Public Reporting Portal

Public Project Reports

Generate public reports by cluster, financial year, quarter, status, and risk. Review summaries, analytics, cluster performance, and export filtered PDF reports.

Report Filters
Narrow the report using one or more filters, then generate or export the result.
Reset
Current filters:
Search: Talanta Hela
P
Total Projects
1
Active in repository
R
Total Reports
68
Submitted updates
B
Total Budget
Ksh 708,350,000.00
Allocated funds
S
Total Spent
Ksh 5,444,902,239.00
Reported expenditure
A
Absorption
768.7%
Spent to budget ratio
%
Average Performance
46.4%
Across filtered projects
!
High Risk Projects
0
Need close attention
Status Distribution
Snapshot of all filtered projects by current implementation status.
Pipeline
0
Ongoing
1
Stalled
0
Completed
0
Cluster Breakdown
Budget and expenditure distribution by cluster.
SOCIAL
Projects: 1
Budget: Ksh 708,350,000.00
Spent: Ksh 5,444,902,239.00
Project Summary
Showing 1 projects
Project Name Cluster Status Budget Spent Absorption Performance Risk Challenges Resolutions Actions
Talanta Hela
Project Talanta Hela under SOCIAL Cluster is currently Ongoing. Average performance is 46.4%. Budget absorption is 768.7%. Key challenges: Sports, Arts, and Social Development Fund (SASDF) cash flows are significantly constrained due to major financial commitments hence affecting funding... | The project lacks a relevant legal framework. | The project has no relevant legal framework.. Proposed resolutions: Exchequer supplement to bridge the funding gap of KSh. 2.035 billion as per the approved budget. | Fast track the formulation of a functional framework or enabling legal instruments. | Fast tracking the formulation of a functional framework or enabling legal instruments..
SOCIAL Ongoing 708,350,000.00 Ksh 5,444,902,239.00
768.7%
46.4%
Medium
Sports, Arts, and Social Development Fund (SASDF) cash flows are significantly constrained due to major financial commitments hence affecting funding... | The project lacks a relevant legal framework. | The project has no relevant legal framework.
Exchequer supplement to bridge the funding gap of KSh. 2.035 billion as per the approved budget. | Fast track the formulation of a functional framework or enabling legal instruments. | Fast tracking the formulation of a functional framework or enabling legal instruments.