Generate public reports by cluster, financial year, quarter, status, and risk. Review summaries, analytics, cluster performance, and export filtered PDF reports.

Report Filters
Narrow the report using one or more filters, then generate or export the result.
Reset
Current filters:
Search: Power Transmission and distribution
P
Total Projects
1
Active in repository
R
Total Reports
71
Submitted updates
B
Total Budget
Ksh 80,017,420,269.50
Allocated funds
S
Total Spent
Ksh 124,759,540,008.00
Reported expenditure
A
Absorption
155.9%
Spent to budget ratio
%
Average Performance
25.0%
Across filtered projects
!
High Risk Projects
0
Need close attention
Status Distribution
Snapshot of all filtered projects by current implementation status.
Pipeline
0
Ongoing
1
Stalled
0
Completed
0
Cluster Breakdown
Budget and expenditure distribution by cluster.
INFRASTRUCTURE
Projects: 1
Budget: Ksh 80,017,420,269.50
Spent: Ksh 124,759,540,008.00
Project Summary
Showing 1 projects
Project Name Cluster Status Budget Spent Absorption Performance Risk Challenges Resolutions Actions
Power Transmission and distribution
Project Power Transmission and distribution under INFRASTRUCTURE Cluster is currently Ongoing. Average performance is 25%. Budget absorption is 155.9%. Key challenges: N/A | Implementation affected by shortage of materials caused by delayed procurement of material. | Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.. Proposed resolutions: N/A | Fast track disbursment of funds | Fast track disbursment of funds..
INFRASTRUCTURE Ongoing 80,017,420,269.50 Ksh 124,759,540,008.00
155.9%
25.0%
Medium
N/A | Implementation affected by shortage of materials caused by delayed procurement of material. | Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
N/A | Fast track disbursment of funds | Fast track disbursment of funds.