Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
58

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
58

Reports where implementation challenges were captured.

With Resolutions
58

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
9,786,107,871.00

Summed expenditure across all filtered report entries.

%
Average Performance
65.2%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

58 Total Records
Pipeline
1.7% share
1
Ongoing
82.8% share
48
Stalled
0.0% share
0
Completed
15.5% share
9

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

PO

Promotion of Konza Technopolis as a Silicon Savanna

Cluster: INFRASTRUCTURE | Last Updated: 16 Jul 2026
Completed Medium Risk Completed Ongoing Pipeline
Budget
35,821,380,000.00
Spent
9,786,107,871.00
Absorption
27.3%
Performance
65.2%
Overall Performance
65.2%
Score
Budget Absorption
27.3%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 58 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 7 Actions 8 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

Ensuring the facility performs as intended during the operation and maintenance period, including timely maintenance and prompt resolution of any defects.
Lengthy approval of financing agreements.
Maintaining optimal performance of the facility during the operation and maintenance phase.
Inadequate financing for infrastructure projects.
Concurrent finishing works require effective coordination to avoid delays and quality issues.
Delays in completing finishing works may postpone project completion and commissioning.
No challenge
Project slowed down due to unavailability of funds.
Actions / Resolutions

Responses and recommendations captured

Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
Enhance bilateral engagement between the Ministry of Information, Communications and the Digital Economy, National Treasury and the Government of South Korea.
Leverage Public-Private Partnerships (PPP's) to mobilize private sector investment, financing, and expertise for the development, operation, and maintenance of critical infrastructure and strategic projects
Enhance work coordination and monitor progress closely to complete the remaining finishing works on schedule.
Expedite the procurement and delivery of finishing materials. Regular progress monitoring should be undertaken to avoid further delays.
No Recomendations
Finalization of the pending activities to allow for completion and operationalization of the Centre.
Review of the Project Concept Note to all for project funding through the PPP framework
Comments / Outcomes

Latest reported progress notes

The project has been compleited
The projects were completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
The Export-Import Bank of Korea is reviewing the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing.
The project was completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
The project feasibility study will be updated in Q2 of the FY 2026/27 to enable the Authority, in collaboration with the PPP Directorate of the National Treasury, to competitively advertise the project.
The project has made significant progress, achieving 78% physical completion. Structural works are substantially complete, and the remaining activities are mainly finishing works on the 1st and 2nd floors.
The project was completed in FY 2024/25, commissioned in October 2025, and is fully operational.
The Disaster Recovery Data Centre is at 96% completion level. System acceptance, handover and customer onboarding and service activation planned
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
15 Jul 2026

Ensuring the facility performs as intended during the operation and maintenance period, including timely maintenance and prompt resolution of any defects.

Action
Resolution / recommendation

Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.

Outcome
Completed

The projects were completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.

!
Challenge
15 Jul 2026

Lengthy approval of financing agreements.

Action
Resolution / recommendation

Enhance bilateral engagement between the Ministry of Information, Communications and the Digital Economy, National Treasury and the Government of South Korea.

Outcome
Ongoing

The Export-Import Bank of Korea is reviewing the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing.

!
Challenge
15 Jul 2026

Maintaining optimal performance of the facility during the operation and maintenance phase.

Action
Resolution / recommendation

Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.

Outcome
Completed

The project was completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.

!
Challenge
15 Jul 2026

Inadequate financing for infrastructure projects.

Action
Resolution / recommendation

Leverage Public-Private Partnerships (PPP's) to mobilize private sector investment, financing, and expertise for the development, operation, and maintenance of critical infrastructure and strategic projects

Outcome
Pipeline

The project feasibility study will be updated in Q2 of the FY 2026/27 to enable the Authority, in collaboration with the PPP Directorate of the National Treasury, to competitively advertise the project.

!
Challenge
15 Jul 2026

Concurrent finishing works require effective coordination to avoid delays and quality issues.

Action
Resolution / recommendation

Enhance work coordination and monitor progress closely to complete the remaining finishing works on schedule.

Outcome
Ongoing

Ongoing

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 58
Date Status Amount Spent Performance Challenges Recommendations Comments
16 Jul 2026 Completed 6,925,373,738.00 100.0%
N/A
N/A
The project has been compleited
15 Jul 2026 Completed 1,000,000.00 100.0%
Ensuring the facility performs as intended during the operation and maintenance period, including timely maintenance and prompt resolution of any defects.
Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
The projects were completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
15 Jul 2026 Ongoing 100,000.00 0.0%
Lengthy approval of financing agreements.
Enhance bilateral engagement between the Ministry of Information, Communications and the Digital Economy, National Treasury and the Government of South Korea.
The Export-Import Bank of Korea is reviewing the project’s financing framework to transition from Economic Development Promotion Facility (EDPF) to Economic Cooperation Development Fund (EDCF) financing.
15 Jul 2026 Completed 1,000,000.00 100.0%
Maintaining optimal performance of the facility during the operation and maintenance phase.
Implement the operation and maintenance plan effectively, conduct regular inspections and preventive maintenance, address defects promptly, and monitor performance to ensure the facility remains functional and sustainable.
The project was completed in FY 2024/25, commissioned in October 2025, and are under operational and maintenance.
15 Jul 2026 Pipeline 1,000,000.00 0.0%
Inadequate financing for infrastructure projects.
Leverage Public-Private Partnerships (PPP's) to mobilize private sector investment, financing, and expertise for the development, operation, and maintenance of critical infrastructure and strategic projects
The project feasibility study will be updated in Q2 of the FY 2026/27 to enable the Authority, in collaboration with the PPP Directorate of the National Treasury, to competitively advertise the project.
15 Jul 2026 Ongoing 1,000,000.00 100.0%
Concurrent finishing works require effective coordination to avoid delays and quality issues.
Enhance work coordination and monitor progress closely to complete the remaining finishing works on schedule.
N/A
14 Jul 2026 Ongoing 100,000.00 78.0%
Delays in completing finishing works may postpone project completion and commissioning.
Expedite the procurement and delivery of finishing materials. Regular progress monitoring should be undertaken to avoid further delays.
The project has made significant progress, achieving 78% physical completion. Structural works are substantially complete, and the remaining activities are mainly finishing works on the 1st and 2nd floors.
16 Jun 2026 Completed 0.00 100.0%
No challenge
No Recomendations
The project was completed in FY 2024/25, commissioned in October 2025, and is fully operational.
21 Apr 2026 Ongoing 0.00 96.0%
N/A
Finalization of the pending activities to allow for completion and operationalization of the Centre.
The Disaster Recovery Data Centre is at 96% completion level. System acceptance, handover and customer onboarding and service activation planned
21 Apr 2026 Completed 0.00 100.0%
N/A
N/A
Project completed in FY 2024/25