Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
9

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
9

Reports where implementation challenges were captured.

With Resolutions
9

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
11,000,000.00

Summed expenditure across all filtered report entries.

%
Average Performance
55.5%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

9 Total Records
Pipeline
0.0% share
0
Ongoing
100.0% share
9
Stalled
0.0% share
0
Completed
0.0% share
0

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

UB

Universal Broadband Connectivity (100,000 km Fibre Optic Cable)

Cluster: INFRASTRUCTURE | Last Updated: 15 Jul 2026
Ongoing Medium Risk Ongoing
Budget
3,202,060,000.00
Spent
11,000,000.00
Absorption
0.3%
Performance
55.5%
Overall Performance
55.5%
Score
Budget Absorption
0.3%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
9 of 9 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 8 Actions 4 Coverage 50.0%
!
Key Challenges

Issues slowing or affecting delivery

Changes in the activation schedule and delays in importing fiber-related accessories led to prolonged procurement and implementation timelines, affecting project performance.
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
The under-performance is due to the slow start of the financial year.
Limited budgetary provision
Lack of on-boarding contractors
The underperformance is due to delayed disbursement of funding
The underperformance is due to delayed disbursement of funding.
Inadequate funding
Actions / Resolutions

Responses and recommendations captured

Improve project scheduling and coordination for network activation, strengthen procurement planning, engage suppliers early to mitigate importation delays, and establish contingency measures to minimize disruptions to implementation timelines.
Fast tracking of implementation by applying measure to mitigate against the delays.
Increase budgetary allocation
Fast-track contractor engagement
Comments / Outcomes

Latest reported progress notes

The underachievement is attributed to changes in the schedule for activating links on the already installed fibre network, as well as delays in the importation of fiber-related accessories, which resulted in extended procurement and delivery timelines.
,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
underperformance due to delay on-boarding of contractors
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
15 Jul 2026

Changes in the activation schedule and delays in importing fiber-related accessories led to prolonged procurement and implementation timelines, affecting project performance.

Action
Resolution / recommendation

Improve project scheduling and coordination for network activation, strengthen procurement planning, engage suppliers early to mitigate importation delays, and establish contingency measures to minimize disruptions to implementation timelines.

Outcome
Ongoing

The underachievement is attributed to changes in the schedule for activating links on the already installed fibre network, as well as delays in the importation of fiber-related accessories, which resulted in extended procurement and delivery timelines.

!
Challenge
21 Apr 2026

Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[

Action
Resolution / recommendation

Fast tracking of implementation by applying measure to mitigate against the delays.

Outcome
Ongoing

4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.

!
Challenge
18 Nov 2025

The under-performance is due to the slow start of the financial year.

Action
Resolution / recommendation

No resolution or recommendation recorded.

Outcome
Ongoing

3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.

!
Challenge
08 Sep 2025

Limited budgetary provision

Action
Resolution / recommendation

Increase budgetary allocation

Outcome
Ongoing

underperformance due to delay on-boarding of contractors

!
Challenge
05 Aug 2025

Lack of on-boarding contractors

Action
Resolution / recommendation

Fast-track contractor engagement

Outcome
Ongoing

Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 9 of 9
Date Status Amount Spent Performance Challenges Recommendations Comments
15 Jul 2026 Ongoing 1,000,000.00 80.0%
Changes in the activation schedule and delays in importing fiber-related accessories led to prolonged procurement and implementation timelines, affecting project performance.
Improve project scheduling and coordination for network activation, strengthen procurement planning, engage suppliers early to mitigate importation delays, and establish contingency measures to minimize disruptions to implementation timelines.
The underachievement is attributed to changes in the schedule for activating links on the already installed fibre network, as well as delays in the importation of fiber-related accessories, which resulted in extended procurement and delivery timelines.
21 Apr 2026 Ongoing 10,000,000.00 82.0%
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
Fast tracking of implementation by applying measure to mitigate against the delays.
4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
11 Feb 2026 Ongoing 0.00 10.0%
N/A
N/A
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
18 Nov 2025 Ongoing 0.00 50.0%
The under-performance is due to the slow start of the financial year.
N/A
3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
08 Sep 2025 Ongoing 0.00 60.0% Derived from status
Limited budgetary provision
Increase budgetary allocation
underperformance due to delay on-boarding of contractors
05 Aug 2025 Ongoing 0.00 60.0% Derived from status
Lack of on-boarding contractors
Fast-track contractor engagement
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
27 Mar 2025 Ongoing 0.00 60.0% Derived from status
The underperformance is due to delayed disbursement of funding
N/A
Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
27 Mar 2025 Ongoing 0.00 60.0% Derived from status
The underperformance is due to delayed disbursement of funding.
N/A
350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
27 Mar 2025 Ongoing 0.00 60.0% Derived from status
Inadequate funding
N/A
A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.