P
Total Projects
1
Active in repository
R
Total Reports
14
Submitted updates
B
Total Budget
Ksh 1,356,850,000.00
Allocated funds
S
Total Spent
Ksh 0.00
Reported expenditure
A
Absorption
0.0%
Spent to budget ratio
%
Average Performance
0.0%
Across filtered projects
!
High Risk Projects
0
Need close attention
Status Distribution
Snapshot of all filtered projects by current implementation status.
Pipeline
1
Ongoing
0
Stalled
0
Completed
0
Cluster Breakdown
Budget and expenditure distribution by cluster.
ENVIRONMENT AND NATURAL RESOURCES
Projects: 1
Budget: Ksh 1,356,850,000.00
Spent: Ksh 0.00
Project Summary
Showing 1 projects
Project Name Cluster Status Budget Spent Absorption Performance Risk Challenges Resolutions Actions
Mineral Resource Development and Commercialization
Project Mineral Resource Development and Commercialization under ENVIRONMENT AND NATURAL RESOURCES Cluster is currently Pipeline. Average performance is 0%. Budget absorption is 0%. Key challenges: Delayed finalization of the Project Concept Notes for submission to the National Treasury | Pending budgetary allocation | Pending approval of the developed Project Concept Notes. Proposed resolutions: The State Department for mining to fast-track completion of the project concept notes to facilitate development and commercialization of copper and ch... | SDM to include budgetary provision in the subsector report for FY 2026/27 and MTEF | SDM to make a follow up with The National Treasury to expedite the approval process.
ENVIRONMENT AND NATURAL RESOURCES Pipeline 1,356,850,000.00 Ksh 0.00
0.0%
0.0%
Medium
Delayed finalization of the Project Concept Notes for submission to the National Treasury | Pending budgetary allocation | Pending approval of the developed Project Concept Notes
The State Department for mining to fast-track completion of the project concept notes to facilitate development and commercialization of copper and ch... | SDM to include budgetary provision in the subsector report for FY 2026/27 and MTEF | SDM to make a follow up with The National Treasury to expedite the approval process