Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

11

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

10

Issues reported
Reports With Resolutions

11

Action points provided
Total Amount Spent

3,500,008,424.55

Sum of filtered report expenditure
Average Performance

48.3%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
11
Stalled
0
Completed
0
Provision of Financing to MSMEs (Hustler Fund)
Cluster: FINANCE AND PRODUCTION | Last Updated: 10 Feb 2026
Ongoing Medium Risk Ongoing
Budget
7,300,000,000.00
Spent
3,500,008,424.55
Absorption
47.9%
Performance
48.3%
Overall Performance
48.3%
Performance
Budget Absorption
47.9%
Spent against total budget
Report Volume
11 entries
Scaled visual of entry count
Challenges
• None
• N/A
• inadequate allocation
Resolutions
• Request for more funding from the Exchequer to cater for the growing demand
• None
• N/A
• On track
• timely allocation
Comments
• Target For FY2025/26 Changed from 2.5 Billion to 4 Billion per Quarter. The state Department introduced 'Bridge Loan' Product to cater for demand. This requires provision of more funding
• Targets surpassed due increased borrowing of the loan products by MSMEs
• Total amounts disbursed in Q1 and Q2
• There were no funds from Exchequer to be disbursed to MSMEs in the fourth quarter, the whole amount was offered in quarters 1 and 2
• None
• The fund received only one Billion from the exchequer which is below the expected target
• Target achieved
• Target Achieved
• inadequate allocation
Budget Notes
No budget notes recorded.
Raw Report Entries
11 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
10 Feb 2026 Ongoing 4,247.00 85.0% N/A Request for more funding from the Exchequer to cater for the growing demand Target For FY2025/26 Changed from 2.5 Billion to 4 Billion per Quarter. The state Department introduced 'Bridge Loan' Product to cater for demand. This requires provision of more funding
09 Feb 2026 Ongoing 4,177.55 50.0% N/A N/A Targets surpassed due increased borrowing of the loan products by MSMEs
08 Oct 2025 Ongoing 0.00 10.0% N/A N/A Total amounts disbursed in Q1 and Q2
06 Aug 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A There were no funds from Exchequer to be disbursed to MSMEs in the fourth quarter, the whole amount was offered in quarters 1 and 2
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A The fund received only one Billion from the exchequer which is below the expected target
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Target achieved
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Target achieved
25 Feb 2025 Ongoing 2,500,000,000.00 60.0%
Derived from status
N/A N/A Target achieved
20 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A On track Target Achieved
19 Feb 2025 Ongoing 1,000,000,000.00 60.0%
Derived from status
inadequate allocation timely allocation inadequate allocation