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
No funds
|
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
|
Project yet to start
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 21 Apr 2026 | Stalled | 0.00 | 0.0% |
The funds were not allocated for the project
|
The project to be considered when funds are available
|
The project had no allocations for theis finacial year
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
No funding
|
SD for Industry to source for alternative sources of funding including PPP
|
The project is yet to commence
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
No funding
|
SD for Industry to source for alternative sources of funding including PPP
|
Project is yet to commence
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 10 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 29 Jan 2026 | Stalled | 0.00 | 10.0% |
N/A
|
Prioritize funding the project
|
No budget allocation
|
| 04 Nov 2025 | Stalled | 0.00 | 10.0% |
N/A
|
N/A
|
No budgetary allocation
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 20 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
no Budgetary allocation
|
Timely allocation of funds
|
N/A
|
| 20 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
no budgetary allocation
|
Timely provision of funds
|
no budgetary allocation
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
Limited fiscal space
|
Need to engage the National Treasury to understand the importance of the insurance thus re consider and allocate funds to the project
|
Funds not allocated for FY 2025/26
|
| 04 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Targeted for Q2 and Q4
|
| 08 Oct 2025 | Ongoing | 0.00 | 10.0% |
No funds
|
SD for Agriculture to allocate funds towards this program
SD for Agriculture to consider other crops for insurance including Potatoes, Cotton etc.
|
Funds were not allocated
|
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% |
No funds
|
SD for Agriculture to allocate funds towards this program
SD for Agriculture to consider other crops for insurance including Potatoes, Cotton etc.
|
Funds were not allocated
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Funds were not availed
|
N/A
|
Funds were not availed
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Funds were not availed
|
N/A
|
Funds were not availed
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 20 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Funds were not allocated
|
Timely Provision of funds
|
Funds were not allocated
|
| 19 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
no budgetary allocation
|
timely provision of funds
|
funds not provided
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 22 Apr 2026 | Ongoing | 0.00 | 89.0% |
The institution faced breakdown of equipment and a shortfalls of raw materials which limited production capacity.
|
Replacement of the old equipment with modern and more efficient equipment
|
The Institution produce 10 million doses of assorted vaccines against a target of 11.25 million doses indicating a 89% achievement over the quarter.
|
| 22 Apr 2026 | Stalled | 0.00 | 69.0% |
Lack of funding for the projects
|
The institution seeking authority from Treasury to use own revenue to co-fund the project
|
N/A
|
| 22 Apr 2026 | Ongoing | 0.00 | 69.0% |
The Institute encountered breakdown of equipment during the period and shortfall of raw materials which limited production capacity.
|
Replacement of the old and outdated equipment with modern and efficient equipment
|
N/A
|
| 11 Feb 2026 | Stalled | 0.00 | 66.0% |
The delay in Modernization of the KEVEVAPI plant has affected the attainment of vaccines production targets as envisaged in MTP IV.
|
Provide remaining budget of KES 585 Million to finalize the Phase I of the KEVEVAPI Modernization project
|
The project has experience budgetary issues during the MTP IV period.
By 2023/24FY the project expenditure was KES 1,165 Million out of the Project Cost of KES 1,750 Million. The Project requires KES 585 million to finalize the Phase I of Modernization of the plant. The Good Manufacturing Practice Certification (GMP) will increase production of animal vaccine from 45 Million doses to 70 million doses annually and allow access the international markets for the vaccines. However, the production of vaccines is still ongoing at the limited capacity.
|
| 11 Feb 2026 | Ongoing | 0.00 | 89.0% |
The delayed finalization of the Modernization of the KEVEVAPI plant to achieve Good Manufacturing practice limits the production and productivity. Thia is also complicated by reduced demand for vaccines by the Counties.
|
Finalize the KEVEVAPI Modernization project, harmonize and coordinate the national vaccination
|
The Production of assorted animal vaccines was 5.5 Million doses against a target of 9.25 Million doses (60%).
|
| 11 Feb 2026 | Ongoing | 0.00 | 23.0% |
The lack of GMP certification limits the expanded production capacity to achieve the MTP IV targets.
|
Finalize the implementation of the Modernization of the KEVEVAPI Plant which requires a budget of KES 585 Million to finalize Phase I of the project.
|
The production of assorted animal vaccines is affected by the delayed Modernization of the Plant to achieve Good Manufacturing (GMP) certification.
During the quarter 8.4 million doses were produced against a target of 9.25 Million (91%).
|
| 11 Feb 2026 | Ongoing | 0.00 | 29.0% |
The production and distribution is mainly driven by the demands from the counties, when the demand is low the production slows down.
|
Harmonize and schedule regular animal vaccinations across the control to facilitate disease control and management.
|
The Production of assorted animal vaccines in Quarter II was 2.3 million doses against a target of 9.25 Million doses (25% of the target). This is affected by low demand by the counties.
|
| 11 Feb 2026 | Ongoing | 0.00 | 20.0% |
The stalling of the modernization component affected the expansion of vaccines production line
|
Fund the KEVEVAPI Modernization project to attain Good Manufacturing Practice (GMP) certification at a cost of KES 585 Million to improve the efficiency and productivity.
|
The increase of vaccines affected by the National Mass Vaccination campaign
|
| 10 Feb 2026 | Ongoing | 0.00 | 50.0% |
Delay finalization of the modernization of plant to a Good Manufacturing Practice (GMP) certification level
|
Allocate funds and expedite the Modernization project
|
Lack of budget provision delayed the project implementation.
The overachievement in vaccines production can be attributed to National Vaccination campaign on FMD and PPR and exports of vaccines.
|
| 09 Feb 2026 | Ongoing | 0.00 | 31.0% |
Poor vaccination programs lacking harmonized vaccination schedules affecting the vaccine production
|
Finalize the Modernization of the plant to achieve Good Manufacturing Practice (GMP) certification to enhance productivity and access the global animal vaccines markets.
Develop and implement a regular nationally coordinated animal vaccination program.
|
The over achievement in the quarter was attributed to the Mass National Campaign initiated by the Government
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 19 May 2026 | Ongoing | 326,106,249.00 | 75.0% |
i. Resource Constraint persisted and affected implementation of budgets. The rationalization of the budget, occasioned by underperformance of revenue collection and emerging government priorities affected the implementation of programmes.
ii. Delays between approval and fund disbursement due to long internal processes with regards to partnership agreements impact negatively on the implementation Green Climate Fund projects;
iii. Lack of system to identify and track climate finance.
|
i. Mobilization of adequate resources by exploring various funding sources, both domestic and international, and ensuring that resources are channeled to priority projects;
ii. Capacity building at both national and county levels is essential for effective implementation. This includes training and development of human resources, strengthening institutional frameworks, and promoting good governance;
iii. Implementation of an effective robust monitoring and evaluation (M&E) system for tracking progress, identifying challenges, and making necessary adjustments. This system should provide regular feedback on project performance and ensure that resources are used effectively.
|
1. Policy, Institutional and Legal Frameworks developed during 2024/25 FY to facilitate implementation of Green Financeing;
i. Finance Bill 2025 submitted to the National Assembly.
ii. Draft Kenya Green Climate Country Programme 2024- 2027 developed
iii. Draft National Climate Finance Mobilization Strategy 2024-2030 developed
iv. Draft Carbon Market regulations 2025 developed
|
| 19 May 2026 | Ongoing | 326,106,249.00 | 75.0% |
i. Resource Constraint persisted and affected implementation of budgets. The rationalization of the budget, occasioned by underperformance of revenue collection and emerging government priorities affected the implementation of programmes.
ii. Delays between approval and fund disbursement due to long internal processes with regards to partnership agreements impact negatively on the implementation Green Climate Fund projects;
iii. Lack of system to identify and track climate finance.
|
i. Mobilization of adequate resources by exploring various funding sources, both domestic and international, and ensuring that resources are channeled to priority projects;
ii. Capacity building at both national and county levels is essential for effective implementation. This includes training and development of human resources, strengthening institutional frameworks, and promoting good governance;
iii. Implementation of an effective robust monitoring and evaluation (M&E) system for tracking progress, identifying challenges, and making necessary adjustments. This system should provide regular feedback on project performance and ensure that resources are used effectively.
|
1. Policy, Institutional and Legal Frameworks developed during 2024/25 FY to facilitate implementation of Green Financeing;
i. Finance Bill 2025 submitted to the National Assembly.
ii. Draft Kenya Green Climate Country Programme 2024- 2027 developed
iii. Draft National Climate Finance Mobilization Strategy 2024-2030 developed
iv. Draft Carbon Market regulations 2025 developed
|
| 19 May 2026 | Ongoing | 2,384,110.00 | 75.0% |
i. Resource Constraint persisted and affected implementation of budgets. The rationalization of the budget, occasioned by underperformance of revenue collection and emerging government priorities affected the implementation of programmes.
ii. Delays between approval and fund disbursement due to long internal processes with regards to partnership agreements impact negatively on the implementation Green Climate Fund projects;
iii. Lack of system to identify and track climate finance.
|
i. Mobilization of adequate resources by exploring various funding sources, both domestic and international, and ensuring that resources are channeled to priority projects;
ii. Capacity building at both national and county levels is essential for effective implementation. This includes training and development of human resources, strengthening institutional frameworks, and promoting good governance;
iii. Implementation of an effective robust monitoring and evaluation (M&E) system for tracking progress, identifying challenges, and making necessary adjustments. This system should provide regular feedback on project performance and ensure that resources are used effectively.
|
Validation of strategy done. Awaiting approval and sign off.
|
| 19 May 2026 | Completed | 326,106,249.00 | 100.0% |
The process took longer than anticipated.
|
The Policy is ready for implementation.
|
The Policy was completed and approved by Cabinet.
|
| 19 May 2026 | Ongoing | 326,106,249.00 | 40.0% |
The process has taken longer than anticipated due to process delays.
|
Need to fast-track the process to ensure the target is fully achieved.
|
The National Treasury has been nominated for accreditation. Submission of full accreditation documents to the GCF will be concluded in Q4.
|
| 17 Apr 2026 | Completed | 1.00 | 100.0% |
N/A
|
The Strategy is already being implemented.
|
The strategy is completed
|
| 11 Feb 2026 | Completed | 4,729,750.00 | 100.0% |
i. Resource Constraint persisted and affected implementation of budgets. The rationalization of the budget, occasioned by underperformance of revenue collection and emerging government priorities affected the implementation of programmes.
ii. Delays between approval and fund disbursement due to long internal processes with regards to partnership agreements impact negatively on the implementation Green Climate Fund projects;
iii. Lack of system to identify and track climate finance.
|
i. Mobilization of adequate resources by exploring various funding sources, both domestic and international, and ensuring that resources are channeled to priority projects;
ii. Capacity building at both national and county levels is essential for effective implementation. This includes training and development of human resources, strengthening institutional frameworks, and promoting good governance;
iii. Implementation of an effective robust monitoring and evaluation (M&E) system for tracking progress, identifying challenges, and making necessary adjustments. This system should provide regular feedback on project performance and ensure that resources are used effectively.
|
Policy approved by Cabinet to facilitate implementation of Green Financing;
i. Draft Kenya Green Climate Country Programme 2024- 2027 developed
ii. Draft Carbon Market regulations 2025 developed
|
| 11 Feb 2026 | Completed | 4,729,750.00 | 100.0% |
No challange experienced.
|
i. Mobilization of adequate resources by exploring various funding sources, both domestic and international, and ensuring that resources are channeled to priority projects;
ii. Capacity building at both national and county levels is essential for effective implementation. This includes training and development of human resources, strengthening institutional frameworks, and promoting good governance;
iii. Implementation of an effective robust monitoring and evaluation (M&E) system for tracking progress, identifying challenges, and making necessary adjustments. This system should provide regular feedback on project performance and ensure that resources are used effectively.
|
Strategy finalized and signed off for implementation.
|
| 10 Feb 2026 | Ongoing | 1,338,240,000.00 | 100.0% |
There is a significant financing gap to meet the Country's Nationally Determined Contributions (NDCs) of USD 62 Billion by 2030.
|
Government to push for higher, more consistent allocations from County budgets to address the significant gaps.
|
Target Surpassed.
The Fund Value is based on the book value of the County Climate Resilience Investments. Counties allocated 1.5% -2% of development budget to the County Climate Change Funds
|
| 10 Feb 2026 | Ongoing | 1,338,240,000.00 | 100.0% |
No challange encountered
|
All Counties to be allocated more funds towards climate smart initiatives.
|
Target surpassed
All 47 Counties met the minimum performance conditions, an eligibility criteria for funding
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 30 Apr 2026 | Ongoing | 0.00 | 17.0% |
N/A
|
N/A
|
N/A
|
| 21 Apr 2026 | Ongoing | 388,196,768.84 | 24.0% |
Heavy rainfall experienced in the last 2 months continues to halt backfilling works on Block B2
|
An updated resourced program of works required
|
N/A
|
| 25 Feb 2026 | Ongoing | 0.00 | 50.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 1,045,675,844.00 | 5.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 1,045,675,844.00 | 5.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 567,768,044.00 | 0.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 206,978,868.00 | 15.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| 25 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Construction Works Ongoing
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
Proposed to be implemented under water sector climate financing and Designs are ready.
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
Proposed to be implemented under water sector climate financing.The project is under Financial Negotiations and awaiting closure between the National Treasury and the Exim Bank of China
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
Proposed to be implemented under water sector climate financing (PPP).Designs Ready
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
The project has detailed designs and it is ready for implementation.
To be funded under EPC&F
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
Lack of funds
|
Expedite provision of funds.
|
Still awaiting funding. Designs Ready.
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
Lack of funds
|
Expedite provision of financing for the project.
|
Proposed to be implemented under water sector climate financing.Preliminary Design Ready
|
| 03 Mar 2026 | Ongoing | 0.00 | 10.0% |
lack of funds
|
N/A
|
Still awaiting funds.Project meant to serve communities in Soy, Likuyani and Tongaren Constituencies.
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
Lack of funds
|
N/A
|
Still awaiting funds.Ready designs & feasibility
|
| 03 Mar 2026 | Ongoing | 0.00 | 10.0% |
Lack of funds
|
N/A
|
N/A
|
| 03 Mar 2026 | Ongoing | 0.00 | 10.0% |
Lack of funds
|
N/A
|
Still awaiting funding.Project meant to serve communities in Mt Elgon, Sirisia, Kabuchai and Kanduyi Constituencies in Bungoma County.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
FATs (Factory acceptance tests) completed, shipping of materials ongoing. Line Construction has commenced; Project closure is expected by September 2026 for KOSAP Mini grids. Contract preparation ongoing for GoK funded Mini grids.
|
| 07 May 2026 | Completed | 1.00 | 0.0% |
N/A
|
N/A
|
No target for this quarter
|
| 07 May 2026 | Ongoing | 1.00 | 8.0% |
Implementation affected by shortage of materials caused by delayed procurement of material.
|
N/A
|
Target not achieved.
|
| 07 May 2026 | Ongoing | 1.00 | 3.0% |
Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
|
Fast track disbursment of funds
|
KPLC’s Q3 target was 253. The
achievement was 77.
REREC’s Q3 target was 238. The
achievement was 38. Implementation
affected by
|
| 07 May 2026 | Ongoing | 1.00 | 94.0% |
Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.
|
N/A
|
Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC
|
| 07 May 2026 | Ongoing | 1.00 | 24.0% |
Kenya Power’s achievement affected by delayed funding.
Implementation by REREC affected by shortage of materials caused by delayed procurement of material.
|
Fast track disbursment of funds.
|
Kenya Power installed 636 while REREC installed 260 in Q3.
|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
To be reported in Q4
|
| 07 May 2026 | Ongoing | 0.00 | 0.0% |
Affected by delays in materials but the issue is now sorted
|
N/A
|
To be reported in Q4
|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
Pre commissioning tests on going for kimuka substation
|
| 18 Feb 2026 | Ongoing | 5,726,700,000.00 | 81.0% |
Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
|
Promote local capacity in manufacturing of the materials.
Exemption from eGP on procurement of the materials.
|
Target not achieved.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 98,138,746.00 | 0.0% |
Redesigning of the implementation strategy of the project to include the private sector players
|
The State Department to develop a framework for private sector involvement in the project.
Undertake Continuous stakeholder engagement.
|
•Installation of 2-two tonne Clean Cooking Gas bullets and associated infrastructure was done in Kitui Teachers Training College, Kitui County during the Energy Week.
• There was a change in the project implementation strategy following the issuance of a directive to have the private sector players involved.
• Expression of interest (EOI) for supply, delivery, and commissioning of CCG installations in Institutions of public learning to prequalify contractors who will provide CCG in other public institutions of learning undertaken where to 25 firms were prequalified.
|
| 18 Feb 2026 | Ongoing | 63,534,651.00 | 0.0% |
Delays in the development of a robust distribution framework by the NOCK.
|
State Department to fast track the finalization of the distribution framework for effective roll out countrywide.
|
Beneficiaries in Kitui County were identified; and distribution plan for roll out in Kitui County during the Energy Week developed. Actual distribution to be done in the second quarter.
|
| 18 Feb 2026 | Ongoing | 43,220,314.00 | 0.0% |
Redesigning of the project implementation strategy to incorporate the private sector.
|
Development of Framework to incorporate the private sector.
|
Following the directive to have the private sector involved, expression of interest (EOI) for supply, delivery and commissioning of CCG installations in institutions to prequalify contractors who will provide CCG in public institutions of learning is commenced.
|
| 18 Feb 2026 | Ongoing | 87,953,262.00 | 48.0% |
The mandate of distributing the Cylinders was transferred to the National Oil Corporation of Kenya (NOCK). The corporation is in the process of mapping and developing a new distribution framework.
|
State Department to fast track the development of a robust distribution framework by NOCK to facilitate effective distribution of the cylinders.
|
24,000 6Kg LPG cylinders and associated accessories were distributed in eight (8) constituencies (3000 cylinders per constituency) in Kitui County. This was made possible due to the celebrations of the Energy Week held during Mashujaa Day
|
| 18 Feb 2026 | Ongoing | 23,470,195.00 | 0.0% |
The budgetary allocation only allowed for installation of the infrastructure in 20 institutions.
|
prioritize the project to attract more funding.
|
Procurement of works for installation of the infrastructure in the identified 20 beneficiary institutions completed and and contracts signed; and Environmental and Social Impact Assessment for the institutions conducted and reports submitted to NEMA for approval.
|
| 18 Feb 2026 | Ongoing | 278,000,000.00 | 0.0% |
Delays in the development of a robust distribution framework by the corporation.
|
NOCK to finalize the development of a distribution framework.
|
The assets (6kg cylinders, burners, grills, 2-burner cook stoves and flex rubber hosepipes) were transferred to the National Oil Corporation of Kenya (NOCK) for distribution. The project's scope was expanded to cover LPG reticulation in the affordable housing project where 1,080 housing units were reticulated In FY 2024/25 at Mukuru kwa Njenga in the pilot phase.
|
| 18 Feb 2026 | Ongoing | 82,000,000.00 | 0.0% |
Lack of a distribution plan at the National Oil Corporation of Kenya
|
NOCK to develop a robust distribution framework.
|
The assets: 6kg cylinders, burners, grills, 2-burner cook stoves and flex rubber hosepipes were transferred to NOCK.
|
| 18 Feb 2026 | Ongoing | 90,000,000.00 | 0.0% |
Underachievement was due to Low budgetary allocation.
|
Prioritize the project in the next budget cycle to attract more funding.
|
The pilot phase is 100% complete.
Installation of the LPG infrastructure at Kenya Coast national Polytechnic completed.
|
| 18 Feb 2026 | Ongoing | 35,000,000.00 | 0.0% |
Changes in the project implementation strategy to have NOCK as implementing agency for the project.
|
The State Department to fast track the transfer of the assets to NOCK for subsequent distribution.
|
Transfer of the assets (6kg cylinders, burners, grills, 2-burner cook stoves and flex rubber hosepipes) to National Oil Corporation of Kenya for distribution done.
|
| 18 Feb 2026 | Ongoing | 39,000,000.00 | 8.0% |
Underachievement was due to low budgetary allocations.
|
Prioritize the project in the next budget cycle to increase the number of institutions.
|
The pilot phase is 98% complete.
Installation of the LPG infrastructure have been completed in 19 institutions. Completion is pending only at the Kenya Coast National Polytechnic, Kwale Campus where the kitchen is still under construction.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 21 Apr 2026 | Ongoing | 10,000,000.00 | 82.0% |
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
|
Fast tracking of implementation by applying measure to mitigate against the delays.
|
4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
|
| 18 Nov 2025 | Ongoing | 0.00 | 50.0% |
The under-performance is due to the slow start of the financial year.
|
N/A
|
3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
|
| 08 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Limited budgetary provision
|
Increase budgetary allocation
|
underperformance due to delay on-boarding of contractors
|
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of on-boarding contractors
|
Fast-track contractor engagement
|
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The underperformance is due to delayed disbursement of funding
|
N/A
|
Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The underperformance is due to delayed disbursement of funding.
|
N/A
|
350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Inadequate funding
|
N/A
|
A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 21 Apr 2026 | Ongoing | 0.00 | 100.0% |
Connectivity is based on the establishment of the digital hubs
|
Fast tracking establishment of the digital hubs to facilitate connectivity
|
156 digital hubs have been connected. Assembly of devices is ongoing and will be completed by June 2026. The first batch of 3,000 devices will be ready for deployment from 1st May 2026
|
| 21 Apr 2026 | Ongoing | 5,000,000.00 | 100.0% |
N/A
|
The project is on course and adherence to the timelines is key.
|
Recruitment of 400 PDTP Interns was completed and training is ongoing in collaboration with partners.
|
| 17 Feb 2026 | Ongoing | 29,000,000.00 | 100.0% |
N/A
|
N/A
|
Target achieved. The interns were recruited, inducted and deployed to MCDAs. Currently the interns are undergoing specialized certification training.
|
| 17 Feb 2026 | Ongoing | 116,000,000.00 | 100.0% |
N/A
|
N/A
|
As per the MTP IV, the target is to train 100 annually. The programme target was revised to onboard 400 Interns annually from 100 indicated in the National Indicator Handbook.
|
| 17 Feb 2026 | Ongoing | 102,300,000.00 | 100.0% |
N/A
|
N/A
|
As per the MTP IV, the target is to train 100,000 annually. The target was
|
| 17 Feb 2026 | Ongoing | 76,000,000.00 | 100.0% |
N/A
|
N/A
|
As per the MTP IV, the target is to equip 86 TVETs in 2023/24. Q1-Q4, 176 TVETs were equipped. The high
|
| 17 Feb 2026 | Ongoing | 340,737,906.00 | 50.0% |
N/A
|
N/A
|
A total of 88 digital hubs have been completed awaiting connection to hotspots.
|
| 17 Feb 2026 | Ongoing | 197,018,511.00 | 10.0% |
N/A
|
N/A
|
Nine (9) institutions (2-TVETs – Siaya and Kiambu digital hubs, 5 Schools-Katani DEB, Riyabe Mixed, Waitua Sec, Kagonye Boys Sec, and Karara Sec, 2-MDAs) – Machakos County Commissioners Office and Eastern Region Commissioners Office were equipped with 155 VDIs.
|
| 17 Feb 2026 | Ongoing | 51,200,000.00 | 85.0% |
N/A
|
N/A
|
45,949 youth were trained through Ajira program and 1,471 youths trained through the Jitume Enablement Programme.
|
| 17 Feb 2026 | Ongoing | 60,750,000.00 | 10.0% |
N/A
|
N/A
|
Recruitment of 400 PDTP Interns completed and training to commence in Quarter 3 and continue through the FY.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 17 Feb 2026 | Ongoing | 18,259,900.00 | 10.0% |
N/A
|
N/A
|
Low-level surveys for Phase V are ongoing, with connectivity scheduled for implementation in the fourth quarter.
|
| 17 Feb 2026 | Stalled | 28,700,000.00 | 10.0% |
The project has faced contractual issues due to a tax dispute that is being resolved
|
Resolve tax dispute for the project to progress
|
The project has faced contractual issues due to a tax dispute that is being resolved
|
| 17 Feb 2026 | Ongoing | 28,000,000.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 18 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Low level survey for Phase V to begin in quarter two. Connection to be done in quarter four.
|
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Tax disputes
|
Expedite tax dispute resolution
|
The project has faced contractual issues due to a tax dispute that is being resolved. This informed the nil target in Q3.
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Last-mile internet connectivity has been undertaken in Kenya Medical Training Colleges (KMTCs), Hospitals, Police Stations, and Government Offices in Counties to enhance internet.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 17 Feb 2026 | Ongoing | 203,456,212.00 | 10.0% |
N/A
|
N/A
|
Purchase of Systems in procurement stage, through KDEAP funding.
|
| 17 Feb 2026 | Ongoing | 480,000,000.00 | 100.0% |
N/A
|
N/A
|
The over achievement was due to increased demand for online services and Government commitment towards
|
| 17 Feb 2026 | Ongoing | 203,456,212.00 | 10.0% |
N/A
|
N/A
|
Procurement is ongoing
|
| 17 Feb 2026 | Ongoing | 203,456,212.00 | 50.0% |
bulkiness of the records
|
we need to revise the output
|
N/A
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Under-performance is due to delayed procurement.
|
| 18 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Under-performance is due to delayed procurement.
|
| 09 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Delayed procurement of ICT Systems under the Kenya Digital Economy Acceleration Project (KDEAP).
|
Fastrack procurement of ICT Systems under the Kenya Digital Economy Acceleration Project (KDEAP).
|
The target has not been achieved due to delayed procurement of ICT Systems under the Kenya Digital Economy Acceleration Project (KDEAP).
|
| 09 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Delays were occasioned by the non-provision of budget.
|
Prioritize funding for the project
|
The project is still in contractual stage awaiting to commence in the FY 2025/2026. The delays were occasioned by the non-provision of budget.
|
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
The target has not been achieved due to delayed procurement of ICT Systems under the Kenya Digital Economy Acceleration Project (KDEAP).
|
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
E-citizen contract moved from ICTA to the Ministry of Interior and Coordination of National Government
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 21 Apr 2026 | Ongoing | 0.00 | 96.0% |
N/A
|
Finalization of the pending activities to allow for completion and operationalization of the Centre.
|
The Disaster Recovery Data Centre is at 96% completion level. System acceptance, handover and customer onboarding and service activation planned
|
| 21 Apr 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
Project completed in FY 2024/25
|
| 21 Apr 2026 | Ongoing | 0.00 | 0.0% |
Project slowed down due to unavailability of funds.
|
Review of the Project Concept Note to all for project funding through the PPP framework
|
The project feasibility study will be updated in Q4 to reflect the conditions of the project and enable the KoTDA together with the PPP Directorate, to competitively advertise the project.
|
| 21 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
The Export-Import Bank of Korea commenced review of the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing and requested completion of the Kenya-AIST project closure before progressing the Digital Media Centre project.
|
| 21 Apr 2026 | Ongoing | 0.00 | 76.0% |
The project stalled at 76% level of completion due to funding challenges.
|
Project Concept Note revised to reflect updates in the project scope and subsequently submitted to the National Treasury for review and consideration for funding.
|
KoTDA revised the Project Concept Note to reflect updates in the project scope and subsequently submitted the revised version to the National Treasury for review and consideration.
|
| 05 Mar 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
The Export-Import Bank of Korea is in the process of reviewing financing framework for the Project with an aim of transitioning project financing model from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing
|
| 24 Feb 2026 | Completed | 0.00 | 96.0% |
N/A
|
N/A
|
The Disaster Recovery Data Centre is at 96 percent completion, with system acceptance, handover, customer onboarding, and service activation scheduled for Q3 and Q4 of FY 2025/26.
|
| 17 Feb 2026 | Ongoing | 2,718,532,083.00 | 84.0% |
Delays in Exchequer release
|
Fast track the release of Exchequer
|
N/A
|
| 17 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Target achieved
|
| 17 Feb 2026 | Completed | 13,800,205.00 | 85.0% |
N/A
|
N/A
|
Project completed in FY 2024/25)
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Currently JKIA terminal building optimization is being undertaken
|
| 25 Feb 2026 | Ongoing | 43,005,971.00 | 10.0% |
Delays due to E-GP system for procurement process
|
E-GP Exception to accelerate the procurement process
|
This indicator expressed as an absolute number is not the most appropriate measure for Air Navigation Services (ANS), as ANS performance is assessed based on the availability of navigation and communication systems in accordance with ICAO Standards and Recommended Practices (SARPs), which require a minimum availability of 97% to ensure there is no loss of service time (in seconds); accordingly, the appropriate Key Performance Indicator (KPI) is the percentage availability of navigation systems, against which we achieved 98%, exceeding the ICAO requirement.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
Land issues
|
Land is not available within the airport, it is recommended that a suitabe site is identified for acquisition
|
Project not scheduled to commence in FY 2025/26 due to non-allocation of land
|
| 24 Feb 2026 | Ongoing | 128,845,939.00 | 10.0% |
N/A
|
N/A
|
5% was allocated to JKIA masterplan - the Interim Report has been submitted by the consultant
10% was allocated to detailed design and Procurement
85% was allocated to actual construction
|
| 23 Feb 2026 | Completed | 0.00 | 85.0% |
N/A
|
N/A
|
Construction completed. The Tower building was handed over to KCAA on 15th December 2025.
|
| 18 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
KCAA and KAA are still in talks regarding the suitable location
|
| 18 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
KCAA and KAA are still in talks regarding the suitable location
|
| 18 Nov 2025 | Ongoing | 0.00 | 85.0% |
N/A
|
N/A
|
It is scheduled to be launched in December, 2025
|
| 18 Nov 2025 | Ongoing | 0.00 | 85.0% |
N/A
|
N/A
|
On track of completion
|
| 18 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Different equipment are tracked per individual contract eg radar equipment are tracked by contract
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 06 May 2026 | Ongoing | 0.00 | 0.0% |
• Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection.
|
• Coordination with the National Land Commission.
|
N/A
|
| 06 May 2026 | Ongoing | 0.00 | 0.0% |
• Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection.
|
• Coordination with the National Land Commission.
|
N/A
|
| 25 Feb 2026 | Ongoing | 78,855,360.00 | 10.0% |
-none
|
-none
|
Ongoing
|
| 25 Feb 2026 | Ongoing | 148,539,332.00 | 10.0% |
-none
|
-none
|
Delayed payments causing slowdown in progress.
|
| 25 Feb 2026 | Ongoing | 26,352,746.00 | 10.0% |
-none
|
-none
|
Ongoing
|
| 25 Feb 2026 | Ongoing | 108,299,228.00 | 10.0% |
-none
|
-none
|
Ongoing
|
| 23 Feb 2026 | Ongoing | 79,320,240.00 | 10.0% |
-none
|
-none
|
Ongoing
|
| 23 Feb 2026 | Ongoing | 118,439,346.00 | 10.0% |
-none
|
-none
|
Ongoing
|
| 23 Feb 2026 | Ongoing | 107,703,779.00 | 10.0% |
-none
|
-none
|
Ongoing
|
| 23 Feb 2026 | Ongoing | 0.00 | 10.0% |
-none
|
-none
|
Slow execution of works by the contractor
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 18 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
As part of project conceptualization, a Project Concept Note has been developed and forwarded to the National Treasury for approval in line with PIM regulations, 2022. Awaiting the National Treasury approval to progress to the next steps.
|
| 18 Feb 2026 | Ongoing | 3,571,488,412.75 | 100.0% |
N/A
|
N/A
|
N/A
|
| 17 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 17 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
• Concept Note prepared and submitted to National Treasury for approval
|
| 17 Feb 2026 | Ongoing | 0.00 | 0.0% |
• Resettlement of PAPs
• Delay in getting concurrence from JICA
• Delay in payment of advance payment
|
• Continuous engagements with the Ministry of Roads & Transport and the National Treasury to ensure funding availability throughout project implementation period.
• Ensure adherence to the implementation schedule
|
• Preliminary studies for 3 additional berths at Lamu Port are planned for FY 2026/2027
|
| 17 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
• Project has not commenced
• Feasibility study has been completed.
• KPA has written to JICA to commence negotiations for financing through National Treasury
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Not commenced.
Preliminary studies for 3 additional berths at Lamu Port are planned for FY 2026/2027.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Container Terminal 2: Concept note developed awaiting approval.
The Authority has written to JICA to commence negotiations for financing through National Treasury
Berth 19: Contract for civil works signed in March 2025. The Contractor is in the process of mobilizing for work.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
Technical & Engineering Challenges in demolishing the existing KOT I
|
The need to undertake through studies prior to commencement of the project.
|
Ongoing
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
The project is progressing to the procurement stage for private partners after the approval of the feasibility study.
|
The project is progressing to the procurement stage for private partners after the approval of the feasibility study.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 0.00 | 5.0% |
N/A
|
N/A
|
Lowaat Dam (384MCM) Privately Initiated Proposals received and at EOI Phase.
Detailed Feasibility Study and Designs initiated
|
| 25 Feb 2026 | Ongoing | 123,636,952.00 | 100.0% |
Low uptake/low production in the existing 10,000 acres due to siltation in the sump well
|
Desilting of the sump well by the Private Party
|
The Concessional agreement provides for production in the existing 10,000 acres and development of irrigation infrastructure in another 10,000 acres.
The private party (SELU) has planted 1,500 acres and harvesting is scheduled to commence in Q2.
Bush clearing has been done on 1,000 acres for phase 2
|
| 25 Feb 2026 | Ongoing | 0.00 | 10.0% |
Termination of PIP PPP Process
|
N/A
|
Targeted acreage premised on construction of Galana Dam and a 62KM Canal at an estimated cost of KShs 39 Billion.
PIP Evaluation concluded that project is not suitable for PPP framework – very high water tariff. PPP process has been terminated.
|
| 25 Feb 2026 | Ongoing | 40,000,000.00 | 24.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Ongoing | 200,000,000.00 | 22.0% |
N/A
|
N/A
|
3 schemes expanded (Lokubae (190)and Katilu (200)– 390 acres, Lokapel – 100 acres)
|
| 25 Feb 2026 | Ongoing | 80,000,000.00 | 25.0% |
Irrigation scheme and projects within Turkana county are affected by heavy flooding, heavy siltation, Prosopis Infestation and unstable river banks which require frequent rehabilitation.
|
Funding for Climate proofing of Lokubae and Katilu Clusters
|
Expansion of the Lokubae, Elelea, Morulem schemes not likely to be realized due to insufficient allocations.
|
| 24 Feb 2026 | Ongoing | 0.00 | 15.0% |
N/A
|
N/A
|
Galana Dam PIP Evaluated
|
| 24 Feb 2026 | Ongoing | 0.00 | 5.0% |
N/A
|
N/A
|
Galana PIP Received
|
| 24 Feb 2026 | Ongoing | 0.00 | 10.0% |
PIP Evaluation concluded that project is not suitable for PPP framework – very high water tariff - and the
PPP process was terminated.
|
N/A
|
Targeted acreage premised on construction of Galana Dam and a 62KM Canal at a estimated cost of KShs 39 Billion.
Bilateral Financing Framework between Kenya and UAE concluded and signed on 8th May, 2025.
Procurement of EPC contractor is ongoing – evaluation stage
|
| 24 Feb 2026 | Ongoing | 0.00 | 17.0% |
Inadequate Financial Resources
|
N/A
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 15 Apr 2026 | Ongoing | 0.00 | 0.0% |
None. Interns are posted only twice in the Financial Year
|
N/A
|
The interns were posted during the first quarter with effect from 1st July,2025. No Intern was posted during the second quarter
|
| 25 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Ongoing | 0.00 | 85.0% |
N/A
|
N/A
|
Target achieved. The 107,831 more CHPs were bought on board This was attributed to the increased number of CHPs engaged at the counties.
|
| 25 Feb 2026 | Ongoing | 1,303,075,741.25 | 85.0% |
N/A
|
N/A
|
Target surpassed. This was attributed to more admissions and graduants form the training institutions.
|
| 25 Feb 2026 | Ongoing | 1,303,075,741.00 | 10.0% |
N/A
|
N/A
|
Target not achieved. The posting of medical interns is done once annually and was done in Q2.
|
| 25 Feb 2026 | Ongoing | 1,167,582,778.25 | 100.0% |
N/A
|
N/A
|
Target achieved in Q1
|
| 25 Feb 2026 | Ongoing | 1,302,111,803.00 | 79.0% |
The delay in signing of the MOU.
|
refer to verification report
|
The low target was set before the signing of the MOU. Following the conclusion of the MOU, MOH was able to surpass this issue target.
|
| 25 Feb 2026 | Ongoing | 865,910,126.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
The government has placed 8,550 UHC staff on permanent and pensionable terms.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 16 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
The interns were posted during the first quarter with effect from 1st July,2025. No Intern was posted during the
|
| 16 Apr 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Target achieved. All registered CHPs were facilitated in the quarter.
|
| 25 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
Target not achieved. This is due to inadequate funds for affected implementation
|
N/A
|
N/A
|
| 25 Feb 2026 | Ongoing | 808,732,500.00 | 85.0% |
N/A
|
Partnerships and collaborations enable achievement of set targets
|
Target surpassed due to devepoment partners support
|
| 25 Feb 2026 | Ongoing | 190,000,000.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Ongoing | 190,000,000.00 | 100.0% |
Further investigation
|
Refer to the verification report
|
The target requires further investigation
|
| 25 Feb 2026 | Ongoing | 190,000,000.00 | 100.0% |
Investigate further
|
Refer to the verification report
|
The target requires further investigation
|
| 25 Feb 2026 | Ongoing | 190,000,000.00 | 100.0% |
Investigate further
|
Refer to verification report
|
The target requires further investigation
|
| 25 Feb 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
The Echis system was developed and successfully rolled out across all 47 counties in Kenya in FY 2024/25, providing a standardized platform for community health data management and reporting.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 22,374,922,440.00 | 20.0% |
N/A
|
N/A
|
N/A
|
| 25 Feb 2026 | Ongoing | 32,815,641,991.00 | 49.0% |
1. Registration to the Social Health Insurance Fund (SHIF)
2. registration in Kenya faces significant challenges, primarily driven by technical glitches with the Afya Yangu portal, low public awareness, and reluctance in the informal sector. Other major obstacles include registration errors, missing dependent data, and high, inconsistent, or un-affordable premiums, which have led to service disruptions and public, or private, health facility, challenges
|
1. Promotion of Registration: Use USSD code *147# or visit www.sha.go.ke and all targeted registration by the government.
2. Dependents must be linked to existing covers: Requirement to manually link spouses and children (using birth certificates/marriage certificates) on the portal, or they will not be covered.
3. Means Testing: If unemployed, complete the "Means Testing" section on the portal to qualify for government-subsidized premiums.
4. Expansion of Benefits Package: SHA covers primary (Level 2/3), inpatient, outpatient, mental health, and emergency care.
5. Employer Obligations: Employers must register and remit contributions by the 9th of every month.
|
By 31st December 2025, 27 million Kenyans had been registered to SHA representing approximately 48.75% of the total population. and have been able to access the essential health services as per the gazette benefits package and tariffs of 20th September 2024.
As of December 2025, approximately 4.8 million people were active contributors to the fund. This includes about 4 million salaried contributors and 890,000 contributors in the informal sector.
5.48 million people had undergone the means testing process to determine their appropriate contribution levels.
|
| 25 Feb 2026 | Ongoing | 32,815,641,991.00 | 46.0% |
Social Health Authority (SHA) registration in Kenya faces significant challenges, primarily driven by technical glitches with the Afya Yangu portal, low public awareness, and reluctance in the informal sector. Other major obstacles include registration errors, missing dependent data, and high, inconsistent, or un-affordable premiums, which have led to service disruptions and public, or private, health facility, challenges
|
1. Promotion of Registration: Use USSD code *147# or visit www.sha.go.ke and all targeted registration by the government.
2. Dependents must be linked to existing covers: Requirement to manually link spouses and children (using birth certificates/marriage certificates) on the portal, or they will not be covered.
3. Means Testing: If unemployed, complete the "Means Testing" section on the portal to qualify for government-subsidized premiums.
4. Expansion of Benefits Package: SHA covers primary (Level 2/3), inpatient, outpatient, mental health, and emergency care.
5. Employer Obligations: Employers must register and remit contributions by the 9th of every month.
|
By 31st December 2025, 27 million Kenyans had been registered to SHA representing approximately 48.4% of the total population. and have been able to access the essential health services as per the gazette benefits package and tariffs of 20th September 2024
|
| 25 Feb 2026 | Ongoing | 29,061,322,010.00 | 30.0% |
Low public enrollment to the program
|
Intensify Public outreach on the program
|
Target not achieved
|
| 25 Feb 2026 | Ongoing | 29,061,322,010.00 | 30.0% |
Slow uptake
|
Intensify rollout plan
|
Target not achieved
|
| 25 Feb 2026 | Ongoing | 29,061,322,010.00 | 30.0% |
Slow uptake
|
Re strategize rollout plan
|
Target not achieved
|
| 25 Feb 2026 | Ongoing | 29,061,322,010.00 | 30.0% |
Negative public perception
|
Intensify public sensitization
|
19.3 Million Kenyans had been registered to SHA by 30th June 2025, representing approximately 35% of the total population. The same have been able to access the essential health services as per the gazette benefits package and tariffs of 20th September 2024
|
| 24 Feb 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
The consolidation of Health Insurance schemes was done with the enactment of the Social Insurance Act 2023 which An an Act of Parliament to establish the framework for the management of social health insurance; to provide for the establishment of the Social Health Authority.
|
| 24 Feb 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
A health benefits package (HBP) is a defined set of essential, evidence-informed health services—including consultations, medication, inpatient/outpatient care, and diagnostics—guaranteed to eligible individuals. These packages aim to provide financial protection and equitable access to quality care, often structured around primary healthcare and preventive services, such as the Social Health Authority (SHA) in Kenya.
Common Components of Health Benefit Packages
1. Primary & Outpatient Care: Consultations, diagnostics, laboratory tests, and medicines.
2. Inpatient Services: Hospital accommodation, nursing care, and surgery (Levels 4-6).
3. Maternity & Newborn Care: Prenatal, delivery, and postnatal care.
4. Specialized Services: Chronic disease management (HIV, TB, diabetes), imaging (X-rays, ultrasound), and physiotherapy.
5. Preventive Services: Vaccinations, counseling, and health education.
|
| 24 Feb 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
The Benefits Package and Tariffs Advisory Panel (BPTAP) was established in Kenya via Gazette Notice No. 5044 of 23rd April 2025 to guide the Social Health Authority (SHA) in developing evidence-based, sustainable health benefits and tariffs. This 11-member panel (plus joint secretaries) advises on Social Health Insurance (SHI) regulations, conducting Health Technology Assessments (HTA) to ensure equitable, affordable care for UHC.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 28 Apr 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Increased outreach campaign on inclusive education and disability mainstreaming has ensured more PWLD learners in schools
|
| 28 Apr 2026 | Ongoing | 0.00 | 50.0% |
Lack of enough funds to fully fund capitation of learners in LCBS
|
Allocate enough resources
|
Target achieved.
More learners enrolled due to efforts to enroll out of school children (OOSC)
|
| 28 Apr 2026 | Ongoing | 0.00 | 70.0% |
Inadequate budget allocation leading each learner receiving lower amount than the expected of Ksh 22,244.
|
The National treasury to disburse all the money for capitation
|
The deviation from the initial target was due to change of the education system from 8-4-4 to CBC and as a result there were no learners in Q3 and Q4
|
| 28 Apr 2026 | Ongoing | 0.00 | 50.0% |
Access data from counties is not well coordinated
|
Council of Governors representative to be sending quarterly reports to MOE on pre school learners enrolled
|
Learners enrolled due to efforts by NACONEK and MoE and support from the world bank
|
| 28 Apr 2026 | Ongoing | 0.00 | 50.0% |
Not enough funds to meet the target for all the school calendar days
|
Allocation of more resources enough to feed all learners
|
More learners to be fed in second term of 2026
|
| 28 Apr 2026 | Ongoing | 0.00 | 85.0% |
Lack of enough funds to fully develop the integration guidelines. And implement in other counties.
|
Allocate funds for the programme to be implemented in other counties
|
Target not achieved. The 4 counties are the ones that were implementing since FY 2022/23.
This was funded by UNICEF. Since the funding ended there no plans to implement the programme in other counties
|
| 28 Apr 2026 | Ongoing | 0.00 | 0.0% |
Delayed exchequer release led to delay in starting of the projects
|
There is need of disbursing the funds in time
|
Target not achieved.
Target not achieved
54 schools have received an amount totaling to 0.556B identification of project type and approval of authority to utilize funds ongoing.
|
| 28 Apr 2026 | Ongoing | 0.00 | 0.0% |
Budgetary constraints
|
Prioritize the project
|
Target not achieved due to lack of funds.
|
| 28 Apr 2026 | Ongoing | 0.00 | 0.0% |
Budgetary constraints
|
Prioritize the project
|
Target not achieved.
There is a pending bill arising from previous financial year that is being serviced.
|
| 28 Apr 2026 | Ongoing | 0.00 | 0.0% |
Budgetary constraints
|
Prioritize the project
|
Target not achieved.
Verification and approval is Ongoing.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 24 Feb 2026 | Completed | 1,468,800,000.00 | 100.0% |
N/A
|
N/A
|
The State Department posted all the 2,000 recruited trainers and instructors to their respective institutions
|
| 24 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
Cumulatively, 195 of 244 TVET institutions are offering online content
|
| 24 Feb 2026 | Ongoing | 0.00 | 58.0% |
Poor internet connectivity in some TVETs based in remote areas of the country
|
The Ministry of ICT to enhance internet connectivity in the most remote areas of the country
|
Cumulatively, 195 TVET institutions are offering online content
|
| 24 Feb 2026 | Ongoing | 20,817,800.00 | 19.0% |
N/A
|
N/A
|
Cumulatively, 65 TVET institutions are offering online content
|
| 24 Feb 2026 | Ongoing | 39,900,000.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 24 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 24 Feb 2026 | Ongoing | 74,376,190.00 | 0.0% |
N/A
|
N/A
|
Development of Learning Management System is ongoing
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Cumulatively, 143 courses are implemented online in 236 TVETs
|
| 24 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 24 Feb 2026 | Ongoing | 8,945,340.00 | 100.0% |
N/A
|
N/A
|
Cumulatively, 134 programmes/ courses are offered online
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 16 Apr 2026 | Ongoing | 0.00 | 100.0% |
- Delay in the approval of the Draft Labour Mobility Management Bill, which is affecting labour mobility processes, particularly the regulation of recruitment agencies, coordination among institutions and compliance with agreed labour mobility frameworks.
- Delay in the operationalization of the labour mobility agreement with the United Kingdom, resulting in slow finalization of operating modalities, delayed posting of a Labour Attaché and a lag in the receipt of job orders for Kenyan workers.
|
- Cabinet to prioritize the approval and subsequent implementation of the Draft Labour Mobility Management Bill to provide a clear legal and institutional framework that supports effective regulation of labour mobility, improved inter-agency coordination and implementation of existing labour mobility arrangements.
- The State Department for Labour and Skills Development, in collaboration with the Ministry of Foreign and Diaspora Affairs, to expedite the implementation of the operating modalities of the UK Agreement, facilitating the posting of a Labour Attaché to the United Kingdom and engaging the relevant UK authorities to activate job orders and placement under the agreement.
|
The five (5) signed BLAs/MOUs are in force with the following countries: Germany (2024), the United Kingdom (2021) on the recruitment of healthcare professionals, the United Arab Emirates (2018), the Kingdom of Saudi Arabia (2017) and the State of Qatar (2012). Labour attaches had been posted in three (3) countries. Labour attaches have been posted in four (4) countries.
|
| 16 Apr 2026 | Ongoing | 0.00 | 100.0% |
Delay in getting mutually agreeable dates for signing completed BLAs.
The negotiation and conclusion of BLAs are contingent upon the readiness, priorities and internal processes of destination countries. As a result, progress on some agreements may experience delays beyond the control of the Government of Kenya, particularly where partner countries require extended consultations, legal reviews or alignment with their domestic labour migration policies.
The negotiation and finalization of BLAs require sustained technical engagements, consultative meetings and bilateral missions between partner countries. However, limited financial resources to support these engagements can slow down the pace of concluding Agreements.
|
Strengthen structured engagement with destination countries by establishing regular technical consultations and joint working mechanisms to expedite the negotiation and conclusion of BLAs.
Allocate sufficient financial resources to support bilateral meetings, technical missions and stakeholder consultations necessary for timely conclusion of BLAs.
|
Two BLAs with Oman and Kuwait are complete and ready for signing however pending mutually agreeable dates between the two countries for signing.
|
| 16 Apr 2026 | Ongoing | 0.00 | 100.0% |
- Skills mismatch limiting the absorption of vacancies posted.
- Delays in conclusion of BLAs to enable Kenyans get access to more opportunities in various labour markets.
- Limited job orders from destination countries, constraining placement opportunities for qualified job seekers.
- Unethical recruitment practices and the rise of unscrupulous agencies, undermining safe and orderly labour migration.
- Fragmented labour migration placement data across multiple government institutions, leading to incomplete capture of job placement information as different agencies maintain separate datasets and reporting systems.
- Delay in the approval of the Draft Labour Mobility Management Bill leading to slowing of the establishment of a comprehensive legal and institutional framework to regulate labour mobility and expand overseas employment opportunities.
|
-The State Department for Labour and Skills Development to expand access to more labour markets by initiating BLAs, to enable Kenyan job seekers get more opportunities.
-The National Employment Authority to enhance regulation, monitoring and enforcement against unethical recruitment agencies and promote compliance with ethical recruitment standards.
- Establish an inter-agency labour migration data coordination or committee involving the State Department for Labour and Skills Development, State Department for Diaspora Affairs, State Department for National Government Co-ordination and State Department for Immigration and Citizen Services to harmonize data collection, sharing and reporting on labour migration and placements.
-Funding approval and disbursement from the National Treasury to enable the posting of additional labour attaches to increase the sourcing of jobs in the destination countries.
- Requesting the support of the Office of the Prime Cabinet Secretary to facilitate the approval and fast-tracking of the Draft Labour Mobility Management Bill when it is resubmitted for consideration and tabling before Cabinet.
|
A total of 23,177 Kenyans were placed in employment abroad.
|
| 16 Apr 2026 | Ongoing | 0.00 | 40.0% |
None.
|
Public sensitization to be planned in advance to enable smooth rollout.
|
Progress towards development of the system include:
- System modules developed.
- Implementation of the system architect.
- Integration component with other relevant IMS identified.
Validation and user system training to be conducted in Q4
|
| 16 Apr 2026 | Completed | 0.00 | 100.0% |
Need for public sensitization and awareness on the labour migration services being offered at the OSSC
|
- Need for the development of IEC materials and its distribution.
- Continuous publicizing the OSSC on social media.
|
The OSSC for labour migration services was established, operationalized and equipped in 2024/25 FY
|
| 16 Apr 2026 | Ongoing | 0.00 | 0.0% |
Delay in planning and funding allocation for the activity pushed the project to be conducted in Q4.
|
Activity to be undertaken in Q4.
|
Activity scheduled to be conducted in Q4.
|
| 25 Feb 2026 | Ongoing | 38,000,000.00 | 100.0% |
- Delay in the approval of the Draft Labour Mobility Management Bill, which is affecting labour mobility processes, particularly the regulation of recruitment agencies, coordination among institutions and compliance with agreed labour mobility frameworks.
- Delay in the operationalization of the labour mobility agreement with the United Kingdom, resulting in slow finalization of operating modalities, delayed posting of a Labour Attaché and a lag in the receipt of job orders for Kenyan workers..
|
- Cabinet to prioritize the approval and subsequent implementation of the Draft Labour Mobility Management Bill to provide a clear legal and institutional framework that supports effective regulation of labour mobility, improved inter-agency coordination and implementation of existing labour mobility arrangements.
- The State Department for Labour and Skills Development, in collaboration with the Ministry of Foreign and Diaspora Affairs, to expedite the implementation of the operating modalities of the UK Agreement, facilitating the posting of a Labour Attaché to the United Kingdom and engaging the relevant UK authorities to activate job orders and placement under the agreement.
|
As of 2023/24 FY Q4, four (4) BLAs/MOUs had been signed and in force with the following countries: the United Kingdom (2021) on the recruitment of healthcare professionals, the United Arab Emirates (2018), the Kingdom of Saudi Arabia (2017) and the State of Qatar (2012). In addition, labour Attaché offices were established in three (3) destination countries where such Agreements exist, to oversee the implementation of the Bilateral Labour Agreements (BLAs) and safeguard the welfare of Kenyan migrant workers, particularly those facing distress. These offices are in the Kingdom of Saudi Arabia, the United Arab Emirates and the State of Qatar.
|
| 25 Feb 2026 | Ongoing | 0.00 | 50.0% |
Challenge with funding delayed the process and limited the ability to conduct assessments in various countries as scheduled.
|
Timely and adequate disbursement of funds by the the National Treasury to facilitate implementation of activities at the appropriate stages of the BLA negotiation and conclusion process.
|
Skills assessment conducted in Germany with consultations done with German employers and trainers.
|
| 25 Feb 2026 | Ongoing | 0.00 | 100.0% |
- Delays in conclusion of BLAs to enable Kenyans get access to more opportunities in various labour markets.
- Limited job orders from destination countries, constraining placement opportunities for qualified jobseekers.
- Unethical recruitment practices and the rise of unscrupulous agencies, undermining safe and orderly labour migration.
- Fragmented labour migration placement data across multiple government institutions, leading to incomplete capture of job placement information as different agencies maintain separate datasets and reporting systems.
- Delay in the approval of the Draft Labour Mobility Management Bill leading to slowing of the establishment of a comprehensive legal and institutional framework to regulate labour mobility and expand overseas employment opportunities.
|
-The State Department for Labour and Skills Development to expand access to more labour markets by initiating BLAs, to enable Kenyan job seekers get more opportunities.
-The National Employment Authority to enhance regulation, monitoring and enforcement against unethical recruitment agencies and promote compliance with ethical recruitment standards.
- Establish an inter-agency labour migration data coordination or committee involving the State Department for Labour and Skills Development, State Department for Diaspora Affairs, State Department for National Government Co-ordination and State Department for Immigration and Citizen Services to harmonize data collection, sharing and reporting on labour migration and placements.
-Funding approval and disbursement from the National Treasury to enable the posting of additional labour attaches to increase the sourcing of jobs in the destination countries.
- Requesting the support of the Office of the Prime Cabinet Secretary to facilitate the approval and fast-tracking of the Draft Labour Mobility Management Bill when it is resubmitted for consideration and tabling before Cabinet.
|
The placement is based on job orders received.
|
| 25 Feb 2026 | Ongoing | 0.00 | 100.0% |
- Delays in conclusion of BLAs to enable Kenyans get access to more opportunities in various labour markets.
- Limited job orders from destination countries, constraining placement opportunities for qualified jobseekers.
- Unethical recruitment practices and the rise of unscrupulous agencies, undermining safe and orderly labour migration.
- Fragmented labour migration placement data across multiple government institutions, leading to incomplete capture of job placement information as different agencies maintain separate datasets and reporting systems.
- Delay in the approval of the Draft Labour Mobility Management Bill leading to slowing of the establishment of a comprehensive legal and institutional framework to regulate labour mobility and expand overseas employment opportunities.
|
-The State Department for Labour and Skills Development to expand access to more labour markets by initiating BLAs, to enable Kenyan job seekers get more opportunities.
-The National Employment Authority to enhance regulation, monitoring and enforcement against unethical recruitment agencies and promote compliance with ethical recruitment standards.
- Establish an inter-agency labour migration data coordination or committee involving the State Department for Labour and Skills Development, State Department for Diaspora Affairs, State Department for National Government Co-ordination and State Department for Immigration and Citizen Services to harmonize data collection, sharing and reporting on labour migration and placements.
-Funding approval and disbursement from the National Treasury to enable the posting of additional labour attaches to increase the sourcing of jobs in the destination countries.
- Requesting the support of the Office of the Prime Cabinet Secretary to facilitate the approval and fast-tracking of the Draft Labour Mobility Management Bill when it is resubmitted for consideration and tabling before Cabinet.
|
The placement is based on job orders.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 22 Apr 2026 | Ongoing | 6,895,086,000.00 | 25.0% |
- Lack of operations funds
|
- Allocate funds for operationalizing the Inua Jamii Cash Transfer Programme
|
Amount spent on 1,149,181 beneficiaries for 3 months at Ksh. 2,000 each
|
| 25 Feb 2026 | Ongoing | 10,552,410,000.00 | 86.0% |
-Lack of Ksh. 150 Million operations funds for Monitoring of the Inua Jamii Cash transfer programme
|
-Allocate adequate and ring-fenced Ksh 150 Million for operational funds to support field supervision, registration, grievance redress, logistics, and continuous programme monitoring.
|
A total number of 1,759,552 beneficiaries supported in the cash transfer programme
|
| 25 Feb 2026 | Ongoing | 7,279,254,000.00 | 74.0% |
- Lack of Ksh. 150 Million budget for operations for the Inua Jamii programme
|
-Allocate adequate and ring-fenced Ksh 150 Million for operational funds to support field supervision, registration, grievance redress, logistics, and continuous programme monitoring.
|
These numbers are as per the December 2025 payroll. The target was based on the allocation for this FY. The CT-
OVC target was moved to the State Department for Children Services.
|
| 25 Feb 2026 | Completed | 0.00 | 100.0% |
-Data inconsistencies and errors during migration from legacy systems
-Insufficient budgetary allocation for system maintenance and upgrades
-System slowdowns or downtime during peak payment processing periods
|
-Conduct thorough data validation and cleaning exercises prior to and after migration from legacy systems.
-Provide ring-fenced budget allocations for system maintenance, upgrades, cybersecurity, and hosting services.
-Upgrade server capacity and optimize system performance to handle peak payment processing periods efficiently.
|
2 modules were enhanced, which include: Payment module and Monitoring and Evaluation Module
|
| 25 Feb 2026 | Ongoing | 0.00 | 100.0% |
CCTPMIS system downtime
|
-Implement robust server infrastructure and backup systems to minimize unplanned outages.
-Establish scheduled maintenance windows and communicate them in advance to staff and beneficiaries.
-Set up real-time system monitoring and alert mechanisms to detect issues early.
-Develop and test a disaster recovery plan to restore data and services quickly after downtime.
-Maintain offline or alternative workflows for critical operations during outages (e.g., paper-based enrolments or payment logs).
|
The CCTPMIS automatically graduates CT-OVC household once the youngest Member has attained the age of 23 Years.
|
| 25 Feb 2026 | Completed | 0.00 | 100.0% |
- Downtimes
- Lack of Budget for continuous maintenance
|
- Reliable backup infrastructure and clear service level agreements to ensure timely system recovery and continuity of services
- Dedicated and ring-fenced budget allocation for continuous system maintenance and upgrades
|
This is an upgraded, integrated social protection information system that consolidates data on beneficiaries of various social assistance programmes into one centralized platform to improve targeting, coordination, and efficiency in service delivery.
It's designed to:
1. Integrate data from programmes such as Inua Jamii (Older Persons, Persons with Severe Disabilities, and OVC Cash Transfers).
2. Enable better identification and targeting of poor and vulnerable households through harmonized data.
3. Reduce duplication of beneficiaries across programmes.
4. Strengthen interoperability with other government systems (e.g., Civil Registration, SHA, Pension, National ID databases, and payment systems).
5. Improve monitoring, reporting, and evidence-based planning.
|
| 25 Feb 2026 | Ongoing | 0.00 | 60.0% |
-Interoperability issues between different government information systems
-Data privacy and security risks for sensitive beneficiary information
|
- Adopt standardized data formats and protocols, and implement a centralized integration framework to ensure seamless communication between all linked systems.
- Robust cybersecurity measures, including encryption, access controls, and regular audits, while ensuring compliance with national data protection laws.
|
The Pensions system is still being upgraded to allow integrations. It's ongoing and will be completed in FY 2025/26
|
| 25 Feb 2026 | Ongoing | 10,249,885,696.00 | 50.0% |
Inadequate funds
|
Provide more funding is required to meet the set target
|
Total of 1,708,314 beneficiaries provided with cash trasfer
|
| 25 Feb 2026 | Ongoing | 0.00 | 30.0% |
-System integration and compatibility issues
-Data migration errors from legacy systems
-System downtime and slow updates
-Cybersecurity and data privacy risks
|
- Ensure standardized system integration and interoperability across all linked platforms.
- Conduct thorough data cleaning, validation, and backup before migrating legacy data.
- Implement redundant servers, cloud backups, and real-time monitoring to reduce downtime.
- Strengthen cybersecurity with encryption, access controls, and regular security audits
|
This is an integrated digital platform that shares data and communicates with other key national databases to improve targeting, verification, payments, and monitoring of beneficiaries
|
| 25 Feb 2026 | Ongoing | 10,552,410,000.00 | 50.0% |
budget limitations
|
more funding/budget
|
A total of 1,758,735 targeted during 2023/24 FY. The additional 500,000 beneficiaries for the FY 2024/25 to reach a target of 2,233,000 beneficiaries have not been onboarded
Due to budget limitations
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 May 2026 | Ongoing | 0.00 | 0.0% |
Inadequate funding has inhibited the effective implementation of talent identification, nurturing, and commercialization programmes
|
Engage private sector players, sponsors, development partners, and investors to support talent development initiatives financially and technically.
|
N/A
|
| 11 May 2026 | Stalled | 0.00 | 0.0% |
The review of the Inter-County Licensing Regime has stalled due to inadequate funds
|
National and county governments should allocate dedicated budgetary support and mobilize reources for the review process and seek development partner support where possible.
|
N/A
|
| 11 May 2026 | Completed | 1,000,000.00 | 100.0% |
N/A
|
N/A
|
Framework for Presidential challenges and Innovation Award was Developed in FY 2023/24
|
| 04 May 2026 | Ongoing | 0.00 | 38.0% |
Inadequate funding which has resulted to delayed payments hence pending bills.
|
Improved funding to honor Interim Payment Certificates from the contractors.
|
In the Q2 report, the progress was based on financial expenditure. However, in the Q3 report, progress is based on scope of works done.
Target not achieved due to strategic redesign and technical audits necessary to align the facility with international FIFA standards as an alternative venue for AFCON2027.
|
| 04 May 2026 | Ongoing | 0.00 | 94.0% |
Inadequate funding which has resulted to delayed payments hence pending bills.
|
Improved funding to honor Interim Payment Certificates from the contractors.
|
In the Q2 report, the progress was based on financial expenditure. However, in the Q3 report, progress is based on scope of works done.
Target not achieved. Phase I is complete, with Phase II structural works including canopy installation now scheduled for commencement.
|
| 04 May 2026 | Stalled | 0.00 | 0.0% |
The project is stalled due to lack of a relevant legal framework.
|
Fast track the formulation of a functional framework or enabling legal instruments.
|
The High Court of Kenya suspended the Talanta Hela council and its technical committees in May 2023 due to legal and constitutional flaws.
|
| 04 May 2026 | Ongoing | 0.00 | 100.0% |
Inadequate funding
|
Establishment of robust domestic and foreign financing framework in collaboration with the National Treasury.
|
Phase I has been concluded, with the final 1% deferred for integration into the comprehensive Phase II upgrades required for AFCON 2027 compliance.
|
| 04 May 2026 | Ongoing | 0.00 | 91.0% |
Technical Complexity and Strategic Design for International Compliance
|
Technical Standardization and Certification: Since the stadium is designated for high-profile events or international competitions it must undergo rigorous technical certification during both the development and implementation phase.
|
Target not achieved as the project transitioned from primary civil works to the high-precision structural installations and specialized systems required for international Category 4 compliance.
|
| 04 May 2026 | Ongoing | 143,965,717.00 | 0.0% |
1. Land disputes in some targeted construction sites
2. Delayed payments which leads to slow pace of construction
|
Engaging with relevant stakeholders in finding for alternative sites for construction. The Academy is in the verge of resolving this challenge.
Timely disbursement of project funds to ensure smooth construction process by the contractor.
|
Target not achieved. While 33 of the 37 proposed sports academy sites have been officially handed over, active construction is in progress at 20 sites.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
Sports, Arts, and Social Development Fund (SASDF) cash flows are significantly constrained due to major financial commitments hence affecting funding for the academies.
|
Exchequer supplement to bridge the funding gap of KSh. 2.035 billion as per the approved budget.
|
37 academies have been prioritized (listed below) with 32 sites handed over to contractors and at different completion levels.
RIFT VALLEY REGION
S/NO. NAME CONSTITUENCY COUNTY
1. St. Patrick’s Iten Keiyo South Elgeyo-Marakwet
2. Chepkorio Sports Ground Keiyo North Elgeyo Marakwet
3. Kibigos Primary School Marakwet West Elgeyo Marakwet
4. Kapchebau Grounds Marakwet East Elgeyo Marakwet
5. Tegat Primary School Bomet East Bomet
6. Koitalel Arap Samoei Academy Nandi Hills Nandi
7. Mogotio Sports Ground Mogotio Baringo
8 Paul Boit Boys Sec. School Turbo Uasin Gishu
9. Kesengei Primary School Aldai Nandi
10 Nakalale Sports Ground Turkana North Turkana
WESTERN REGION
S/NO. NAME CONSTITUENCY COUNTY
11. St. Gabriel Asiriam Primary School Teso South Busia
12. Siera Girls High School Nambale Busia
13. Lunyofu Sports Grounds Budalangi Busia
14. Friends School Bokoli Webuye West Bungoma
15. Nalondo Boys High School Kabuchai Bungoma
16. Burendwa Primary School Ikolomani Kakamega
17. Gisambai Primary School Hamisi Vihiga
NYANZA REGION
S/NO. NAME CONSTITUENCY COUNTY
18. Ukwala Sports Academy Ugenya Siaya
19. Magunga Primary School Suba South Homa Bay
NAIROBI REGION
S/NO. NAME CONSTITUENCY COUNTY
20. Kenya Academy of Sports HQs Kasarani Nairobi
21. Imara Primary School Embakasi Central Nairobi
CENTRAL REGION
S/NO. NAME CONSTITUENCY COUNTY
22. Mirira Primary School Kiharu Murang’a
23. Mukurenju Primary School Kandara Murang’a
24. Kimuchu Primary School Thika Town Kiambu
25. Karenju Primary School Kabete Kiambu
26. Weru Mixed Sec. School Ol Joro orok Nyandarua
EASTERN AND NORTH EASTERN REGIONS
S/NO. NAME CONSTITUENCY COUNTY
27. Mwala Sports Ground Mwala Machakos
28. Kinyui Stadium Matungulu Machakos
29. Kisiiki Primary School Yatta Machakos
30. Nzombe Sports Ground Kitui East Kitui
31. Kiio Secondary School Mwingi West Kitui
32 Holale Primary School Moyale Marsabit
33. Kotulo Primary School Tarbaj Wajir
34. Garbatula Boys High School Isiolo South Isiolo
35. Elwak Baraza Park Mandera South Mandera
COASTAL REGION
S/NO. NAME CONSTITUENCY COUNTY
36. Kombani Football Academy Matuga Kwale
37. Taru Secondary School Kinango Kwale
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 50,000,000.00 | 3.0% |
Production affected by unfavourable weather condition and delay in exchequer release
|
production expected to be scaled up during the long rains (march to may)
national treasury to fasttrack exchequer timely issuance
|
N/A
|
| 25 Feb 2026 | Ongoing | 15,000,000.00 | 5.0% |
Delay in exchequer release
|
the national treasury to facilitate timely exchequer
|
N/A
|
| 25 Feb 2026 | Ongoing | 25,500,700.00 | 35.0% |
rehabilitation is limited during the dry season
|
State department for Forestry to expedite more rehabilitation during the long rains season (march to may) in Q3 and Q4
|
N/A
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
delay in exchequer
|
national treasury to avail timely exchequer issuance
|
target to be achieved in subsequent quarter
|
| 25 Feb 2026 | Ongoing | 500,000,000.00 | 1.0% |
Financial challenges
|
Exchequer to release the funds timely.
|
Target not fully achieved
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
implemnentation at procurement process,planned for Q3 AND Q4 during long rains
|
| 25 Feb 2026 | Ongoing | 143,150,151.00 | 45.0% |
N/A
|
N/A
|
target to be achieved in subsequent quarter
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
lack of budget for construction
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
lack of budget provision
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
exchequer
|
exchequer provision
|
Construction of 1 model nursery at 85% completion.implementation affected by delay in exchequer release.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
KWTA which was implementing the project was disbanded following expiry of Legal Notice No. 27 of 2012 which established the Agency as well as the broader rationalization of state corporation whose functions overlapped with other institutions. The functions of the Agency were transferred to KFS under State Department for Forestry.
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 24 Feb 2026 | Stalled | 0.00 | 0.0% |
Lack of an established policy and criteria on deployment of Tourism
Personnel as Tourism Attache's in strategic Kenyan Foreign Missions. No
budget provision for the same
|
The Ministry proposed consideration for Tourism Attache's in Kenyan
Foreign Missions in the New Foreign Policy submitted to Cabinet. Follow up
on this recommendations with the Cabinet is necessary. Development and
approval of human resource instruments for the Tourism Attache Cadres.
Budget provisions for their operations and personnel emoluments.
|
N/A
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Target achieved
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Target for Q1 achieved
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Target achieved
|
| 24 Feb 2026 | Ongoing | 0.00 | 0.0% |
Lack of an established policy and criteria on deployment of Tourism
Personnel as Tourism Attache's in strategic Kenyan Foreign Missions. No
budget provision for the same.
|
The Ministry proposed consideration for Tourism Attache's in Kenyan
Foreign Missions in the New Foreign Policy submitted to Cabinet. Follow up
on this recommendations with the Cabinet is necessary. Development and
approval of human resource instruments for the Tourism Attache Cadres.
Budget provisions for their operations and personnel emoluments
|
The target is to be achieved in the subsequent quarter.
|
| 24 Feb 2026 | Ongoing | 0.00 | 0.0% |
Lack of an established policy and criteria on deployment of Tourism
Personnel as Tourism Attache's in strategic Kenyan Foreign Missions. No
budget provision for the same.
|
The Ministry proposed consideration for Tourism Attache's in Kenyan
Foreign Missions in the New Foreign Policy submitted to Cabinet. Follow up
on this recommendations with the Cabinet is necessary. Development and
approval of human resource instruments for the Tourism Attache Cadres.
Budget provisions for their operations and personnel emoluments.
|
N/A
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
implemented the “Hapa ni Wapi” Campaign, aimed at promoting the destination to the domestic market
KTB has finalized the Experience the Wonder international Campaign
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
KTB focused on the Asia market in Q2.
Feasibility studies for the new markets were conducted in 2024/25. The focus in 2025/26 is on the development of the new markets; however, due to resource constraints, KTB remained focused on the existing markets
|
| 24 Feb 2026 | Ongoing | 0.00 | 100.0% |
Clashing dates of tourism and travel exhibitions in different countries
|
Profiling of markets with higher impact returns.
|
KTB implemented a campaign in South Africa in Q2 aimed at boosting the South African arrivals to Kenya
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 29 Apr 2026 | Ongoing | 2,442,010.00 | 100.0% |
The target was achieved; however, maritime training—undertaken by Bandari Maritime Academy and other maritime training institutions under the oversight of the Kenya Maritime Authority—continues to face significant challenges. These include inadequate institutional funding, limited access to student financing through the Higher Education Loans Board (HELB), and insufficient sea-time and employment opportunities for trainees. As a result, many cadets are unable to complete mandatory sea-time requirements for certification, leading to delays in qualification, underemployment, and a growing mismatch between trained graduates and industry absorption capacity. This undermines the efficiency of investments in maritime education and constrains the country’s ability to fully harness opportunities within the blue economy.
|
o address these challenges, it is recommended that the Government enhance budgetary support to maritime training institutions, expand HELB financing to fully cover maritime programmes, and establish targeted sea-time facilitation mechanisms, including partnerships with shipping lines and the potential development of a national carrier to guarantee cadet placements. Additionally, strengthening regulation and performance monitoring of recruitment and placement agencies, alongside bilateral agreements with international maritime partners, would improve employment pathways and ensure that training translates into meaningful job opportunities.
|
Target on training was achieved with 1,375 seafarers trained.
|
| 29 Apr 2026 | Ongoing | 918,030.00 | 52.0% |
Lack of an active national carrier to provide sea time and employment opportunities and low-
level placement by licensed recruitment and placement agencies.
|
Establish a national shipping carrier complemented by enforced sea-time quotas and a regulated, performance-based recruitment system to guarantee structured training and employment opportunities for Kenyan seafarers.
|
Target not achieved. Total number of seafarers recruited due low-level placement by licensed recruitment and placement agencies.
|
| 09 Mar 2026 | Ongoing | 0.00 | 0.0% |
Construction of the project has not commenced due to a court injunction
|
Expedite resolution of the court injunction to facilitate the contract to complete the project in good time
|
N/A
|
| 09 Mar 2026 | Ongoing | 359,309,600.00 | 100.0% |
N/A
|
N/A
|
Target was completed during Q2 of the FY 2025/26
|
| 09 Mar 2026 | Ongoing | 140,535,816.93 | 85.0% |
N/A
|
N/A
|
On schedule
The progress is as follows:
• Substructure works completed
• Superstructure works completed
That is, structural framework for NAMARET is completed
|
| 09 Mar 2026 | Ongoing | 267,675,564.00 | 85.0% |
N/A
|
N/A
|
Intent to plan the Indian Ocean gazette notice published; legal review and draft MSP regulations finalized; Key thematic technical areas identified and analytical framework developed; MSP portal development is ongoing; data collection and compilation done; and cloud server procured from the National server provider at Konza city
|
| 09 Mar 2026 | Ongoing | 408,123,414.45 | 50.0% |
N/A
|
N/A
|
Completion rate for the landing sites is as follows: Kidongo- 59.68%; Mukowe 36.20%; Kipini 47.92%; Kilifi Central 58.31%; and Mwaepe 46.44%.
|
| 09 Mar 2026 | Ongoing | 561,501,473.00 | 69.0% |
N/A
|
N/A
|
On schedule
|
| 09 Mar 2026 | Ongoing | 257,000,000.00 | 37.0% |
N/A
|
N/A
|
Scheduled for completion in third quarter for the FY 2025/26
|
| 09 Mar 2026 | Completed | 359,309,600.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 17 Apr 2026 | Pipeline | 0.00 | 0.0% |
Pending budgetary allocation
|
SDM to push for budgetary allocation through BPS 2026
|
Project Concept Notes approved for development of copper and chromite
|
| 17 Apr 2026 | Pipeline | 0.00 | 0.0% |
Pending budgetary allocation
|
SDM to push for budgetary allocation through BPS 2026
|
Project Concept Notes approved for development of copper and chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed finalization of the Project Concept Notes for submission to the National Treasury
|
The State Department for mining to fast-track completion of the project concept notes to facilitate development and commercialization of copper and chromite
|
Development of the Project Concept Notes for two strategic minerals; Copper and Chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Pending budgetary allocation
|
SDM to include budgetary provision in the subsector report for FY 2026/27 and
MTEF
|
Project Concept Notes approved for development of copper and chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed finalization of the Project Concept Notes for submission to the National Treasury
|
The State Department for mining to fast-track completion of the project concept notes to facilitate development and commercialization of copper and chromite
|
Development of the Project Concept Notes for two strategic minerals; Copper and Chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Pending approval of the developed Project Concept Notes
|
SDM to make a follow up with The National Treasury to expedite the approval process
|
Project Concept Notes for Copper and Chromite developed and submitted
to The National Treasury for Approval
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed approval of the developed Project Concept Notes
|
SDM to make a follow up with The National Treasury to expedite the approval process
|
Project Concept Notes for Copper and Chromite developed and submitted to The National Treasury for Approval
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed approval of the developed Project Concept Notes
|
SDM to make a follow up with The National Treasury to expedite the approval process
|
Project Concept Notes for Copper and Chromite developed and submitted
to The National Treasury for Approval
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Pending approval of PCNs
|
SDM to make a follow up for expedited PCNs approvals
|
Project Concept Notes for Copper and Chromite developed and submitted
to The National Treasury for Approval
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 20 Apr 2026 | Ongoing | 0.00 | 0.0% |
Insufficient Funds
|
Seek additional funding.
|
Inavailability of funds to run the programme to completion and finally gazzetment of the units
|
| 20 Apr 2026 | Ongoing | 287,000,000.00 | 71.0% |
Delay in exchequer release and inadequate funding leading to slow project implementation
|
Seek for additional funding.
|
24 Administrative units have been funded for construction and are at different stages.
|
| 20 Apr 2026 | Ongoing | 10,000,000.00 | 50.0% |
Delay in exchequer release. Inadequate funding
|
Seek additional funding for the project
|
6 administrative offices funded for refurbishment in FY 2025/26
|
| 23 Feb 2026 | Completed | 5,000,000.00 | 100.0% |
Delayed fund releases.
Late issuance of Authority to Incur Expenditure (AIE).
|
Timely and full release of funds to support project activities.
Submit expenditure requests and AIEs early and follow up regularly.
|
N/A
|
| 23 Feb 2026 | Ongoing | 144,500,000.00 | 100.0% |
Delayed release of ksh. 144,500,000
|
Timely funds release by exchequer
|
The 20 NGA Offices constructed are for the whole FY
|
| 20 Feb 2026 | Ongoing | 0.00 | 20.0% |
Delayed fund releases and late issuance of Authority to Incur Expenditure (AIE).
|
Timely and full release of funds to support project activities.
Submit expenditure requests and AIEs early and follow up regularly.
|
18 NGA offices under construction
|
| 20 Feb 2026 | Ongoing | 5,000,000.00 | 60.0% |
-Delayed or partial fund releases.
-Late issuance of Authority to Incur Expenditure (AIE).
|
Ensure timely and full release of funds to support project activities.
Submit expenditure requests and AIEs early and follow up regularly.
|
N/A
|
| 20 Feb 2026 | Ongoing | 0.00 | 0.0% |
- Late issuance of Authority to Incur Expenditure (AIE)
|
-Ensure timely and full release of funds to support project activities.
-Submit expenditure requests and AIEs early and follow up regularly.
|
N/A
|
| 20 Feb 2026 | Ongoing | 0.00 | 1.0% |
Dekay in disbursement of ksh. 144,500,000
|
N/A
|
18 NGA Offices under construction
|
| 20 Feb 2026 | Ongoing | 0.00 | 0.0% |
-Delayed exchequer releases and cash flow constraints affecting timely implementation of planned activities.
-Reporting Timing Differences – Implementation commenced administratively, but no financial absorption has been recorded yet.
|
- Submit budget and expenditure requests early in the financial year to allow sufficient time for review and issuance of AIEs.
-Finance, planning, and project teams should collaborate to ensure all supporting documents and justifications for AIE issuance are complete and accurate to ensure funds are released promply.
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 15 May 2026 | Ongoing | 1,697,283,481.00 | 100.0% |
Inadequate funding for state visits
|
Require additional funding for State visit
|
N/A
|
| 15 May 2026 | Ongoing | 2,200,000,000.00 | 100.0% |
In adequate budget allocation. The State Department requires an additional amount of Kshs.3.5 B
|
More funding requires for this target
|
N/A
|
| 14 May 2026 | Ongoing | 0.00 | 0.0% |
budgetary constraints
|
CAB memo to operationalize a mission to be accompanied by a budgetary commitment
|
N/A
|
| 14 May 2026 | Pipeline | 1,000,000.00 | 100.0% |
N/A
|
N/A
|
UNEA-7
|
| 14 May 2026 | Ongoing | 100,000,000.00 | 100.0% |
Budgeting constrait
|
Need for budget set aside for conferences
|
N/A
|
| 14 May 2026 | Pipeline | 0.00 | 10.0% |
Dependent on other parties
|
Need for multi Agency support
|
GoK has provided land at JKIA. Dependent on UN goodwill, funding and geopolitical alignment
|
| 14 May 2026 | Ongoing | 1,000,000.00 | 100.0% |
N/A
|
Need for Multi-Agency support and efforts
|
Judge Njoki Ndungu for ICC( International Criminal Court ), Ms. Fatuma Hajji for Convention on the Rights of Persons with Disabilities (CRPD)
|
| 18 Feb 2026 | Ongoing | 1.00 | 100.0% |
Late involvement of MFDA by MDAs to the preparations of conferences/events.
|
MDAs to involve SDFA in the early preparation processes of conferences/events
|
Recognition of Nairobi as a regional conference hub has increased the number of conferences in the Country significantly.
|
| 18 Feb 2026 | Ongoing | 1.00 | 100.0% |
N/A
|
N/A
|
1. Ongoing campaigns for the AU Peace and Security Council (AUPSC)
2. Ongoing Campaigns to International Telecommunication Union
|
| 18 Feb 2026 | Ongoing | 2,189,955.00 | 100.0% |
Low implementation/follow-up of the signed/concluded legal instruments.
|
1. State Department to prioritise initiation and conclusion of agreements/MoUs that are geared towards implementation of the Government Agenda (BETA)
2. MDAs should negotiate, clear and approve instruments to be signed ahead of time in readiness for signing
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 18 Feb 2026 | Ongoing | 0.00 | 50.0% |
The activity is time consuming and the office lacks adequate human capacity and equipments to to scan the bulky manual documents and records.
|
The office to engage interns and casuals to complement internal staff capacity.
|
Bulky nature of the records and data that require to be digitized. Digitization process ongoing using internal capacity
|
| 18 Feb 2026 | Ongoing | 0.00 | 0.0% |
Delayed approval by PSC and National Treasury
|
Fastrack the approvals by PSC and National Treasury
|
Approval was granted for recruitment of 86 State Counsels in year 2024 and officers reported in the July 2025. Approval for recruitment of additional State Counsels awaiting National Treasury and PSC Approval.
|
| 18 Feb 2026 | Ongoing | 9,564,720.00 | 0.0% |
The training needs surpass allocated funds
|
The office to to enhance efforts on sourcing alternative sources of funds to supplement allocated training budget.
|
Two weeks Induction training for 89 newly recruited state counsels
|
| 18 Feb 2026 | Pipeline | 0.00 | 0.0% |
The available budget ceiling is inadequate to cater for implementation of all projects.
|
The office to prioritize funding to the project over the medium term
|
The project is in the pipeline to be implemented in subsequent years
|
| 18 Feb 2026 | Ongoing | 0.00 | 75.0% |
Delayed reconstitution of the Nairobi Centre for International Arbitration
|
Fastrack replacement of the NCIA Board members who have exited/retired
|
The arbitral court is yet to be fully operationalised
|
| 18 Feb 2026 | Ongoing | 0.00 | 0.0% |
Delayed procurement due to low uptake of eGP System
|
Fastrack operationalization of the eGP by the National Treasury
|
N/A
|
| 18 Feb 2026 | Ongoing | 0.00 | 0.0% |
Delayed procured process due to low uptake of eGP system
|
Fastrack the operationalization of eGP by the National Treasury
|
N/A
|
| 18 Feb 2026 | Ongoing | 0.00 | 0.0% |
Delayed procured process
|
Fastrack the operationalization of eGP system
|
The construction of regional offices is yet to commence
|
| 18 Feb 2026 | Pipeline | 0.00 | 0.0% |
The project is yet to be prioritized for implementation
|
Prioritize and avail budgetary allocation of KShs 2 billion.
|
The Centre is yet to receive budgetary support
|
| 18 Feb 2026 | Ongoing | 0.00 | 50.0% |
Inadequate space at the host County offices
|
Allocate adequate budget for construction of the regional offices
|
The Virtual courts at the Headquarters are operational
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 05 May 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
This activity is fully achieved. All courts have implemented e-filing.
|
| 05 May 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
This activity was completed and achieved.
|
| 22 Apr 2026 | Ongoing | 309,900.00 | 15.0% |
N/A
|
N/A
|
Three (3) Courts Mediation Registries established at the following Court Stations;
• Keroka Law Courts
• Mandera Law Courts
• Gichugu Law Courts
|
| 22 Apr 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted in the Financial Year. Status remains as per the end of the financial year 2024/2025- A feasibility study on the construction of the Supreme Court plaza, Court of Appeal, and the KJA has been done. A proposal was also prepared, which was approved by the Chief Registrar and has been scheduled to be presented as a cabinet memo by the Attorney General in cabinet for approval.
|
| 22 Apr 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted in the Financial Year. Status remains as per the end of the financial year 2024/2025- A feasibility study on the construction of the Supreme Court plaza, Court of Appeal, and the KJA has been done. A proposal was also prepared, which was approved by the Chief Registrar and has been scheduled to be presented as a cabinet memo by the Attorney General in cabinet for approval.
|
| 22 Apr 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted in the Financial Year. Status remains as per the end of the financial year 2024/2025- A feasibility study on the construction of the Supreme Court plaza, Court of Appeal, and the KJA has been done. A proposal was also prepared, which was approved by the Chief Registrar and has been scheduled to be presented as a cabinet memo by the Attorney General in cabinet for approval.
|
| 22 Apr 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted in the Financial Year. Status remains as per the end of the financial year 2024/2025 - A feasibility study on the construction of the Supreme Court plaza, Court of Appeal, and the KJA has been done. A proposal was also prepared, which was approved by the Chief Registrar and has been scheduled to be presented as a cabinet memo by the Attorney General in cabinet for approval.
|
| 22 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted in the Financial Year. Status remains as per the end of the financial year 2024/2025
|
| 22 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 22 Apr 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 18 Feb 2026 | Completed | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 18 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Budget constraints hindered taking off of the project
|
| 18 Feb 2026 | Completed | 0.00 | 0.0% |
N/A
|
N/A
|
The project completed in 2024/25 fy
|
| 18 Feb 2026 | Pipeline | 0.00 | 0.0% |
No funding in the budget
|
Its a critical project for the state department and therefore should be prioritized for budgeting
|
N/A
|
| 18 Feb 2026 | Completed | 0.00 | 0.0% |
N/A
|
N/A
|
N/A
|
| 17 Feb 2026 | Completed | 22,399,154.00 | 100.0% |
N/A
|
Activity achieved, operation and maintenance to take up the remaining costs
|
DIIMS developed, hosted at Konza Data Center and linked to E-citizen with the following services: registration of Kenyans in diaspora; registration of Diaspora associations; Diaspora in conflict with the law; requests by distressed persons; reporting of missing persons; counselling services; reporting death; crisis mapping and remittances.
|
| 17 Feb 2026 | Ongoing | 36,000,000.00 | 100.0% |
N/A
|
The target was exceeded.
|
High Level engagements were held in: Germany, China, USA, Switzerland, India, Egypt, UAE, Qatar, Brazil, UK, Italy, Austria. The target was exceeded.
|
| 17 Feb 2026 | Ongoing | 22,399,154.00 | 10.0% |
No challenge faced
|
Suppliers to submit documents promptly for prompt processing of payment
|
DIIMS hardware and software purchased and installed.
|
| 17 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
Achieved
|
| 17 Feb 2026 | Ongoing | 0.00 | 100.0% |
N/A
|
N/A
|
N/A
|
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 572,027,968.00 | 10.0% |
Excheguer release challenges leading to overdependence on external players
|
Collaboration in realising the project is the way to go
|
Target achieved in collaboration with NIA MIAD and KALRO Mwea
|
| 04 Nov 2025 | Ongoing | 0.00 | 85.0% |
N/A
|
N/A
|
Target achieved in collaboration with Ahero Irrigation Research Station (AIRS) and KALRO
|
| 08 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of funds
|
Exchequer to release funds for the project
|
Funds were not allocated
|
| 08 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of funds for the project
|
Exchequer to release the funds for the project
|
Funds were not available for availing of seeds
|
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 20 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Funds not availed
|
Timely provision of funds
|
Seeds will be availed in the next quarter
|
| 19 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
seasonal crop
|
timely provision of seeds
|
seeds to be availed in the third quarter
|