These settings are saved on this browser.
Explore public projects using searchable filters, executive KPIs, Apache ECharts dashboards, cluster analytics, risk indicators, budget absorption views, and downloadable filtered reports.
This section translates project records into simple public-facing insights for quick decision-making and accountability.
A quick breakdown of completion and ongoing delivery progress from the current filtered project set.
Filtered project status composition rendered using Apache ECharts.
National absorption compared with average performance.
Spent versus unspent value across the filtered portfolio.
Filtered project risk composition.
Cluster-level comparison of total budget and total spent.
Performance and absorption comparison for visible projects.
Top visible projects ranked by budget allocation.
| Project Name | Cluster | Status | Budget | Spent | Absorption | Performance | Risk | Challenges | Resolutions | Actions |
|---|---|---|---|---|---|---|---|---|---|---|
|
Construction of 6,000 km Roads
Project Construction of 6,000 km Roads under INFRASTRUCTURE Cluster is currently Ongoing. Average performance is 41.3%. Budget absorption is 0.5%. Key challenges: • Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection. | • Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection. | -none. Proposed resolutions: • Coordination with the National Land Commission. | -none | -.
|
INFRASTRUCTURE | Ongoing | Ksh 236,145,787,710.00 | Ksh 1,215,078,094.00 |
0.5%
|
41.3%
|
Medium |
• Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection. | • Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection. | -none
|
• Coordination with the National Land Commission. | -none | -
|