Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

7

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

7

Issues reported
Reports With Resolutions

7

Action points provided
Total Amount Spent

0.00

Sum of filtered report expenditure
Average Performance

30.0%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
7
Stalled
0
Completed
0
Universal Broadband Connectivity (100,000 km Fibre Optic Cable)
Cluster: INFRASTRUCTURE | Last Updated: 11 Feb 2026
Ongoing Medium Risk Ongoing
Budget
3,202,060,000.00
Spent
0.00
Absorption
0.0%
Performance
30.0%
Overall Performance
30.0%
Performance
Budget Absorption
0.0%
Spent against total budget
Report Volume
7 entries
Scaled visual of entry count
Challenges
• None
• The under-performance is due to the slow start of the financial year.
• Limited budgetary provision
• Lack of on-boarding contractors
• The underperformance is due to delayed disbursement of funding
• The underperformance is due to delayed disbursement of funding.
• Inadequate funding
Resolutions
• None
• Increase budgetary allocation
• Fast-track contractor engagement
Comments
• Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
• 3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
• underperformance due to delay on-boarding of contractors
• Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
• Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
• 350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
• A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.
Budget Notes
No budget notes recorded.
Raw Report Entries
7 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
11 Feb 2026 Ongoing 0.00 10.0% N/A N/A Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
18 Nov 2025 Ongoing 0.00 50.0% The under-performance is due to the slow start of the financial year. N/A 3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
Limited budgetary provision Increase budgetary allocation underperformance due to delay on-boarding of contractors
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Lack of on-boarding contractors Fast-track contractor engagement Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
The underperformance is due to delayed disbursement of funding N/A Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
The underperformance is due to delayed disbursement of funding. N/A 350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Inadequate funding N/A A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.