Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 17 Apr 2026 | Pipeline | 0.00 | 0.0% |
Pending budgetary allocation
|
SDM to push for budgetary allocation through BPS 2026
|
Project Concept Notes approved for development of copper and chromite
|
| 17 Apr 2026 | Pipeline | 0.00 | 0.0% |
Pending budgetary allocation
|
SDM to push for budgetary allocation through BPS 2026
|
Project Concept Notes approved for development of copper and chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed finalization of the Project Concept Notes for submission to the National Treasury
|
The State Department for mining to fast-track completion of the project concept notes to facilitate development and commercialization of copper and chromite
|
Development of the Project Concept Notes for two strategic minerals; Copper and Chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Pending budgetary allocation
|
SDM to include budgetary provision in the subsector report for FY 2026/27 and
MTEF
|
Project Concept Notes approved for development of copper and chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed finalization of the Project Concept Notes for submission to the National Treasury
|
The State Department for mining to fast-track completion of the project concept notes to facilitate development and commercialization of copper and chromite
|
Development of the Project Concept Notes for two strategic minerals; Copper and Chromite
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Pending approval of the developed Project Concept Notes
|
SDM to make a follow up with The National Treasury to expedite the approval process
|
Project Concept Notes for Copper and Chromite developed and submitted
to The National Treasury for Approval
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed approval of the developed Project Concept Notes
|
SDM to make a follow up with The National Treasury to expedite the approval process
|
Project Concept Notes for Copper and Chromite developed and submitted to The National Treasury for Approval
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Delayed approval of the developed Project Concept Notes
|
SDM to make a follow up with The National Treasury to expedite the approval process
|
Project Concept Notes for Copper and Chromite developed and submitted
to The National Treasury for Approval
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
N/A
|
N/A
|
Not targeted
|
| 25 Feb 2026 | Pipeline | 0.00 | 0.0% |
Pending approval of PCNs
|
SDM to make a follow up for expedited PCNs approvals
|
Project Concept Notes for Copper and Chromite developed and submitted
to The National Treasury for Approval
|