Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
71

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
71

Reports where implementation challenges were captured.

With Resolutions
71

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
124,759,540,008.00

Summed expenditure across all filtered report entries.

%
Average Performance
25.0%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

71 Total Records
Pipeline
0.0% share
0
Ongoing
87.3% share
62
Stalled
0.0% share
0
Completed
12.7% share
9

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

PT

Power Transmission and distribution

Cluster: INFRASTRUCTURE | Last Updated: 07 May 2026
Ongoing Medium Risk Ongoing Completed
Budget
80,017,420,269.50
Spent
124,759,540,008.00
Absorption
155.9%
Performance
25.0%
Overall Performance
25.0%
Score
Budget Absorption
155.9%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 71 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 6 Actions 3 Coverage 50.0%
!
Key Challenges

Issues slowing or affecting delivery

Implementation affected by shortage of materials caused by delayed procurement of material.
Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.
Kenya Power’s achievement affected by delayed funding. Implementation by REREC affected by shortage of materials caused by delayed procurement of material.
Affected by delays in materials but the issue is now sorted
Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
Progress affected by limited availability of critical materials such as electricity meters. Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
The downward review of the power distribution budget affected the attainment of the target.
Actions / Resolutions

Responses and recommendations captured

Fast track disbursment of funds
Fast track disbursment of funds.
Promote local capacity in manufacturing of the materials. Exemption from eGP on procurement of the materials.
Promote local capacity in manufacture of the material. Exemption from eGP on procurement of the materials.
Seek other funding models such as counterpart funding or PPP.
Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of these materials
Increase local capacity on manufacture of these materials
Increase local capacity on manufacture of the materials
Comments / Outcomes

Latest reported progress notes

FATs (Factory acceptance tests) completed, shipping of materials ongoing. Line Construction has commenced; Project closure is expected by September 2026 for KOSAP Mini grids. Contract preparation ongoing for GoK funded Mini grids.
No target for this quarter
Target not achieved.
KPLC’s Q3 target was 253. The achievement was 77. REREC’s Q3 target was 238. The achievement was 38. Implementation affected by
Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC
Kenya Power installed 636 while REREC installed 260 in Q3.
To be reported in Q4
Pre commissioning tests on going for kimuka substation
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
07 May 2026

Implementation affected by shortage of materials caused by delayed procurement of material.

Action
Resolution / recommendation

No resolution or recommendation recorded.

Outcome
Ongoing

Target not achieved.

!
Challenge
07 May 2026

Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.

Action
Resolution / recommendation

Fast track disbursment of funds

Outcome
Ongoing

KPLC’s Q3 target was 253. The achievement was 77. REREC’s Q3 target was 238. The achievement was 38. Implementation affected by

!
Challenge
07 May 2026

Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.

Action
Resolution / recommendation

No resolution or recommendation recorded.

Outcome
Ongoing

Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC

!
Challenge
07 May 2026

Kenya Power’s achievement affected by delayed funding. Implementation by REREC affected by shortage of materials caused by delayed procurement of material.

Action
Resolution / recommendation

Fast track disbursment of funds.

Outcome
Ongoing

Kenya Power installed 636 while REREC installed 260 in Q3.

!
Challenge
07 May 2026

Affected by delays in materials but the issue is now sorted

Action
Resolution / recommendation

No resolution or recommendation recorded.

Outcome
Ongoing

To be reported in Q4

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 71
Date Status Amount Spent Performance Challenges Recommendations Comments
07 May 2026 Ongoing 1.00 0.0%
N/A
N/A
FATs (Factory acceptance tests) completed, shipping of materials ongoing. Line Construction has commenced; Project closure is expected by September 2026 for KOSAP Mini grids. Contract preparation ongoing for GoK funded Mini grids.
07 May 2026 Completed 1.00 0.0%
N/A
N/A
No target for this quarter
07 May 2026 Ongoing 1.00 8.0%
Implementation affected by shortage of materials caused by delayed procurement of material.
N/A
Target not achieved.
07 May 2026 Ongoing 1.00 3.0%
Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
Fast track disbursment of funds
KPLC’s Q3 target was 253. The achievement was 77. REREC’s Q3 target was 238. The achievement was 38. Implementation affected by
07 May 2026 Ongoing 1.00 94.0%
Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.
N/A
Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC
07 May 2026 Ongoing 1.00 24.0%
Kenya Power’s achievement affected by delayed funding. Implementation by REREC affected by shortage of materials caused by delayed procurement of material.
Fast track disbursment of funds.
Kenya Power installed 636 while REREC installed 260 in Q3.
07 May 2026 Ongoing 1.00 0.0%
N/A
N/A
To be reported in Q4
07 May 2026 Ongoing 0.00 0.0%
Affected by delays in materials but the issue is now sorted
N/A
To be reported in Q4
07 May 2026 Ongoing 1.00 0.0%
N/A
N/A
Pre commissioning tests on going for kimuka substation
18 Feb 2026 Ongoing 5,726,700,000.00 81.0%
Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
Promote local capacity in manufacturing of the materials. Exemption from eGP on procurement of the materials.
Target not achieved.