Generate public reports by cluster, financial year, quarter, status, and risk. Review summaries, analytics, cluster performance, and export filtered PDF reports.
| Project Name | Cluster | Status | Budget | Spent | Absorption | Performance | Risk | Challenges | Resolutions | Actions |
|---|---|---|---|---|---|---|---|---|---|---|
|
Construction of 6,000 km Roads
Project Construction of 6,000 km Roads under INFRASTRUCTURE Cluster is currently Ongoing. Average performance is 42.2%. Budget absorption is 0.5%. Key challenges: -none | Insecurity within the project area. Land acquisition and compensation. Potential community demands along the alignment. | Logging activities & Overloading along Gatakaini – Njabini (B20) road coupled with rainy conditions neccesitating repeated maintainance operations. In.... Proposed resolutions: -none | - | Engagement of a security liason and Kenya Defense Forces. Engagement with the National Land Commission to ensure timely transmission of funds to proje....
|
INFRASTRUCTURE | Ongoing | 236,145,787,710.00 | Ksh 1,215,078,094.00 |
0.5%
|
42.2%
|
Medium |
-none | Insecurity within the project area. Land acquisition and compensation. Potential community demands along the alignment. | Logging activities & Overloading along Gatakaini – Njabini (B20) road coupled with rainy conditions neccesitating repeated maintainance operations. In...
|
-none | - | Engagement of a security liason and Kenya Defense Forces. Engagement with the National Land Commission to ensure timely transmission of funds to proje...
|