Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
94

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
94

Reports where implementation challenges were captured.

With Resolutions
94

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
3,131,948,128.60

Summed expenditure across all filtered report entries.

%
Average Performance
27.2%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

94 Total Records
Pipeline
7.4% share
7
Ongoing
87.2% share
82
Stalled
0.0% share
0
Completed
5.3% share
5

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

NT

National Tree Growing and Restoration

Cluster: ENVIRONMENT AND NATURAL RESOURCES | Last Updated: 26 Jun 2026
Ongoing Medium Risk Ongoing Completed Pipeline
Budget
4,147,270,528.00
Spent
3,131,948,128.60
Absorption
75.5%
Performance
27.2%
Overall Performance
27.2%
Score
Budget Absorption
75.5%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 94 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 8 Actions 9 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

inadequate funding
inadequate budgetary allocation
delayed due to EGP
delays caused by EGP System
late excheque releases
no budget allocation
Inadequate Funding: Limited funding hinders effective forest conservation. Additionally, delayed disbursement of funds affects activities such as seed and seedlings production, which are tied to rain seasons. 2. Climate Change: Adverse weather patterns, such as droughts and irregular rainfall, disrupted planting and seedling growth in several regions.
Climate Change: Adverse weather patterns, such as droughts and irregular rainfall, disrupted planting and seedling growth in several regions.
Actions / Resolutions

Responses and recommendations captured

allocate funding
allocate more funding
allocate adequate funding
Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets, to enhance accurate timing of ground moisture.
capacity enhancement on the EGP
Capacity enhancement on EGP
timely disbursement
allocate budget
Comments / Outcomes

Latest reported progress notes

Rehabilitated 727.83 Ha in Kirinyaga County- Kathandeini-15Ha, Laikipia County- Kiamuturi 13Ha, Machakos County- Uuni 25 Ha, Meru 41.3 Ha, Nakuru Couty Logoman 30 ha, Vihiga county -Maragoli Hills 250 Ha among others. Total achivement-1,102.13Ha
Rehabilitated 2107.6 Ha of degraded dryland in: Meru National park-40ha, Machakos Uuni Forest-25ha, Tana River Bura Tana Pastoral farmers- 38ha, Taita Hills wildlife sanctuary-30ha, Kisumu Koguta Forest-40ha among others
ha of established along Timbilil, Kipkiwa Beat 10 Ha of bamboo forest on other public gazetted forest land
Rehabilitation done in Lamu, Kilifi, Mombasa and Kwale Counties
The low performance is attributed to poor short rains across the country, lack of budget, and delayed disbursements.
the projects were completed the previous quarter
projects at procurement stage
the projects are at the procurement stage
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
26 Jun 2026

inadequate funding

Action
Resolution / recommendation

allocate funding

Outcome
Ongoing

Rehabilitated 727.83 Ha in Kirinyaga County- Kathandeini-15Ha, Laikipia County- Kiamuturi 13Ha, Machakos County- Uuni 25 Ha, Meru 41.3 Ha, Nakuru Couty Logoman 30 ha, Vihiga county -Maragoli Hills 250 Ha among others. Total achivement-1,102.13Ha

!
Challenge
26 Jun 2026

inadequate funding

Action
Resolution / recommendation

allocate more funding

Outcome
Completed

Rehabilitated 2107.6 Ha of degraded dryland in: Meru National park-40ha, Machakos Uuni Forest-25ha, Tana River Bura Tana Pastoral farmers- 38ha, Taita Hills wildlife sanctuary-30ha, Kisumu Koguta Forest-40ha among others

!
Challenge
26 Jun 2026

inadequate funding

Action
Resolution / recommendation

allocate more funding

Outcome
Ongoing

65 ha of established along Timbilil, Kipkiwa Beat 10 Ha of bamboo forest on other public gazetted forest land

!
Challenge
26 Jun 2026

inadequate budgetary allocation

Action
Resolution / recommendation

allocate adequate funding

Outcome
Completed

Rehabilitation done in Lamu, Kilifi, Mombasa and Kwale Counties

!
Challenge
24 Jun 2026

delayed due to EGP

Action
Resolution / recommendation

capacity enhancement on the EGP

Outcome
Pipeline

projects at procurement stage

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 94
Date Status Amount Spent Performance Challenges Recommendations Comments
26 Jun 2026 Ongoing 80,000,000.00 36.0%
inadequate funding
allocate funding
Rehabilitated 727.83 Ha in Kirinyaga County- Kathandeini-15Ha, Laikipia County- Kiamuturi 13Ha, Machakos County- Uuni 25 Ha, Meru 41.3 Ha, Nakuru Couty Logoman 30 ha, Vihiga county -Maragoli Hills 250 Ha among others. Total achivement-1,102.13Ha
26 Jun 2026 Completed 30,000,000.00 67.0%
inadequate funding
allocate more funding
Rehabilitated 2107.6 Ha of degraded dryland in: Meru National park-40ha, Machakos Uuni Forest-25ha, Tana River Bura Tana Pastoral farmers- 38ha, Taita Hills wildlife sanctuary-30ha, Kisumu Koguta Forest-40ha among others
26 Jun 2026 Ongoing 20,000,000.00 1.0%
inadequate funding
allocate more funding
65 ha of established along Timbilil, Kipkiwa Beat 10 Ha of bamboo forest on other public gazetted forest land
26 Jun 2026 Completed 160,000,000.00 100.0%
inadequate budgetary allocation
allocate adequate funding
Rehabilitation done in Lamu, Kilifi, Mombasa and Kwale Counties
24 Jun 2026 Ongoing 61,250,000.00 1.0%
N/A
Consideration and allocation of 2024/2025 FY budget, and timely disbursement of budgets, to enhance accurate timing of ground moisture.
The low performance is attributed to poor short rains across the country, lack of budget, and delayed disbursements.
24 Jun 2026 Pipeline 0.00 0.0%
N/A
N/A
the projects were completed the previous quarter
24 Jun 2026 Pipeline 0.00 0.0%
delayed due to EGP
capacity enhancement on the EGP
projects at procurement stage
24 Jun 2026 Pipeline 0.00 0.0%
delays caused by EGP System
Capacity enhancement on EGP
the projects are at the procurement stage
24 Jun 2026 Ongoing 8,000,000.00 94.0%
late excheque releases
timely disbursement
2 seed centres done as follows; Meru Seed Centere at 90% and Londiani seed centre at 8%
24 Jun 2026 Pipeline 0.00 0.0%
no budget allocation
allocate budget
no budget allocation