Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
11

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
11

Reports where implementation challenges were captured.

With Resolutions
11

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
0.00

Summed expenditure across all filtered report entries.

%
Average Performance
2.5%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

11 Total Records
Pipeline
0.0% share
0
Ongoing
63.6% share
7
Stalled
36.4% share
4
Completed
0.0% share
0

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

EO

Establishment of a Modern Integrated Iron and Steel Mill Plant

Cluster: FINANCE AND PRODUCTION | Last Updated: 23 Jun 2026
Stalled High Risk Stalled Ongoing
Budget
160,000,000,000.00
Spent
0.00
Absorption
0.0%
Performance
2.5%
Overall Performance
2.5%
Score
Budget Absorption
0.0%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 11 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 5 Actions 6 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

No funding for the project
The funds were not allocated for the project
No funding
no Budgetary allocation
Actions / Resolutions

Responses and recommendations captured

Funds be allocated
The project to be considered when funds are available
SD for Industry to source for alternative sources of funding including PPP
Prioritize funding the project
Timely allocation of funds
Timely provision of funds
Comments / Outcomes

Latest reported progress notes

The project had no allocations for theis finacial year
The project is yet to commence
Project is yet to commence
No budget allocation
No budgetary allocation
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
23 Jun 2026

No funding for the project

Action
Resolution / recommendation

Funds be allocated

Outcome
Stalled

Stalled

!
Challenge
21 Apr 2026

The funds were not allocated for the project

Action
Resolution / recommendation

The project to be considered when funds are available

Outcome
Stalled

The project had no allocations for theis finacial year

!
Challenge
10 Feb 2026

No funding

Action
Resolution / recommendation

SD for Industry to source for alternative sources of funding including PPP

Outcome
Ongoing

The project is yet to commence

!
Challenge
10 Feb 2026

No funding

Action
Resolution / recommendation

SD for Industry to source for alternative sources of funding including PPP

Outcome
Ongoing

Project is yet to commence

!
Challenge
20 Feb 2025

no Budgetary allocation

Action
Resolution / recommendation

Timely allocation of funds

Outcome
Ongoing

Ongoing

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 11
Date Status Amount Spent Performance Challenges Recommendations Comments
23 Jun 2026 Stalled 0.00 0.0%
No funding for the project
Funds be allocated
N/A
21 Apr 2026 Stalled 0.00 0.0%
The funds were not allocated for the project
The project to be considered when funds are available
The project had no allocations for theis finacial year
10 Feb 2026 Ongoing 0.00 0.0%
No funding
SD for Industry to source for alternative sources of funding including PPP
The project is yet to commence
10 Feb 2026 Ongoing 0.00 0.0%
No funding
SD for Industry to source for alternative sources of funding including PPP
Project is yet to commence
10 Feb 2026 Ongoing 0.00 0.0%
N/A
N/A
N/A
10 Feb 2026 Ongoing 0.00 0.0%
N/A
N/A
N/A
29 Jan 2026 Stalled 0.00 10.0%
N/A
Prioritize funding the project
No budget allocation
04 Nov 2025 Stalled 0.00 10.0%
N/A
N/A
No budgetary allocation
26 Mar 2025 Ongoing 0.00 60.0% Derived from status
N/A
N/A
N/A
20 Feb 2025 Ongoing 0.00 60.0% Derived from status
no Budgetary allocation
Timely allocation of funds
N/A