| Project Name | Cluster | Status | Budget | Spent | Absorption | Performance | Risk | Challenges | Resolutions | Actions |
|---|---|---|---|---|---|---|---|---|---|---|
|
Labour Migration
Project Labour Migration under SOCIAL Cluster is currently Ongoing. Average performance is 60.1%. Budget absorption is 30.1%. Key challenges: - Delay in the approval of the Draft Labour Mobility Management Bill, which is affecting labour mobility processes, particularly the regulation of rec... | Challenge with funding delayed the process and limited the ability to conduct assessments in various countries as scheduled. | - Delays in conclusion of BLAs to enable Kenyans get access to more opportunities in various labour markets. - Limited job orders from destination cou.... Proposed resolutions: - Cabinet to prioritize the approval and subsequent implementation of the Draft Labour Mobility Management Bill to provide a clear legal and instituti... | Timely and adequate disbursement of funds by the the National Treasury to facilitate implementation of activities at the appropriate stages of the BLA... | -The State Department for Labour and Skills Development to expand access to more labour markets by initiating BLAs, to enable Kenyan job seekers get m....
|
SOCIAL | Ongoing | 448,590,039.00 | Ksh 135,147,621.00 |
30.1%
|
60.1%
|
Medium |
- Delay in the approval of the Draft Labour Mobility Management Bill, which is affecting labour mobility processes, particularly the regulation of rec... | Challenge with funding delayed the process and limited the ability to conduct assessments in various countries as scheduled. | - Delays in conclusion of BLAs to enable Kenyans get access to more opportunities in various labour markets. - Limited job orders from destination cou...
|
- Cabinet to prioritize the approval and subsequent implementation of the Draft Labour Mobility Management Bill to provide a clear legal and instituti... | Timely and adequate disbursement of funds by the the National Treasury to facilitate implementation of activities at the appropriate stages of the BLA... | -The State Department for Labour and Skills Development to expand access to more labour markets by initiating BLAs, to enable Kenyan job seekers get m...
|