Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 25 Feb 2026 | Ongoing | 50,000,000.00 | 3.0% | Production affected by unfavourable weather condition and delay in exchequer release | production expected to be scaled up during the long rains (march to may) national treasury to fasttrack exchequer timely issuance | N/A |
| 25 Feb 2026 | Ongoing | 15,000,000.00 | 5.0% | Delay in exchequer release | the national treasury to facilitate timely exchequer | N/A |
| 25 Feb 2026 | Ongoing | 25,500,700.00 | 35.0% | rehabilitation is limited during the dry season | State department for Forestry to expedite more rehabilitation during the long rains season (march to may) in Q3 and Q4 | N/A |
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% | delay in exchequer | national treasury to avail timely exchequer issuance | target to be achieved in subsequent quarter |
| 25 Feb 2026 | Ongoing | 500,000,000.00 | 1.0% | Financial challenges | Exchequer to release the funds timely. | Target not fully achieved |
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% | N/A | N/A | implemnentation at procurement process,planned for Q3 AND Q4 during long rains |
| 25 Feb 2026 | Ongoing | 143,150,151.00 | 45.0% | N/A | N/A | target to be achieved in subsequent quarter |
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% | N/A | N/A | lack of budget for construction |
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% | N/A | N/A | lack of budget provision |
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% | exchequer | exchequer provision | Construction of 1 model nursery at 85% completion.implementation affected by delay in exchequer release. |
| 25 Feb 2026 | Ongoing | 45,000,000.00 | 98.0% | N/A | N/A | plantations done in gazetted forests,drylands and on farms |
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% | N/A | N/A | target to be achieved during long rains in quarter 3 and quarter 4 |
| 25 Feb 2026 | Ongoing | 0.00 | 0.0% | target to be achieved during subsequent quarters | N/A | N/A |
| 24 Feb 2026 | Ongoing | 44,250,000.00 | 10.0% | N/A | N/A | 13,145,655 seedlings produced in the first quarter. Low seedling production in the first quarter. The number of seedlings produced is dependent on the rainy seasons (October- December, March- May) |
| 24 Feb 2026 | Ongoing | 55,659,237.00 | 50.0% | inadequate budget alllocation | provide adequate budget allocation | 224,507,145 trees grown and reported in the first quarter. The cumulative number of trees grown is 1,073,061,390. More trees to the grown and reported in the rainy seasons |
| 24 Feb 2026 | Ongoing | 53,280,500.00 | 10.0% | N/A | N/A | Under achievement due to Budget constraints in Financial Year |
| 24 Feb 2026 | Ongoing | 65,400,700.00 | 10.0% | N/A | N/A | Under achieved due to inadequate budget, Cumulatively, 842,709,943 trees grown since 2022 by State and Non State actors as at end of June 2025. |
| 24 Feb 2026 | Ongoing | 54,230,500.00 | 10.0% | N/A | a) Consideration and allocation of 2024/2025 Development Budget during supplementary budget review; b) Enhanced budget allocation in line with annual seedling production targets; and c) Timely disbursement of budgets. | Underachievement due to Budget constraints in the Financial Year |
| 24 Feb 2026 | Ongoing | 62,105,000.00 | 1.0% | N/A | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets, to enhance accurate timing of ground moisture. | The low performance is attributed to poor short rains across the country, lack of budget, and delayed disbursements. |
| 24 Feb 2026 | Ongoing | 55,145,000.00 | 1.0% | The low performance is mainly due to lack budget. | Recommendations a) Consideration and allocation of 2024/2025 Development Budget during supplementary budget review; b) Enhanced budget allocation in line with annual seedling production targets; and c) Timely disbursement of budgets. | Production of 1.58 billion seedlings is a shared responsibility among KFS, KPS, NYS, & MoE. KFS is expected to produce 1 billion seedlings, while KPS, NYS and MoE were to produce 500 million seedlings, during the current 2024/25 FY. 32,094,302 seedlings produced in Q2 |
| 24 Feb 2026 | Ongoing | 64,512,000.00 | 1.0% | The low performance is attributed to poor 2024 short rains across the country, lack of budget, and delayed disbursements. | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets, to enhance accurate timing of ground moisture. | The cumulative trees grown through whole of government whole of society approach is 754,720,261 (513,022,970 by government institutions and 241,697,291 by non-state actors) |
| 24 Feb 2026 | Ongoing | 52,458,900.00 | 1.0% | The low performance is mainly due to lack budget | Recommendations a) Consideration and allocation of 2024/2025 Development Budget during supplementary budget review; b) Enhanced budget allocation in line with annual seedling production targets; and c) Timely disbursement of budgets. | Production of 1.58 billion seedlings is a shared responsibility among KFS, KPS, NYS, & MoE. KFS is expected to produce 1 billion seedlings, while KPS, NYS and MoE were to produce 500 million seedlings, during the current 2024/25 FY. 31,094,302 seedlings produced in Q1. |
| 24 Feb 2026 | Ongoing | 63,455,400.00 | 45.0% | The low performance is attributed to poor 2025 short rains across the country, inadequate budget, slow procurement process and delayed disbursements. | allocate adequate budget | The cumulative trees grown through whole of government whole of society approach is 1073061390,more trees to be grown and reported in the rainy seasons |
| 24 Feb 2026 | Ongoing | 0.00 | 85.0% | N/A | N/A | Target not achieved due to lack of exchequer. |
| 24 Feb 2026 | Ongoing | 0.00 | 10.0% | N/A | N/A | Delay in exchequer release |
| 24 Feb 2026 | Ongoing | 10,500,000.00 | 85.0% | Delays in procurement process | N/A | The International Day for Conservation of Mangrove ecosystems was within the quarter hence the overachievement |
| 24 Feb 2026 | Pipeline | 0.00 | 10.0% | N/A | N/A | N/A |
| 24 Feb 2026 | Ongoing | 0.00 | 10.0% | N/A | N/A | N/A |
| 24 Feb 2026 | Ongoing | 0.00 | 0.0% | N/A | N/A | The weather condition in the first quarter not suitable for tree growing in ASAL areas |
| 24 Feb 2026 | Ongoing | 330,000,000.00 | 1.0% | Financial challenge | Expedite exchequer release of funds | Target not achieved |
| 24 Feb 2026 | Ongoing | 40.60 | 4.0% | N/A | N/A | N/A |
| 03 Dec 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | N/A |
| 03 Dec 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | N/A |
| 03 Dec 2025 | Ongoing | 0.00 | 50.0% | N/A | N/A | Affected by weather conditions |
| 03 Dec 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Target not achieved due to lack of exchequer |
| 03 Dec 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Target not achieved due to lack of exchequer |
| 03 Dec 2025 | Ongoing | 0.00 | 85.0% | N/A | N/A | Construction has been undertaken up to 93.1% in Londiani, Turbo, Lodwar , Wajir, Lamu and Meru |
| 03 Dec 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | N/A |
| 11 Sep 2025 | Ongoing | 0.00 | 85.0% | N/A | N/A | Over achieved through support from Stakeholders. |
| 11 Sep 2025 | Ongoing | 0.00 | 85.0% | This is affected by budget cuts | N/A | Achieved through support from Stakeholders. |
| 11 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | The low performance is mainly due to lack budget. |
| 11 Sep 2025 | Ongoing | 0.00 | 85.0% | N/A | N/A | Achieved through the nation-wide tree growing campaigns |
| 11 Sep 2025 | Ongoing | 0.00 | 50.0% | N/A | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | The performance deficit is attributed to poor rainfall, lack of budget, and delayed disbursements. |
| 11 Sep 2025 | Ongoing | 0.00 | 85.0% | N/A | N/A | Rehabilitating 23,073.73 Ha of degraded natural forest areas in ten Regional Forest |
| 11 Sep 2025 | Ongoing | 0.00 | 85.0% | N/A | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | Rehabilitating 11,367.25 Ha of degraded natural forest areas in ten Regional Forest |
| 11 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Construction of 9 new KFS tree nurseries are ongoing in Marsabit, Wajir Mandera. The 180% over achievement is due to increased partnership support. |
| 11 Sep 2025 | Ongoing | 0.00 | 10.0% | The lack of budget and delayed disbursements are the major attributions for the lower performance | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | Refurbishment /expansion of 11 existing KFS tree nurseries in Garissa, is ongoing. |
| 11 Sep 2025 | Ongoing | 0.00 | 50.0% | N/A | N/A | Under achieved due to budget constraint 18 KFS Tree Nurseries refurbished in Baringo(2), Kericho (2). Meru (2), Nyeri, Kiambu, Kirinyaga, Machakos, Nakuru, Nyandarua, Marsabit, Mandera (2) Wajir (2) and Garissa. |
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Low achievement was affected by limited resources |
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Established 4,382.2 Ha of new forest plantation areas |
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Established 4,382.2 Ha of new forest plantation areas |
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | Under achieved since there was no allocation for the project. |
| 10 Sep 2025 | Ongoing | 0.00 | 10.0% | N/A | N/A | 11 seed centres constructed out of which 3 centres have been equipped |
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
7) 175,000 Ha of degraded public natural forests rehabilitated Area of degraded public natural forests rehabilitated Ha 13,037 2,000 6,750 2,000 6,750 903.4 2,053.08 Rehabilitated 2,956.5 Ha out of the targeted 8,750 Ha in Q1 and Q2, representing 33.5% achievement. The low performance is attributed to poor 2024 short rains across the country, the lack of 2024/2025 FY Development Budget, and delayed disbursements. | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | Rehabilitated 2,053.08Ha in Q2. The low performance is attributed to poor 2024 short rains across the country, the lack of 2024/2025 FY Development Budget, and delayed disbursements. |
| 26 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A | N/A | N/A |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Low budget release | Expedite exchequer release | 254.69 Ha rehabilitated through support from Partners against the targeted 350 Ha in Q2 |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Low budget release | Expedite release of funds for the project | 251 Ha rehabilitated through support from Partners against the targeted 350 Ha in Q1 |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Expedite exchequer release | The low performance is due to lack of budget |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Low performance is due to lack of budget | Expedite exchequer release | Nothing was achieved due to budget issues |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Awaiting budget | Expedite exchequer release | Nothing was achieved |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Awaiting budget | Expedite exchequer release | Nothing was achieved |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
This responsibility was delegated to the Ministry of Water and the KDF. | This responsibility was delegated to the Ministry of Water and the KDF. | This responsibility was delegated to the Ministry of Water and the KDF. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
This responsibility was delegated to the Ministry of Water and the KDF. | This responsibility was delegated to the Ministry of Water and the KDF. | This responsibility was delegated to the Ministry of Water and the KDF. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The performance deficit is attributed to poor rainfall, lack of budget, and delayed disbursements. | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | 892.9 Ha of new plantations established against the targeted 1250 Ha in Q1 |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The performance deficit is attributed to poor rainfall, lack of budget, and delayed disbursements. | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | 905 Ha of new plantations established against the targeted 1250 Ha in Q1 |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The low performance is attributed to poor 2024 short rains across the country, the lack of 2024/2025 FY Development Budget, and delayed disbursements. | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | Rehabilitated 2,956.5 Ha out of the targeted 8,750 Ha in Q1 and Q2, representing 33.5% achievement. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The low performance is attributed to poor 2024 short rains across the country, the lack of 2024/2025 FY Development Budget, and delayed disbursements | Consideration and allocation of 2024/2025 Development Budget, & timely disbursement of budgets to enhance accurate timing of ground moisture. | Rehabilitated 902.4 Ha out of the targeted 8,750 Ha in Q1. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A | Expedite timely exchequer release | Construction of 9 new KFS tree nurseries are ongoing in Marsabit, Wajir Mandera. The 180% over achievement is due to increased partnership support. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Awaiting budget | Expedite exchequer release | Nothing was achieved in this quarter |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The lack of budget and delayed disbursements are the major attributions for the lower performance | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | Refurbishment /expansion of 11 existing KFS tree nurseries in Garissa, is ongoing. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
The lack of budget and delayed disbursements are the major attributions for the lower performance | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | Refurbishment /expansion of 10 existing KFS tree nurseries in Garissa, is ongoing. |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Affected by budget cuts | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | Supplies for equipping Seed Centers in Migori, Maseno and Kakamega were delivered |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Affected by budget cuts | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | Supplies for equipping Seed Centers in Migori, Maseno and Kakamega were delivered |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Affected by budget cuts | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | The seed centers are at average of 84% completion. 4 seed centres structures complete but not equipped |
| 27 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Affected by budget cuts | Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets | The seed centers are at average of 84% completion. 4 seed centres structures complete but not equipped |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Exchequer to release the funds for the activity | Target to be achieved in the subsequent quarters |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Exchequer to release the funds for the activity | Target to be achieved in the subsequent quarters |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenge | Exchequer to expedite the release of funds for the activity | Target to be achieved in the subsequent quarter |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Exchequer to release funds for the activity | To be achieved in the subsequent quarters |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Exchequer to release funds for the activity | To be achieved in the next quarters |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | exchequer to release funds for the activity | Nothing was achieved in Q4 FY 2023/24 |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Expedite exchequer release | Target not fully achieved |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Expedite release release | Target to be achieved in the subsequent quarters |
| 24 Feb 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Financial challenges | Timely exchequer release | To be achieved in the subsequent quarters |