Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.

Reports Viewed

10

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

10

Issues reported
Reports With Resolutions

10

Action points provided
Total Amount Spent

0.00

Sum of filtered report expenditure
Average Performance

2.9%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
7
Stalled
3
Completed
0
Establishment of a Modern Integrated Iron and Steel Mill Plant
Cluster: FINANCE AND PRODUCTION | Last Updated: 21 Apr 2026
Stalled High Risk Stalled Ongoing
Budget
160,000,000,000.00
Spent
0.00
Absorption
0.0%
Performance
2.9%
Overall Performance
2.9%
Performance
Budget Absorption
0.0%
Spent against total budget
Report Volume
Showing 10 of 10 entries
Scaled visual of entry count
Challenges
• The funds were not allocated for the project
• No funding
• None
• no Budgetary allocation
• no budgetary allocation
Resolutions
• The project to be considered when funds are available
• SD for Industry to source for alternative sources of funding including PPP
• None
• Prioritize funding the project
• Timely allocation of funds
• Timely provision of funds
Comments
• The project had no allocations for theis finacial year
• The project is yet to commence
• Project is yet to commence
• None
• No budget allocation
• No budgetary allocation
• n/a
• no budgetary allocation
Budget Notes
No budget notes recorded.
Raw Report Entries
Showing 10 of 10 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
21 Apr 2026 Stalled 0.00 0.0%
The funds were not allocated for the project
The project to be considered when funds are available
The project had no allocations for theis finacial year
10 Feb 2026 Ongoing 0.00 0.0%
No funding
SD for Industry to source for alternative sources of funding including PPP
The project is yet to commence
10 Feb 2026 Ongoing 0.00 0.0%
No funding
SD for Industry to source for alternative sources of funding including PPP
Project is yet to commence
10 Feb 2026 Ongoing 0.00 0.0%
N/A
N/A
N/A
10 Feb 2026 Ongoing 0.00 0.0%
N/A
N/A
N/A
29 Jan 2026 Stalled 0.00 10.0%
N/A
Prioritize funding the project
No budget allocation
04 Nov 2025 Stalled 0.00 10.0%
N/A
N/A
No budgetary allocation
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A
N/A
N/A
20 Feb 2025 Ongoing 0.00 60.0%
Derived from status
no Budgetary allocation
Timely allocation of funds
N/A
20 Feb 2025 Ongoing 0.00 60.0%
Derived from status
no budgetary allocation
Timely provision of funds
no budgetary allocation