Public Reporting Portal

Public Project Reports

Generate public reports by cluster, financial year, quarter, status, and risk. Review summaries, analytics, cluster performance, and export filtered PDF reports.

Report Filters
Narrow the report using one or more filters, then generate or export the result.
Reset
Current filters:
Search: Modernization of Kenya Veterinary Vaccine Production Institute (KEVEVAPI)
P
Total Projects
1
Active in repository
R
Total Reports
18
Submitted updates
B
Total Budget
Ksh 0.00
Allocated funds
S
Total Spent
Ksh 0.00
Reported expenditure
A
Absorption
0.0%
Spent to budget ratio
%
Average Performance
33.8%
Across filtered projects
!
High Risk Projects
1
Need close attention
Status Distribution
Snapshot of all filtered projects by current implementation status.
Pipeline
0
Ongoing
0
Stalled
1
Completed
0
Cluster Breakdown
Budget and expenditure distribution by cluster.
FINANCE AND PRODUCTION
Projects: 1
Budget: Ksh 0.00
Spent: Ksh 0.00
Project Summary
Showing 1 projects
Project Name Cluster Status Budget Spent Absorption Performance Risk Challenges Resolutions Actions
Modernization of Kenya Veterinary Vaccine Production Institute (KEVEVAPI)
Project Modernization of Kenya Veterinary Vaccine Production Institute (KEVEVAPI) under FINANCE AND PRODUCTION Cluster is currently Stalled. Average performance is 33.8%. Key challenges: The delay in Modernization of the KEVEVAPI plant has affected the attainment of vaccines production targets as envisaged in MTP IV. | The delayed finalization of the Modernization of the KEVEVAPI plant to achieve Good Manufacturing practice limits the production and productivity. Thi... | The lack of GMP certification limits the expanded production capacity to achieve the MTP IV targets.. Proposed resolutions: Provide remaining budget of KES 585 Million to finalize the Phase I of the KEVEVAPI Modernization project | Finalize the KEVEVAPI Modernization project, harmonize and coordinate the national vaccination | Finalize the implementation of the Modernization of the KEVEVAPI Plant which requires a budget of KES 585 Million to finalize Phase I of the project..
FINANCE AND PRODUCTION Stalled 0.00 Ksh 0.00 N/A
33.8%
High
The delay in Modernization of the KEVEVAPI plant has affected the attainment of vaccines production targets as envisaged in MTP IV. | The delayed finalization of the Modernization of the KEVEVAPI plant to achieve Good Manufacturing practice limits the production and productivity. Thi... | The lack of GMP certification limits the expanded production capacity to achieve the MTP IV targets.
Provide remaining budget of KES 585 Million to finalize the Phase I of the KEVEVAPI Modernization project | Finalize the KEVEVAPI Modernization project, harmonize and coordinate the national vaccination | Finalize the implementation of the Modernization of the KEVEVAPI Plant which requires a budget of KES 585 Million to finalize Phase I of the project.