| Project Name | Cluster | Status | Budget | Spent | Absorption | Performance | Risk | Challenges | Resolutions | Actions |
|---|---|---|---|---|---|---|---|---|---|---|
|
Construction of 6,000 km Roads
Project Construction of 6,000 km Roads under INFRASTRUCTURE Cluster is currently Ongoing. Average performance is 41.3%. Budget absorption is 0.5%. Key challenges: • Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection. | • Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection. | -none. Proposed resolutions: • Coordination with the National Land Commission. | -none | -.
|
INFRASTRUCTURE | Ongoing | 236,145,787,710.00 | Ksh 1,215,078,094.00 |
0.5%
|
41.3%
|
Medium |
• Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection. | • Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection. | -none
|
• Coordination with the National Land Commission. | -none | -
|