Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 21 Apr 2026 | Ongoing | 10,000,000.00 | 82.0% |
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
|
Fast tracking of implementation by applying measure to mitigate against the delays.
|
4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
|
| 18 Nov 2025 | Ongoing | 0.00 | 50.0% |
The under-performance is due to the slow start of the financial year.
|
N/A
|
3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
|
| 08 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Limited budgetary provision
|
Increase budgetary allocation
|
underperformance due to delay on-boarding of contractors
|
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Lack of on-boarding contractors
|
Fast-track contractor engagement
|
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The underperformance is due to delayed disbursement of funding
|
N/A
|
Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The underperformance is due to delayed disbursement of funding.
|
N/A
|
350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Inadequate funding
|
N/A
|
A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.
|