Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
6

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
6

Reports where implementation challenges were captured.

With Resolutions
6

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
0.00

Summed expenditure across all filtered report entries.

%
Average Performance
0.0%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

6 Total Records
Pipeline
0.0% share
0
Ongoing
66.7% share
4
Stalled
33.3% share
2
Completed
0.0% share
0

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

EO

Establishment of a Dairy Feed Centre in Every Ward

Cluster: FINANCE AND PRODUCTION | Last Updated: 10 Feb 2026
Stalled High Risk Stalled Ongoing
Budget
0.00
Spent
0.00
Absorption
N/A
Performance
0.0%
Overall Performance
0.0%
Score
Budget Absorption
N/A
Shows the proportion of reported expenditure against the available project budget.
Report Volume
6 of 6 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 4 Actions 5 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

No funds
Actions / Resolutions

Responses and recommendations captured

Fast track the PCN processing in line with PIM Regulations
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
Comments / Outcomes

Latest reported progress notes

The implementation of the Project has not started yet
No budgetary allocation for FY 2025/26
Project yet to start
Project yet to commence
Challenge → Action → Outcome Flow
4 Highlighted
!
Challenge
10 Sep 2025

No funds

Action
Resolution / recommendation

SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project

Outcome
Ongoing

Project yet to start

!
Challenge
10 Sep 2025

No funds

Action
Resolution / recommendation

SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project

Outcome
Ongoing

Project yet to start

!
Challenge
10 Sep 2025

No funds

Action
Resolution / recommendation

SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project

Outcome
Ongoing

Project yet to commence

!
Challenge
10 Sep 2025

No funds

Action
Resolution / recommendation

SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project

Outcome
Ongoing

Project yet to start

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 6 of 6
Date Status Amount Spent Performance Challenges Recommendations Comments
10 Feb 2026 Stalled 0.00 0.0%
N/A
Fast track the PCN processing in line with PIM Regulations
The implementation of the Project has not started yet
09 Feb 2026 Stalled 0.00 0.0%
N/A
N/A
No budgetary allocation for FY 2025/26
10 Sep 2025 Ongoing 0.00 60.0% Derived from status
No funds
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
Project yet to start
10 Sep 2025 Ongoing 0.00 60.0% Derived from status
No funds
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
Project yet to start
10 Sep 2025 Ongoing 0.00 60.0% Derived from status
No funds
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
Project yet to commence
10 Sep 2025 Ongoing 0.00 60.0% Derived from status
No funds
SD for Livestock Development and State Department for Co-operatives to expedite implementation of the project
Project yet to start