Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.
Raw report records returned by the selected filters.
Grouped public projects available in this detailed view.
Reports where implementation challenges were captured.
Reports containing responses, actions, or recommendations.
Summed expenditure across all filtered report entries.
Average performance score from the filtered records.
Share of report records with recorded challenges.
Share of report records with resolutions or recommendations.
Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.
Implementation status mix across the filtered public report records.
Try another project name, status, cluster, challenge, recommendation, or comment.
A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.
Issues slowing or affecting delivery
Responses and recommendations captured
Latest reported progress notes
Implementation affected by shortage of materials caused by delayed procurement of material.
No resolution or recommendation recorded.
Target not achieved.
Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
Fast track disbursment of funds
KPLC’s Q3 target was 253. The achievement was 77. REREC’s Q3 target was 238. The achievement was 38. Implementation affected by
Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.
No resolution or recommendation recorded.
Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC
Kenya Power’s achievement affected by delayed funding. Implementation by REREC affected by shortage of materials caused by delayed procurement of material.
Fast track disbursment of funds.
Kenya Power installed 636 while REREC installed 260 in Q3.
Affected by delays in materials but the issue is now sorted
No resolution or recommendation recorded.
To be reported in Q4
Raw report history is kept here for users who need the full records.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
FATs (Factory acceptance tests) completed, shipping of materials ongoing. Line Construction has commenced; Project closure is expected by September 2026 for KOSAP Mini grids. Contract preparation ongoing for GoK funded Mini grids.
|
| 07 May 2026 | Completed | 1.00 | 0.0% |
N/A
|
N/A
|
No target for this quarter
|
| 07 May 2026 | Ongoing | 1.00 | 8.0% |
Implementation affected by shortage of materials caused by delayed procurement of material.
|
N/A
|
Target not achieved.
|
| 07 May 2026 | Ongoing | 1.00 | 3.0% |
Project execution affected by delays in the release of donor fund and shortage of materials caused by delayed procurement of material.
|
Fast track disbursment of funds
|
KPLC’s Q3 target was 253. The
achievement was 77.
REREC’s Q3 target was 238. The
achievement was 38. Implementation
affected by
|
| 07 May 2026 | Ongoing | 1.00 | 94.0% |
Progress affected by limited availability of critical materials at the beginning of the FY. This however has been resolved and improved results expected subsequently.
|
N/A
|
Target not achieved. Kenya Power connected 98,093 customers in Q3. 11,962 customers were connected by REREC
|
| 07 May 2026 | Ongoing | 1.00 | 24.0% |
Kenya Power’s achievement affected by delayed funding.
Implementation by REREC affected by shortage of materials caused by delayed procurement of material.
|
Fast track disbursment of funds.
|
Kenya Power installed 636 while REREC installed 260 in Q3.
|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
To be reported in Q4
|
| 07 May 2026 | Ongoing | 0.00 | 0.0% |
Affected by delays in materials but the issue is now sorted
|
N/A
|
To be reported in Q4
|
| 07 May 2026 | Ongoing | 1.00 | 0.0% |
N/A
|
N/A
|
Pre commissioning tests on going for kimuka substation
|
| 18 Feb 2026 | Ongoing | 5,726,700,000.00 | 81.0% |
Achievement affected by fewer projects implemented during the quarter as a result of shortage of materials caused by introduction of eGP procurement requirement which is yet to take-off.
|
Promote local capacity in manufacturing of the materials.
Exemption from eGP on procurement of the materials.
|
Target not achieved.
|