Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 50,000,000.00 | 3.0% |
Production affected by unfavourable weather condition and delay in exchequer release
|
production expected to be scaled up during the long rains (march to may)
national treasury to fasttrack exchequer timely issuance
|
N/A
|
| 25 Feb 2026 | Ongoing | 15,000,000.00 | 5.0% |
Delay in exchequer release
|
the national treasury to facilitate timely exchequer
|
N/A
|
| 25 Feb 2026 | Ongoing | 25,500,700.00 | 35.0% |
rehabilitation is limited during the dry season
|
State department for Forestry to expedite more rehabilitation during the long rains season (march to may) in Q3 and Q4
|
N/A
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
delay in exchequer
|
national treasury to avail timely exchequer issuance
|
target to be achieved in subsequent quarter
|
| 25 Feb 2026 | Ongoing | 500,000,000.00 | 1.0% |
Financial challenges
|
Exchequer to release the funds timely.
|
Target not fully achieved
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
implemnentation at procurement process,planned for Q3 AND Q4 during long rains
|
| 25 Feb 2026 | Ongoing | 143,150,151.00 | 45.0% |
N/A
|
N/A
|
target to be achieved in subsequent quarter
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
lack of budget for construction
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
lack of budget provision
|
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% |
exchequer
|
exchequer provision
|
Construction of 1 model nursery at 85% completion.implementation affected by delay in exchequer release.
|