Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.

Reports Viewed

8

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

8

Issues reported
Reports With Resolutions

8

Action points provided
Total Amount Spent

10,000,000.00

Sum of filtered report expenditure
Average Performance

47.3%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
8
Stalled
0
Completed
0
Universal Broadband Connectivity (100,000 km Fibre Optic Cable)
Cluster: INFRASTRUCTURE | Last Updated: 21 Apr 2026
Ongoing Medium Risk Ongoing
Budget
3,202,060,000.00
Spent
10,000,000.00
Absorption
0.3%
Performance
47.3%
Overall Performance
47.3%
Performance
Budget Absorption
0.3%
Spent against total budget
Report Volume
Showing 8 of 8 entries
Scaled visual of entry count
Challenges
• Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
• None
• The under-performance is due to the slow start of the financial year.
• Limited budgetary provision
• Lack of on-boarding contractors
• The underperformance is due to delayed disbursement of funding
• The underperformance is due to delayed disbursement of funding.
• Inadequate funding
Resolutions
• Fast tracking of implementation by applying measure to mitigate against the delays.
• None
• Increase budgetary allocation
• Fast-track contractor engagement
Comments
• 4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
• Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
• 3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
• underperformance due to delay on-boarding of contractors
• Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
• Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
• 350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
• A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.
Budget Notes
No budget notes recorded.
Raw Report Entries
Showing 8 of 8 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
21 Apr 2026 Ongoing 10,000,000.00 82.0%
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network. The slow progress is attributable to delays in the importation of fibre-related accessories, resulting in extended procurement and delivery timelines[
Fast tracking of implementation by applying measure to mitigate against the delays.
4,100 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
11 Feb 2026 Ongoing 0.00 10.0%
N/A
N/A
Under achievement is due to the change of schedule on the activation of links on the already installed fibre network.
18 Nov 2025 Ongoing 0.00 50.0%
The under-performance is due to the slow start of the financial year.
N/A
3,703 Kms of fibre was laid across the Country to facilitate provision of internet connectivity.
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
Limited budgetary provision
Increase budgetary allocation
underperformance due to delay on-boarding of contractors
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Lack of on-boarding contractors
Fast-track contractor engagement
Underperformance is due to delay in the on-boarding of the contractors to undertake the last mile connectivity. Mitigation measures are under implementation to fast track contractor engagement and recover lost time in Q4.
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
The underperformance is due to delayed disbursement of funding
N/A
Cumulatively 3,254 Kms of Fibre Optic Cable installed for internet connectivity across the Country since FY 2023/2024
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
The underperformance is due to delayed disbursement of funding.
N/A
350 Km installed under Universal Service Fund (USF) for internet connectivity in Elgeyo, Samburu and Baringo.
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Inadequate funding
N/A
A s per MTP IV the target is to install 20,000 Km annually. Cumulatively, 22,486 Km of fibre have been installed.