Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 17 Feb 2026 | Ongoing | 18,259,900.00 | 10.0% |
N/A
|
N/A
|
Low-level surveys for Phase V are ongoing, with connectivity scheduled for implementation in the fourth quarter.
|
| 17 Feb 2026 | Stalled | 28,700,000.00 | 10.0% |
The project has faced contractual issues due to a tax dispute that is being resolved
|
Resolve tax dispute for the project to progress
|
The project has faced contractual issues due to a tax dispute that is being resolved
|
| 17 Feb 2026 | Ongoing | 28,000,000.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 18 Nov 2025 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Low level survey for Phase V to begin in quarter two. Connection to be done in quarter four.
|
| 05 Aug 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
Tax disputes
|
Expedite tax dispute resolution
|
The project has faced contractual issues due to a tax dispute that is being resolved. This informed the nil target in Q3.
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
N/A
|
| 27 Mar 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
N/A
|
Last-mile internet connectivity has been undertaken in Kenya Medical Training Colleges (KMTCs), Hospitals, Police Stations, and Government Offices in Counties to enhance internet.
|