These settings are saved on this browser.
Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
FATs (Factory acceptance tests) completed, shipping of materials ongoing. Line Construction has commenced; Project closure is expected by September 2026 for KOSAP Mini grids. Contract preparation ongoing for GoK funded Mini grids.
|
| 07 May 2026 | Completed | 1.00 | 0.0% |
N/A
|
N/A
|
No target for this quarter
|
| 07 May 2026 | Ongoing | 1.00 | 8.0% |
Implementation affected by shortage of materials caused by delayed procurement of material.
|
N/A
|
Target not achieved.
|
| 07 May 2026 | Ongoing | 1.00 | 3.0% |
Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
|
Fast track disbursment of funds
|
KPLC’s Q3 target was 253. The
achievement was 77.
REREC’s Q3 target was 238. The
achievement was 38. Implementation
affected by
|
| 07 May 2026 | Ongoing | 1.00 | 94.0% |
Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.
|
N/A
|
Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC
|
| 07 May 2026 | Ongoing | 1.00 | 24.0% |
Kenya Power’s achievement affected by delayed funding.
Implementation by REREC affected by shortage of materials caused by delayed procurement of material.
|
Fast track disbursment of funds.
|
Kenya Power installed 636 while REREC installed 260 in Q3.
|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
To be reported in Q4
|
| 07 May 2026 | Ongoing | 0.00 | 0.0% |
Affected by delays in materials but the issue is now sorted
|
N/A
|
To be reported in Q4
|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
Pre commissioning tests on going for kimuka substation
|
| 18 Feb 2026 | Ongoing | 5,726,700,000.00 | 81.0% |
Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
|
Promote local capacity in manufacturing of the materials.
Exemption from eGP on procurement of the materials.
|
Target not achieved.
|