Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

62

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

62

Issues reported
Reports With Resolutions

62

Action points provided
Total Amount Spent

124,759,540,000.00

Sum of filtered report expenditure
Average Performance

26.6%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
54
Stalled
0
Completed
8
Power Transmission and distribution
Cluster: INFRASTRUCTURE | Last Updated: 18 Feb 2026
Ongoing Medium Risk Ongoing Completed
Budget
80,017,420,269.50
Spent
124,759,540,000.00
Absorption
155.9%
Performance
26.6%
Overall Performance
26.6%
Performance
Budget Absorption
155.9%
Spent against total budget
Report Volume
62 entries
Scaled visual of entry count
Challenges
• Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
• Progress affected by limited availability of critical materials such as electricity meters. Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
• The downward review of the power distribution budget affected the attainment of the target.
• Affected by budget rationalization.
• Affected by budget rationalization
• Implementation affected by budget rationalization and shortage of materials caused by introduction of eGP requirement which delayed procurement of material.
• Target not achieved due to delays in disbursement of funds.
• The unavailability of street lighting materials slowed down the installation of lanterns.
• The unavailability of street lighting materials affected the installation of lanterns. Procurement of the same is in progress to enable achievement of target during Q3.
• Affected by budget rationalization in the beginning of the FY
• Implementation affected by shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
• Affected by budget rationalization and shortage of materials caused by introduction of eGP requirement which delayed procurement of material.
• Affected by budget rationalization and shortage of materials
• Affected by budget rationalization and availability of materials.
• Project affected by land acquisition challenges for the KOSAP minigrids
• Project affected by land acquisition challenges during project inception
• None
• Affected by budget rationalization at the beginning of the FY.
• Affected by budget rationalization and challenges in wayleave acquisition
• The under achievement was caused by delays in procurement of critical materials due to non responsive tenders and financial challenges.
• There was delay in disbursement of budget by the National Treasury which affected progress in payments for works.
• Kosap Mini-grids under REREC reduced to 31 due to budget rationalization. Award of contract done.
• None as the project pre requisite requirements are being undertaken
• Commissioning Mariakani substation delayed by pending payments to contractor.
Resolutions
• Promote local capacity in manufacturing of the materials. Exemption from eGP on procurement of the materials.
• Promote local capacity in manufacture of the material. Exemption from eGP on procurement of the materials.
• Seek other funding models such as counterpart funding or PPP.
• Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of these materials
• Increase local capacity on manufacture of these materials
• Increase local capacity on manufacture of the materials
• Exemption from eGP on procurement of materials
• Exemption from eGP for procurement of the materials.
• Exemption from eGP for the specific materials
• Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of some of the materials.
• Release of exchequer to support the acqquisition process.
• None
• Pursue alternative funding models such as PPP
• Pursue alternative funding models such as Public Private Partnerships (PPP)
• Release exchequer
Comments
• Target not achieved.
• Target not achieved
• Quarterly target not achieved.
• 112 projects were commissioned during the period by REREC.
• 46 projects under GOK were commissioned during the quarter. This comprised 9 New projects from FY 2024/25 and 37 under Works-in-Progress from previous financial year (carry-forward), Cumulatively 13 New and 137 Carry Forward Public Facilities were commissioned during the period. 15 Projects commissioned under BADEA and 0 under OFID funding. Cumulatively 27 projects commissioned during the Period - 22 under BADEA and 5 under OFID/KEEP
• A total of 86 Public Facilities projects were completed during the quarter. These targets and achievements include projects carried forward from previous years.
• Achievement due to availability of some materials and contribution of Matching funds by Counties and Constituencies for project implementation.
• 33 projects were commissioned during the period by REREC. 3 were installed by KPLC funded by AFD/EU/EIB.
• The commisioning of 168 public facilty transformers carried forward from the previous years.
• A total of 78 Transformer Maximization projects were completed during the quarter. These targets and achievements include projects carried forward from previous years.
• 4 new project commissioned from FY 2024/25 and 60 (carry-forward) from previous financial year. Cumulatively 5 New and 168 Carry Forward Public Facilities were commissioned during the period.
• REREC commissioned Ngothe and Takawiri in Homa Bay County in Q2. 3 other mini-grids were in progress. Kosap Mini-grids under REREC reduced to 31 due to budget. Tendering completed, WB No Objection received and Award done
• REREC commissioned Mageta Island Hybrid Mini-Grid Station in Siaya County in Q1
• KOSAP Mini grids - Tendering completed, WB No Objection received and Award done under 6 Lots Contracts signed. Inception meeting done on 26/03/2025 GoK- Dadajabula solar mini-grid-tendering complete, contracting in progress.
• Two substations were completed and energized: 400/220kV 4x200MVA Mariakani and 132/33kV 1x23MVA Kabarnet.
• Completed are Turkwel, Ortum and Mariakani.
• Target could not be met as a result of lack of funds for both contractor and wayleaves acquisition for the Kenya power Transmission Improvement project where we were to realize the 43km,.
• The over achievement is due to availability of critical materials and counter funding from counties.The total number of distribution lines constructed in the whole FY is 5291.35KM with 4791KM done by REREC and 500KM done by KPLC
• Target achieved
• 78km circuit length of the 220KV Ortum-Kitale line,29km of the 132KV Awendo-Isebania line,192km circuit length of the 96KM 400kV Kenya – Tanzania Interconnector and 107.5km 132kV Sultan Hamud – Merueshi-Loitoktok transmission lines completed and energized during the FY 2024/25
• 132/33Kv Isebania substation completed in Q3 but energized in Q4
• 220/132KV Kitale completed and energized
• 32/33kV Loitoktok completed and energized
• To be reported in Q4
• 33/11kv Kapsumbuweio,33/11kv Maralal,33kv Nrok-Bomet interconnector ,B2 Oyugis and Retrofitting of diesel minigrids with solar (Hybridization)Merti power stations were completed during the year.
• 132/33Kv Isebania substation complete to be energized in Q4
• REREC commissioned Mageta Island Hybrid Mini-Grid Station in Siaya County in Q1 and Ngothe and Takawiri in Homa Bay County in Q2. 3 other mini-grids were in progress.
• KOSAP - Site handed over; Advance Payment done; Review of design drawings ongoing (Approvals to be done by Mid-October 2025) GoK - Land acquisition and designs completed, Tendering expected in Q2.
• 1) KOSAP - Site handed over; Advance Payment done; Contractor Environmental and Social Safeguard Training done. Review of design drawings for Solar Photovoltaic Generation Plants completed and approved. Contractor's change of manufacturers request Approved. 2) GoK - Land acquisition and designs completed, Tendering - in progress for 1 (Advertised and evaluation ongoing) and Tendering expected in Q3 for another one.
• Commissioning of Konza substation pending re-routing of 400kV Mombasa-Nairobi line around Isinya substation to allow completion of Isinya-Konza line.
• Land acquisition in progress
Budget Notes
• Expenditure includes transformers installed and construction of transmission lines
Raw Report Entries
62 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
18 Feb 2026 Ongoing 5,726,700,000.00 81.0% Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off. Promote local capacity in manufacturing of the materials. Exemption from eGP on procurement of the materials. Target not achieved.
18 Feb 2026 Ongoing 2,034,000,000.00 74.0% Progress affected by limited availability of critical materials such as electricity meters. Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off. Promote local capacity in manufacture of the material. Exemption from eGP on procurement of the materials. Target not achieved.
18 Feb 2026 Ongoing 9,439,990,000.00 62.0% The downward review of the power distribution budget affected the attainment of the target. Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 4,107,000,000.00 62.0% Affected by budget rationalization. Seek other funding models such as counterpart funding or PPP. Quarterly target not achieved.
18 Feb 2026 Ongoing 2,300,000,000.00 60.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 2,000,000,000.00 62.0% Affected by budget rationalization. Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 17,261,000,000.00 80.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 120,810,000.00 14.0% Implementation affected by budget rationalization and shortage of materials caused by introduction of eGP requirement which delayed procurement of material. Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of these materials Target not achieved.
18 Feb 2026 Ongoing 0.00 10.0% Target not achieved due to delays in disbursement of funds. Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 297,800,000.00 52.0% The unavailability of street lighting materials slowed down the installation of lanterns. Increase local capacity on manufacture of these materials Target not achieved
18 Feb 2026 Ongoing 0.00 46.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 0.00 22.0% The unavailability of street lighting materials affected the installation of lanterns. Procurement of the same is in progress to enable achievement of target during Q3. Increase local capacity on manufacture of these materials Target not achieved
18 Feb 2026 Ongoing 0.00 36.0% The unavailability of street lighting materials slowed down the installation of lanterns. Increase local capacity on manufacture of the materials Quarterly target not achieved.
18 Feb 2026 Ongoing 294,000,000.00 39.0% Affected by budget rationalization in the beginning of the FY Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 6,400,000.00 1.0% Implementation affected by budget rationalization and shortage of materials caused by introduction of eGP requirement which delayed procurement of material. Exemption from eGP on procurement of materials Target not achieved.
18 Feb 2026 Ongoing 0.00 1.0% Implementation affected by shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off. Exemption from eGP for procurement of the materials. 112 projects were commissioned during the period by REREC.
18 Feb 2026 Ongoing 0.00 2.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. 46 projects under GOK were commissioned during the quarter. This comprised 9 New projects from FY 2024/25 and 37 under Works-in-Progress from previous financial year (carry-forward), Cumulatively 13 New and 137 Carry Forward Public Facilities were commissioned during the period. 15 Projects commissioned under BADEA and 0 under OFID funding. Cumulatively 27 projects commissioned during the Period - 22 under BADEA and 5 under OFID/KEEP
18 Feb 2026 Ongoing 0.00 1.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. A total of 86 Public Facilities projects were completed during the quarter. These targets and achievements include projects carried forward from previous years.
18 Feb 2026 Ongoing 290,000,000.00 1.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. 46 projects under GOK were commissioned during the quarter. This comprised 9 New projects from FY 2024/25 and 37 under Works-in-Progress from previous financial year (carry-forward), Cumulatively 13 New and 137 Carry Forward Public Facilities were commissioned during the period. 15 Projects commissioned under BADEA and 0 under OFID funding. Cumulatively 27 projects commissioned during the Period - 22 under BADEA and 5 under OFID/KEEP
18 Feb 2026 Ongoing 18,080,000,000.00 3.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. Achievement due to availability of some materials and contribution of Matching funds by Counties and Constituencies for project implementation.
18 Feb 2026 Ongoing 0.00 0.0% Affected by budget rationalization Seek other funding models such as counterpart funding or PPP. Target not achieved
18 Feb 2026 Ongoing 4,320,000.00 0.0% Affected by budget rationalization and shortage of materials caused by introduction of eGP requirement which delayed procurement of material. Exemption from eGP for the specific materials Target not achieved
18 Feb 2026 Ongoing 0.00 1.0% Implementation affected by shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off. Exemption from eGP for the specific materials 33 projects were commissioned during the period by REREC. 3 were installed by KPLC funded by AFD/EU/EIB.
18 Feb 2026 Ongoing 2,636,000,000.00 3.0% Affected by budget rationalization and shortage of materials Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of some of the materials. The commisioning of 168 public facilty transformers carried forward from the previous years.
18 Feb 2026 Ongoing 0.00 2.0% Affected by budget rationalization and shortage of materials Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of some of the materials. A total of 78 Transformer Maximization projects were completed during the quarter. These targets and achievements include projects carried forward from previous years.
18 Feb 2026 Ongoing 825,000,000.00 1.0% Affected by budget rationalization and shortage of materials Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of some of the materials. 4 new project commissioned from FY 2024/25 and 60 (carry-forward) from previous financial year. Cumulatively 5 New and 168 Carry Forward Public Facilities were commissioned during the period.
18 Feb 2026 Ongoing 0.00 0.0% Affected by budget rationalization and shortage of materials Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of some of the materials. Target not achieved
18 Feb 2026 Ongoing 10,905,000,000.00 2.0% Affected by budget rationalization and availability of materials. Seek other funding models such as counterpart funding or PPP. Increase local capacity on manufacture of some of the materials. Target not achieved
18 Feb 2026 Ongoing 2,290,000.00 17.0% Project affected by land acquisition challenges for the KOSAP minigrids Release of exchequer to support the acqquisition process. REREC commissioned Ngothe and Takawiri in Homa Bay County in Q2. 3 other mini-grids were in progress. Kosap Mini-grids under REREC reduced to 31 due to budget. Tendering completed, WB No Objection received and Award done
18 Feb 2026 Ongoing 1,430,000.00 8.0% Project affected by land acquisition challenges for the KOSAP minigrids Release of exchequer to support the acqquisition process. REREC commissioned Mageta Island Hybrid Mini-Grid Station in Siaya County in Q1
18 Feb 2026 Ongoing 2,290,000.00 0.0% Project affected by land acquisition challenges during project inception Release of exchequer to support the acqquisition process. KOSAP Mini grids - Tendering completed, WB No Objection received and Award done under 6 Lots Contracts signed. Inception meeting done on 26/03/2025 GoK- Dadajabula solar mini-grid-tendering complete, contracting in progress.
18 Feb 2026 Completed 0.00 100.0% N/A N/A Two substations were completed and energized: 400/220kV 4x200MVA Mariakani and 132/33kV 1x23MVA Kabarnet.
18 Feb 2026 Ongoing 12,956,000,000.00 25.0% Affected by budget rationalization at the beginning of the FY. Pursue alternative funding models such as PPP Completed are Turkwel, Ortum and Mariakani.
18 Feb 2026 Ongoing 378,000,000.00 10.0% Affected by budget rationalization and challenges in wayleave acquisition Pursue alternative funding models such as Public Private Partnerships (PPP) Target could not be met as a result of lack of funds for both contractor and wayleaves acquisition for the Kenya power Transmission Improvement project where we were to realize the 43km,.
18 Feb 2026 Completed 275,220,000.00 100.0% N/A N/A The over achievement is due to availability of critical materials and counter funding from counties.The total number of distribution lines constructed in the whole FY is 5291.35KM with 4791KM done by REREC and 500KM done by KPLC
18 Feb 2026 Completed 6,237,000,000.00 100.0% N/A N/A Target achieved
18 Feb 2026 Completed 97,580,000.00 100.0% N/A N/A 78km circuit length of the 220KV Ortum-Kitale line,29km of the 132KV Awendo-Isebania line,192km circuit length of the 96KM 400kV Kenya – Tanzania Interconnector and 107.5km 132kV Sultan Hamud – Merueshi-Loitoktok transmission lines completed and energized during the FY 2024/25
18 Feb 2026 Completed 5,436,620,000.00 100.0% N/A N/A 132/33Kv Isebania substation completed in Q3 but energized in Q4
18 Feb 2026 Completed 0.00 100.0% N/A N/A 220/132KV Kitale completed and energized
18 Feb 2026 Completed 602,490,000.00 100.0% N/A N/A 32/33kV Loitoktok completed and energized
18 Feb 2026 Ongoing 1,120,190,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 134,650,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 4,826,160,000.00 71.0% The under achievement was caused by delays in procurement of critical materials due to non responsive tenders and financial challenges. N/A 33/11kv Kapsumbuweio,33/11kv Maralal,33kv Nrok-Bomet interconnector ,B2 Oyugis and Retrofitting of diesel minigrids with solar (Hybridization)Merti power stations were completed during the year.
18 Feb 2026 Ongoing 331,000,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 97,610,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Completed 6,898,000,000.00 100.0% N/A N/A Target achieved
18 Feb 2026 Ongoing 231,840,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 0.00 0.0% There was delay in disbursement of budget by the National Treasury which affected progress in payments for works. Release exchequer To be reported in Q4
18 Feb 2026 Ongoing 110,820,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 1,126,500,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 65,040,000.00 0.0% N/A N/A To be reported in Q4
18 Feb 2026 Ongoing 6,738,180,000.00 0.0% N/A N/A 132/33Kv Isebania substation complete to be energized in Q4
17 Feb 2026 Ongoing 0.00 0.0% Kosap Mini-grids under REREC reduced to 31 due to budget rationalization. Award of contract done. N/A REREC commissioned Mageta Island Hybrid Mini-Grid Station in Siaya County in Q1 and Ngothe and Takawiri in Homa Bay County in Q2. 3 other mini-grids were in progress.
17 Feb 2026 Ongoing 10,130,000.00 0.0% None as the project pre requisite requirements are being undertaken N/A KOSAP - Site handed over; Advance Payment done; Review of design drawings ongoing (Approvals to be done by Mid-October 2025) GoK - Land acquisition and designs completed, Tendering expected in Q2.
17 Feb 2026 Ongoing 6,830,000.00 0.0% None as the project pre requisite requirements are being undertaken N/A 1) KOSAP - Site handed over; Advance Payment done; Contractor Environmental and Social Safeguard Training done. Review of design drawings for Solar Photovoltaic Generation Plants completed and approved. Contractor's change of manufacturers request Approved. 2) GoK - Land acquisition and designs completed, Tendering - in progress for 1 (Advertised and evaluation ongoing) and Tendering expected in Q3 for another one.
17 Feb 2026 Ongoing 745,650,000.00 0.0% Commissioning Mariakani substation delayed by pending payments to contractor. N/A Commissioning of Konza substation pending re-routing of 400kV Mombasa-Nairobi line around Isinya substation to allow completion of Isinya-Konza line.
17 Feb 2026 Ongoing 0.00 0.0% N/A N/A Land acquisition in progress