Search: Construction of High Social Impact Dams
P
Total Projects
1
Active in repository
R
Total Reports
532
Submitted updates
B
Total Budget
Ksh 3,455,499,000.00
Allocated funds
S
Total Spent
Ksh 266,560,000.00
Reported expenditure
A
Absorption
7.7%
Spent to budget ratio
%
Average Performance
36.9%
Across filtered projects
!
High Risk Projects
0
Need close attention
Status Distribution
Snapshot of all filtered projects by current implementation status.
Pipeline
1
Ongoing
0
Stalled
0
Completed
0
Cluster Breakdown
Budget and expenditure distribution by cluster.
INFRASTRUCTURE
Projects: 1
Budget: Ksh 3,455,499,000.00
Spent: Ksh 266,560,000.00
Project Summary
Showing 1 projects
Project Name Cluster Status Budget Spent Absorption Performance Risk Challenges Resolutions Actions
Construction of High Social Impact Dams
Project Construction of High Social Impact Dams under INFRASTRUCTURE Cluster is currently Pipeline. Average performance is 36.9%. Budget absorption is 7.7%. Key challenges: None | Lack of funds | lack of funds. Proposed resolutions: None | Expedite provision of funds. | Expedite provision of financing for the project..
INFRASTRUCTURE Pipeline 3,455,499,000.00 Ksh 266,560,000.00
7.7%
36.9%
Medium
None | Lack of funds | lack of funds
None | Expedite provision of funds. | Expedite provision of financing for the project.