Report Filters
Narrow the report using one or more filters, then generate or export the result.
Reset
Current filters:
Search: Last Mile County Internet Connectivity Programme (Phase IV and V)
P
Total Projects
1
Active in repository
R
Total Reports
7
Submitted updates
B
Total Budget
Ksh 625,900,205.00
Allocated funds
S
Total Spent
Ksh 74,959,900.00
Reported expenditure
A
Absorption
12.0%
Spent to budget ratio
%
Average Performance
31.4%
Across filtered projects
!
High Risk Projects
0
Need close attention
Status Distribution
Snapshot of all filtered projects by current implementation status.
Pipeline
0
Ongoing
1
Stalled
0
Completed
0
Cluster Breakdown
Budget and expenditure distribution by cluster.
INFRASTRUCTURE
Projects: 1
Budget: Ksh 625,900,205.00
Spent: Ksh 74,959,900.00
Project Summary
Showing 1 projects
Project Name Cluster Status Budget Spent Absorption Performance Risk Challenges Resolutions Actions
Last Mile County Internet Connectivity Programme (Phase IV and V)
Project Last Mile County Internet Connectivity Programme (Phase IV and V) under INFRASTRUCTURE Cluster is currently Ongoing. Average performance is 31.4%. Budget absorption is 12%. Key challenges: None | The project has faced contractual issues due to a tax dispute that is being resolved | Tax disputes. Proposed resolutions: none | Resolve tax dispute for the project to progress | None.
INFRASTRUCTURE Ongoing 625,900,205.00 Ksh 74,959,900.00
12.0%
31.4%
Medium
None | The project has faced contractual issues due to a tax dispute that is being resolved | Tax disputes
none | Resolve tax dispute for the project to progress | None