Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
48

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
47

Reports where implementation challenges were captured.

With Resolutions
47

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
1,796,805,441.00

Summed expenditure across all filtered report entries.

%
Average Performance
53.0%

Average performance score from the filtered records.

C
Challenge Rate
97.9%

Share of report records with recorded challenges.

A
Action Rate
97.9%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

48 Total Records
Pipeline
0.0% share
0
Ongoing
95.8% share
46
Stalled
0.0% share
0
Completed
4.2% share
2

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

DA

Digital Access and Creative Economy

Cluster: INFRASTRUCTURE | Last Updated: 16 Jul 2026
Ongoing Medium Risk Ongoing Completed
Budget
717,500,000.00
Spent
1,796,805,441.00
Absorption
250.4%
Performance
53.0%
Overall Performance
53.0%
Score
Budget Absorption
250.4%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 48 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 5 Actions 6 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

Limited programme coverage due to resource constraints, resulting in only a fraction of targeted learning institutions and digital hubs benefiting from the initiative.
Inadequate funding limits the expansion and sustainability of the Public Wi-Fi initiative.
Slow implementation due to funding constraints, procurement and logistics delays, and dependence on external financing has affected the pace of rollout, making it difficult to meet the annual target.
Inadequate funds
Connectivity is based on the establishment of the digital hubs
The under-performance is due to the slow start of the financial year.
Not applicable
Limited budgetary provision
Actions / Resolutions

Responses and recommendations captured

Mobilize additional resources and strengthen partnerships to scale up the deployment of VDIs to more TVET institutions, digital hubs, and schools while ensuring adequate technical support and maintenance.
Expedite the development and implementation of the proposed framework, strengthen public-private partnerships, and mobilize additional funding to support the expansion and long-term sustainability of the Public Wi-Fi initiative.
Strengthen coordination with Exim Bank and other implementing partners to accelerate project implementation, expedite procurement and installation processes, ensure timely release of counterpart funds, and prioritize the remaining institutions to improve achievement against the annual target.
A PPP framework is being developed to expedite implementation
Fast tracking establishment of the digital hubs to facilitate connectivity
The project is on course and adherence to the timelines is key.
Not applicable
Increase budgetary allocation
Comments / Outcomes

Latest reported progress notes

The project is being implemented in collaboration with NGCDF
The target was exceeded
The programme recruited and trained 400trainees
Three (3) TVET Institutions (Kiharu Technical and Vocational college, Ol Kalou Technical and Vocational College and Manyatta Technical and Vocational College) were equipped with 150 Virtual Desktop Infrastructure (VDIs) under the Jitume Enablement Programme. During the same period, 5 digital hubs and 9 schools were equipped with 330 VDIs under the Jitume Digital Enablement Programme.
Scaling and sustaining the Public Wi-Fi initiative is constrained by limited funding. The State Department is developing a framework to enhance confidence in NOFBI and increase private sector participation in Wi-Fi rollout.
Project is progressing but at a slower pace
The target was surpassed as more training was conducted virtually.
digital hubs have been connected. Assembly of devices is ongoing and will be completed by June 2026. The first batch of 3,000 devices will be ready for deployment from 1st May 2026
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
15 Jul 2026

Limited programme coverage due to resource constraints, resulting in only a fraction of targeted learning institutions and digital hubs benefiting from the initiative.

Action
Resolution / recommendation

Mobilize additional resources and strengthen partnerships to scale up the deployment of VDIs to more TVET institutions, digital hubs, and schools while ensuring adequate technical support and maintenance.

Outcome
Ongoing

Three (3) TVET Institutions (Kiharu Technical and Vocational college, Ol Kalou Technical and Vocational College and Manyatta Technical and Vocational College) were equipped with 150 Virtual Desktop Infrastructure (VDIs) under the Jitume Enablement Programme. During the same period, 5 digital hubs and 9 schools were equipped with 330 VDIs under the Jitume Digital Enablement Programme.

!
Challenge
15 Jul 2026

Inadequate funding limits the expansion and sustainability of the Public Wi-Fi initiative.

Action
Resolution / recommendation

Expedite the development and implementation of the proposed framework, strengthen public-private partnerships, and mobilize additional funding to support the expansion and long-term sustainability of the Public Wi-Fi initiative.

Outcome
Ongoing

Scaling and sustaining the Public Wi-Fi initiative is constrained by limited funding. The State Department is developing a framework to enhance confidence in NOFBI and increase private sector participation in Wi-Fi rollout.

!
Challenge
14 Jul 2026

Slow implementation due to funding constraints, procurement and logistics delays, and dependence on external financing has affected the pace of rollout, making it difficult to meet the annual target.

Action
Resolution / recommendation

Strengthen coordination with Exim Bank and other implementing partners to accelerate project implementation, expedite procurement and installation processes, ensure timely release of counterpart funds, and prioritize the remaining institutions to improve achievement against the annual target.

Outcome
Ongoing

Ongoing

!
Challenge
02 Jul 2026

Inadequate funds

Action
Resolution / recommendation

A PPP framework is being developed to expedite implementation

Outcome
Ongoing

Project is progressing but at a slower pace

!
Challenge
21 Apr 2026

Connectivity is based on the establishment of the digital hubs

Action
Resolution / recommendation

Fast tracking establishment of the digital hubs to facilitate connectivity

Outcome
Ongoing

156 digital hubs have been connected. Assembly of devices is ongoing and will be completed by June 2026. The first batch of 3,000 devices will be ready for deployment from 1st May 2026

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 48
Date Status Amount Spent Performance Challenges Recommendations Comments
16 Jul 2026 Ongoing 692,424,024.00 100.0%
N/A
N/A
The project is being implemented in collaboration with NGCDF
16 Jul 2026 Ongoing 93,000,000.00 25.0%
N/A
N/A
The target was exceeded
16 Jul 2026 Ongoing 30,375,000.00 25.0%
N/A
N/A
The programme recruited and trained 400trainees
15 Jul 2026 Ongoing 1,000,000.00 70.0%
Limited programme coverage due to resource constraints, resulting in only a fraction of targeted learning institutions and digital hubs benefiting from the initiative.
Mobilize additional resources and strengthen partnerships to scale up the deployment of VDIs to more TVET institutions, digital hubs, and schools while ensuring adequate technical support and maintenance.
Three (3) TVET Institutions (Kiharu Technical and Vocational college, Ol Kalou Technical and Vocational College and Manyatta Technical and Vocational College) were equipped with 150 Virtual Desktop Infrastructure (VDIs) under the Jitume Enablement Programme. During the same period, 5 digital hubs and 9 schools were equipped with 330 VDIs under the Jitume Digital Enablement Programme.
15 Jul 2026 Ongoing 1,000,000.00 86.0%
Inadequate funding limits the expansion and sustainability of the Public Wi-Fi initiative.
Expedite the development and implementation of the proposed framework, strengthen public-private partnerships, and mobilize additional funding to support the expansion and long-term sustainability of the Public Wi-Fi initiative.
Scaling and sustaining the Public Wi-Fi initiative is constrained by limited funding. The State Department is developing a framework to enhance confidence in NOFBI and increase private sector participation in Wi-Fi rollout.
14 Jul 2026 Ongoing 1,000,000.00 23.0%
Slow implementation due to funding constraints, procurement and logistics delays, and dependence on external financing has affected the pace of rollout, making it difficult to meet the annual target.
Strengthen coordination with Exim Bank and other implementing partners to accelerate project implementation, expedite procurement and installation processes, ensure timely release of counterpart funds, and prioritize the remaining institutions to improve achievement against the annual target.
N/A
02 Jul 2026 Ongoing 0.00 28.0%
Inadequate funds
A PPP framework is being developed to expedite implementation
Project is progressing but at a slower pace
16 Jun 2026 Completed 0.00 100.0%
N/A
N/A
The target was surpassed as more training was conducted virtually.
21 Apr 2026 Ongoing 0.00 100.0%
Connectivity is based on the establishment of the digital hubs
Fast tracking establishment of the digital hubs to facilitate connectivity
156 digital hubs have been connected. Assembly of devices is ongoing and will be completed by June 2026. The first batch of 3,000 devices will be ready for deployment from 1st May 2026
21 Apr 2026 Ongoing 5,000,000.00 100.0%
N/A
The project is on course and adherence to the timelines is key.
Recruitment of 400 PDTP Interns was completed and training is ongoing in collaboration with partners.