Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

26

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

26

Issues reported
Reports With Resolutions

26

Action points provided
Total Amount Spent

16,000,000,000.00

Sum of filtered report expenditure
Average Performance

27.2%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
25
Stalled
1
Completed
0
E-Voucher Inputs System to Support 2 Million Farmers
Cluster: FINANCE AND PRODUCTION | Last Updated: 11 Feb 2026
Ongoing Medium Risk Ongoing Stalled
Budget
22,000,000,000.00
Spent
16,000,000,000.00
Absorption
72.7%
Performance
27.2%
Overall Performance
27.2%
Performance
Budget Absorption
72.7%
Spent against total budget
Report Volume
26 entries
Scaled visual of entry count
Challenges
• Exchequer release coupled with inadequate budgetary allocation that has lead to huge pending bills that has been accumulating over time
• Inadeguate budgetary allocation coupled with exchequer delays leading to huge pending bills
• None
• N/A
• Lack of funds for the project
• Lack of funds
• Lack of budget allocation
• Lack of Budget allocation
• No budget allocation
Resolutions
• There is need for a special fund to be established for this programme which has a high impact on food security
• Given the high impact of the fertilizer subsidy programmee as evidenced in increased food security in the Country, there is need for creation of a special fund to support the programme
• None
• N/A
• Exchequer release
• Exchequer release for the project
• Exchequer release funds for the project
• N one
Comments
• High registration of farmers also led to high uptake
• The demand for the subsidised fertiliser more than doubled
• No budgetary allocation
• Inadequate budgetary allocation
• There is strategic government intervention hence the high achievement. High registration of farmers also leading to high uptake Note: This target is not broken into quarters. It is a continuous exercise
• Funds not allocated
• Funds were not released
• Target achieved
• Target Achieved
• Funds were not allocated
• None
• Target to be achieved in the 2nd quarter
Budget Notes
No budget notes recorded.
Raw Report Entries
26 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
11 Feb 2026 Ongoing 8,000,000,000.00 85.0% Exchequer release coupled with inadequate budgetary allocation that has lead to huge pending bills that has been accumulating over time There is need for a special fund to be established for this programme which has a high impact on food security High registration of farmers also led to high uptake
10 Feb 2026 Ongoing 8,000,000,000.00 10.0% Inadeguate budgetary allocation coupled with exchequer delays leading to huge pending bills Given the high impact of the fertilizer subsidy programmee as evidenced in increased food security in the Country, there is need for creation of a special fund to support the programme The demand for the subsidised fertiliser more than doubled
29 Jan 2026 Ongoing 0.00 10.0% N/A N/A No budgetary allocation
04 Nov 2025 Ongoing 0.00 10.0% N/A N/A Inadequate budgetary allocation
04 Nov 2025 Stalled 0.00 10.0% N/A N/A No budgetary allocation
04 Nov 2025 Ongoing 0.00 50.0% N/A N/A There is strategic government intervention hence the high achievement. High registration of farmers also leading to high uptake Note: This target is not broken into quarters. It is a continuous exercise
07 Oct 2025 Ongoing 0.00 10.0% N/A N/A Funds not allocated
07 Oct 2025 Ongoing 0.00 10.0% Lack of funds for the project Exchequer release Funds were not released
07 Oct 2025 Ongoing 0.00 50.0% N/A N/A Target achieved
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Target Achieved
08 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Lack of funds Exchequer release for the project Funds were not allocated
08 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Lack of funds Exchequer release funds for the project Funds were not allocated
08 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Lack of funds Exchequer release for the project Funds were not allocated
08 Aug 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Target achieved
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of budget allocation N/A N/A
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of budget allocation N/A N/A
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of Budget allocation N/A N/A
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of budget allocation N/A N/A
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of budget allocation N/A N/A
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
No budget allocation N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Target achieved
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N one Target to be achieved in the 2nd quarter
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N one Target to be achieved in the 2nd quarter
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N one Target to be achieved in the 2nd quarter
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A