Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% | N/A | N/A | Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. |
| 18 Nov 2025 | Ongoing | 0.00 | 50.0% | The under-performance is due to the slow start of the financial year. | N/A | 3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity. |
| 08 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Limited budgetary provision | Increase budgetary allocation | underperformance due to delay on-boarding of contractors |
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of on-boarding contractors | Fast-track contractor engagement | Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4. |
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The underperformance is due to delayed disbursement of funding | N/A | Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024 |
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The underperformance is due to delayed disbursement of funding. | N/A | 350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo. |
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Inadequate funding | N/A | A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed. |