| Project Name | Cluster | Status | Budget | Spent | Absorption | Performance | Risk | Challenges | Resolutions | Actions |
|---|---|---|---|---|---|---|---|---|---|---|
|
Construction, Rehabilitation, and Operationalization of Ports
Project Construction, Rehabilitation, and Operationalization of Ports under INFRASTRUCTURE Cluster is currently Ongoing. Average performance is 43.3%. Budget absorption is 17.5%. Key challenges: None | none | • Resettlement of PAPs • Delay in getting concurrence from JICA • Delay in payment of advance payment. Proposed resolutions: None | none | • Continuous engagements with the Ministry of Roads & Transport and the National Treasury to ensure funding availability throughout project implementa....
|
INFRASTRUCTURE | Ongoing | 20,384,750,000.00 | Ksh 3,571,488,412.75 |
17.5%
|
43.3%
|
Medium |
None | none | • Resettlement of PAPs • Delay in getting concurrence from JICA • Delay in payment of advance payment
|
None | none | • Continuous engagements with the Ministry of Roads & Transport and the National Treasury to ensure funding availability throughout project implementa...
|