Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.

Reports Viewed

50

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

50

Issues reported
Reports With Resolutions

50

Action points provided
Total Amount Spent

2,856,534,133.00

Sum of filtered report expenditure
Average Performance

62.1%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
45
Stalled
0
Completed
5
Promotion of Konza Technopolis as a Silicon Savanna
Cluster: INFRASTRUCTURE | Last Updated: 21 Apr 2026
Ongoing Medium Risk Ongoing Completed
Budget
35,821,380,000.00
Spent
2,856,534,133.00
Absorption
8.0%
Performance
62.1%
Overall Performance
62.1%
Performance
Budget Absorption
8.0%
Spent against total budget
Report Volume
Showing 10 of 50 entries
Scaled visual of entry count
Challenges
• None
• Project slowed down due to unavailability of funds.
• The project stalled at 76% level of completion due to funding challenges.
• Delays in Exchequer release
• Project at the tendering stage
• Delays in Approvals of the Concept Note
• Project affected by budget rationalization in FY 2024/25
• The project is complete and is on the 12-months Defects Notification Period. Performance certificate will be issued on expiry of the Defects Notification Period.
• This output is planned for FY 2025/26
• The project is planned for implementation in FY 2025/26 after completion of the ongoing preliminaries.
Resolutions
• Finalization of the pending activities to allow for completion and operationalization of the Centre.
• None
• Review of the Project Concept Note to all for project funding through the PPP framework
• Project Concept Note revised to reflect updates in the project scope and subsequently submitted to the National Treasury for review and consideration for funding.
• none
• Fast track the release of Exchequer
• Fastrack the tendering process
• Fastrack approvals of the concept note
• Secure additional funds from National Treasury
Comments
• The Disaster Recovery Data Centre is at 96% completion level. System acceptance, handover and customer onboarding and service activation planned
• Project completed in FY 2024/25
• The project feasibility study will be updated in Q4 to reflect the conditions of the project and enable the KoTDA together with the PPP Directorate, to competitively advertise the project.
• The Export-Import Bank of Korea commenced review of the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing and requested completion of the Kenya-AIST project closure before progressing the Digital Media Centre project.
• KoTDA revised the Project Concept Note to reflect updates in the project scope and subsequently submitted the revised version to the National Treasury for review and consideration.
• The Export-Import Bank of Korea is in the process of reviewing financing framework for the Project with an aim of transitioning project financing model from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing
• The Disaster Recovery Data Centre is at 96 percent completion, with system acceptance, handover, customer onboarding, and service activation scheduled for Q3 and Q4 of FY 2025/26.
• Target achieved
• Project completed in FY 2024/25)
• KoTDA submitted the Project Concept Note to the National Treasury (PPP Directorate) for consideration and was guided to update the project feasibility study to support market sounding and engagement with potential investors.
• The projects were completed in FY 2024/25 and operational. Commissioning was undertaken in October 2025
• The project is at 76 percent completion since FY 2023/24 due to financial challenges. Following the review of the Project Concept Note by the National Treasury, KoTDA was guided to accelerate implementation and complete the contracted project activities before introducing any additional scope.
• A Financing Agreement was signed in June 2024 between the Government of Kenya and the Export-Import Bank of Korea. The Authority is awaiting a No Objection from the Korean Government to commence the procurement of the project consultant.
• In FY 2024/25, the Authority developed a Project Concept Note to facilitate Public-Private Partnership (PPP) engagement. The Concept Note is currently under review by the PPP Directorate at the National Treasury.
• The project stalled at 76% level of completion due to funding challenges. KoTDA revised the Project Concept Note to reflect updates in the project scope and subsequently submitted the revised version to the National Treasury for review and consideration.
• The project feasibility study was finalized and the loan financing agreement between the government of Kenya and the Exim Bank of Korea signed
• The implementation of Smart City Facilities is complete
• Project concept note prepared and submitted to the National treasury
• The annual target was achieved in quarter II
• The project feasibility study was finalized and the loan financing agreement between the government of Kenya and the Exim Bank of Korea signed. The project is at consultant tendering stage.
• The project entails the installation of: i. Konza Complex CCTV & Wi-Fi-100%; ii. Smart City Facilities-IOC & Experience Center Fit out-92%; iii. Smart City Facilities-Platform IOC Platform, Smart pole, ITS, City Network, ROMA, Wi-Fi-80%; iv. Konza Smart City Facilities Street Scape Facilities Smart pole, - ITS (Checkpoint, traffic and ePolice)-99%; and v. Konza City Network & Fiber Works-95%.
• The horizontal infrastructure is complete and in use. The infrastructure constitutes streetscape and public utilities, street lighting, water distribution and treatment, 40km roads, landscaping, sewerage, parks, and ICT network. .
• The project is complete
• Concept note in preparation for PPP engagement. The project is planned for implementation in FY 2025/26.
• The annual Target achieved in Q2 due to a roll over funds.
• The project is at the feasibility study.
• At preliminary stage. This output is planned for FY 2024/25
• The project is on course being
• The project is complete and is on the 12-months Defects Notification Period. Performance certificate will be issued on expiry of the Defects Notification Period.
• This output is planned for FY 2025/26
• The project is planned for implementation in FY 2025/26 after completion of the ongoing preliminaries.
• The project is on course.
• Target Acheived
• None
Budget Notes
• the remaining balance has already been processed awaiting exchequre
Raw Report Entries
Showing 10 of 50 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
21 Apr 2026 Ongoing 0.00 96.0%
N/A
Finalization of the pending activities to allow for completion and operationalization of the Centre.
The Disaster Recovery Data Centre is at 96% completion level. System acceptance, handover and customer onboarding and service activation planned
21 Apr 2026 Completed 0.00 100.0%
N/A
N/A
Project completed in FY 2024/25
21 Apr 2026 Ongoing 0.00 0.0%
Project slowed down due to unavailability of funds.
Review of the Project Concept Note to all for project funding through the PPP framework
The project feasibility study will be updated in Q4 to reflect the conditions of the project and enable the KoTDA together with the PPP Directorate, to competitively advertise the project.
21 Apr 2026 Ongoing 0.00 0.0%
N/A
N/A
The Export-Import Bank of Korea commenced review of the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing and requested completion of the Kenya-AIST project closure before progressing the Digital Media Centre project.
21 Apr 2026 Ongoing 0.00 76.0%
The project stalled at 76% level of completion due to funding challenges.
Project Concept Note revised to reflect updates in the project scope and subsequently submitted to the National Treasury for review and consideration for funding.
KoTDA revised the Project Concept Note to reflect updates in the project scope and subsequently submitted the revised version to the National Treasury for review and consideration.
05 Mar 2026 Ongoing 0.00 10.0%
N/A
N/A
The Export-Import Bank of Korea is in the process of reviewing financing framework for the Project with an aim of transitioning project financing model from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing
24 Feb 2026 Completed 0.00 96.0%
N/A
N/A
The Disaster Recovery Data Centre is at 96 percent completion, with system acceptance, handover, customer onboarding, and service activation scheduled for Q3 and Q4 of FY 2025/26.
17 Feb 2026 Ongoing 2,718,532,083.00 84.0%
Delays in Exchequer release
Fast track the release of Exchequer
N/A
17 Feb 2026 Ongoing 0.00 100.0%
N/A
N/A
Target achieved
17 Feb 2026 Completed 13,800,205.00 85.0%
N/A
N/A
Project completed in FY 2024/25)