Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

7

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

7

Issues reported
Reports With Resolutions

7

Action points provided
Total Amount Spent

74,959,900.00

Sum of filtered report expenditure
Average Performance

10.0%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
6
Stalled
1
Completed
0
Last Mile County Internet Connectivity Programme (Phase IV and V)
Cluster: INFRASTRUCTURE | Last Updated: 17 Feb 2026
Ongoing Medium Risk Ongoing Stalled
Budget
625,900,205.00
Spent
74,959,900.00
Absorption
12.0%
Performance
10.0%
Overall Performance
10.0%
Performance
Budget Absorption
12.0%
Spent against total budget
Report Volume
7 entries
Scaled visual of entry count
Challenges
• None
• The project has faced contractual issues due to a tax dispute that is being resolved
• Tax disputes
Resolutions
• none
• Resolve tax dispute for the project to progress
• None
• Expedite tax dispute resolution
Comments
• Low-level surveys for Phase V are ongoing, with connectivity scheduled for implementation in the fourth quarter.
• The project has faced contractual issues due to a tax dispute that is being resolved
• None
• Low level survey for Phase V to begin in quarter two. Connection to be done in quarter four.
• The project has faced contractual issues due to a tax dispute that is being resolved. This informed the nil target in Q3.
• Last-mile internet connectivity has been undertaken in Kenya Medical Training Colleges (KMTCs), Hospitals, Police Stations, and Government Offices in Counties to enhance internet.
Budget Notes
No budget notes recorded.
Raw Report Entries
7 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
17 Feb 2026 Ongoing 18,259,900.00 10.0% N/A N/A Low-level surveys for Phase V are ongoing, with connectivity scheduled for implementation in the fourth quarter.
17 Feb 2026 Stalled 28,700,000.00 10.0% The project has faced contractual issues due to a tax dispute that is being resolved Resolve tax dispute for the project to progress The project has faced contractual issues due to a tax dispute that is being resolved
17 Feb 2026 Ongoing 28,000,000.00 10.0% N/A N/A N/A
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Low level survey for Phase V to begin in quarter two. Connection to be done in quarter four.
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Tax disputes Expedite tax dispute resolution The project has faced contractual issues due to a tax dispute that is being resolved. This informed the nil target in Q3.
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Last-mile internet connectivity has been undertaken in Kenya Medical Training Colleges (KMTCs), Hospitals, Police Stations, and Government Offices in Counties to enhance internet.