Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.
Raw report records returned by the selected filters.
Grouped public projects available in this detailed view.
Reports where implementation challenges were captured.
Reports containing responses, actions, or recommendations.
Summed expenditure across all filtered report entries.
Average performance score from the filtered records.
Share of report records with recorded challenges.
Share of report records with resolutions or recommendations.
Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.
Implementation status mix across the filtered public report records.
Try another project name, status, cluster, challenge, recommendation, or comment.
A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.
Issues slowing or affecting delivery
Responses and recommendations captured
Latest reported progress notes
Ensuring the facility performs as intended during the operation and maintenance period, including timely maintenance and prompt resolution of any defects.
Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
The projects were completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
Lengthy approval of financing agreements.
Enhance bilateral engagement between the Ministry of Information, Communications and the Digital Economy, National Treasury and the Government of South Korea.
The Export-Import Bank of Korea is reviewing the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing.
Maintaining optimal performance of the facility during the operation and maintenance phase.
Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
The project was completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
Inadequate financing for infrastructure projects.
Leverage Public-Private Partnerships (PPP's) to mobilize private sector investment, financing, and expertise for the development, operation, and maintenance of critical infrastructure and strategic projects
The project feasibility study will be updated in Q2 of the FY 2026/27 to enable the Authority, in collaboration with the PPP Directorate of the National Treasury, to competitively advertise the project.
Concurrent finishing works require effective coordination to avoid delays and quality issues.
Enhance work coordination and monitor progress closely to complete the remaining finishing works on schedule.
Ongoing
Raw report history is kept here for users who need the full records.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 16 Jul 2026 | Completed | 6,925,373,738.00 | 100.0% |
N/A
|
N/A
|
The project has been compleited
|
| 15 Jul 2026 | Completed | 1,000,000.00 | 100.0% |
Ensuring the facility performs as intended during the operation and maintenance period, including timely maintenance and prompt resolution of any defects.
|
Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
|
The projects were completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
|
| 15 Jul 2026 | Ongoing | 100,000.00 | 0.0% |
Lengthy approval of financing agreements.
|
Enhance bilateral engagement between the Ministry of Information, Communications and the Digital Economy, National Treasury and the Government of South Korea.
|
The Export-Import Bank of Korea is reviewing the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing.
|
| 15 Jul 2026 | Completed | 1,000,000.00 | 100.0% |
Maintaining optimal performance of the facility during the operation and maintenance phase.
|
Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
|
The project was completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
|
| 15 Jul 2026 | Pipeline | 1,000,000.00 | 0.0% |
Inadequate financing for infrastructure projects.
|
Leverage Public-Private Partnerships (PPP's) to mobilize private sector investment, financing, and expertise for the development, operation, and maintenance of critical infrastructure and strategic projects
|
The project feasibility study will be updated in Q2 of the FY 2026/27 to enable the Authority, in collaboration with the PPP Directorate of the National Treasury, to competitively advertise the project.
|
| 15 Jul 2026 | Ongoing | 1,000,000.00 | 100.0% |
Concurrent finishing works require effective coordination to avoid delays and quality issues.
|
Enhance work coordination and monitor progress closely to complete the remaining finishing works on schedule.
|
N/A
|
| 14 Jul 2026 | Ongoing | 100,000.00 | 78.0% |
Delays in completing finishing works may postpone project completion and commissioning.
|
Expedite the procurement and delivery of finishing materials. Regular progress monitoring should be undertaken to avoid further delays.
|
The project has made significant progress, achieving 78% physical completion. Structural works are substantially complete, and the remaining activities are mainly finishing works on the 1st and 2nd floors.
|
| 16 Jun 2026 | Completed | 0.00 | 100.0% |
No challenge
|
No Recomendations
|
The project was completed in FY 2024/25, commissioned in October 2025, and is fully operational.
|
| 21 Apr 2026 | Ongoing | 0.00 | 96.0% |
N/A
|
Finalization of the pending activities to allow for completion and operationalization of the Centre.
|
The Disaster Recovery Data Centre is at 96% completion level. System acceptance, handover and customer onboarding and service activation planned
|
| 21 Apr 2026 | Completed | 0.00 | 100.0% |
N/A
|
N/A
|
Project completed in FY 2024/25
|