Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.
Raw report records returned by the selected filters.
Grouped public projects available in this detailed view.
Reports where implementation challenges were captured.
Reports containing responses, actions, or recommendations.
Summed expenditure across all filtered report entries.
Average performance score from the filtered records.
Share of report records with recorded challenges.
Share of report records with resolutions or recommendations.
Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.
Implementation status mix across the filtered public report records.
Try another project name, status, cluster, challenge, recommendation, or comment.
A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.
Issues slowing or affecting delivery
Responses and recommendations captured
Latest reported progress notes
Changes in the activation schedule and delays in importing fiber-related accessories led to prolonged procurement and implementation timelines, affecting project performance.
Improve project scheduling and coordination for network activation, strengthen procurement planning, engage suppliers early to mitigate importation delays, and establish contingency measures to minimize disruptions to implementation timelines.
The underachievement is attributed to changes in the schedule for activating links on the already installed fibre network, as well as delays in the importation of fiber-related accessories, which resulted in extended procurement and delivery timelines.
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
Fast tracking of implementation by applying measure to mitigate against the delays.
4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
The under-performance is due to the slow start of the financial year.
No resolution or recommendation recorded.
3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
Limited budgetary provision
Increase budgetary allocation
underperformance due to delay on-boarding of contractors
Lack of on-boarding contractors
Fast-track contractor engagement
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
Raw report history is kept here for users who need the full records.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 15 Jul 2026 | Ongoing | 1,000,000.00 | 80.0% |
Changes in the activation schedule and delays in importing fiber-related accessories led to prolonged procurement and implementation timelines, affecting project performance.
|
Improve project scheduling and coordination for network activation, strengthen procurement planning, engage suppliers early to mitigate importation delays, and establish contingency measures to minimize disruptions to implementation timelines.
|
The underachievement is attributed to changes in the schedule for activating links on the already installed fibre network, as well as delays in the importation of fiber-related accessories, which resulted in extended procurement and delivery timelines.
|
| 21 Apr 2026 | Ongoing | 10,000,000.00 | 82.0% |
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
|
Fast tracking of implementation by applying measure to mitigate against the delays.
|
4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
|
| 18 Nov 2025 | Ongoing | 0.00 | 50.0% |
The under-performance is due to the slow start of the financial year.
|
N/A
|
3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
|
| 08 Sep 2025 | Ongoing | 0.00 | 60.0% Derived from status |
Limited budgetary provision
|
Increase budgetary allocation
|
underperformance due to delay on-boarding of contractors
|
| 05 Aug 2025 | Ongoing | 0.00 | 60.0% Derived from status |
Lack of on-boarding contractors
|
Fast-track contractor engagement
|
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
|
| 27 Mar 2025 | Ongoing | 0.00 | 60.0% Derived from status |
The underperformance is due to delayed disbursement of funding
|
N/A
|
Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
|
| 27 Mar 2025 | Ongoing | 0.00 | 60.0% Derived from status |
The underperformance is due to delayed disbursement of funding.
|
N/A
|
350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
|
| 27 Mar 2025 | Ongoing | 0.00 | 60.0% Derived from status |
Inadequate funding
|
N/A
|
A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.
|