Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
12

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
12

Reports where implementation challenges were captured.

With Resolutions
12

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
28,162,097,664.00

Summed expenditure across all filtered report entries.

%
Average Performance
16.9%

Average performance score from the filtered records.

C
Challenge Rate
100.0%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

12 Total Records
Pipeline
0.0% share
0
Ongoing
100.0% share
12
Stalled
0.0% share
0
Completed
0.0% share
0

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

CA

County Aggregation and Industrial Parks Project

Cluster: FINANCE AND PRODUCTION | Last Updated: 23 Jun 2026
Ongoing Medium Risk Ongoing
Budget
15,348,437,500.00
Spent
28,162,097,664.00
Absorption
183.5%
Performance
16.9%
Overall Performance
16.9%
Score
Budget Absorption
183.5%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 12 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 7 Actions 7 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

The progress is slow in some counties
Some counties the contractors are slow
Delay of release of funds
Delay in relase of funds
Some counties had no allocation of kshs 250M from their budget
Delays in disbursent of funds
budgetary allocation
Lack of funds
Actions / Resolutions

Responses and recommendations captured

funding required for the remaining 13 CAIPS
The counties to do more supervision of the project
Parliament to fast track the pass the bill
Fast tract the passage of county additional allocation of revenue bill.
Prioritize Funding the remaining counties
Counties to fast tract the construction of CAIPs
Timely provision
Timely provision of funds
Comments / Outcomes

Latest reported progress notes

First and second Phase (34) counties fully funded by National government
The construction varies in percentage in different counties. The priority counties are almost complete with percentages ranging from 61%-99%. The phase two counties are also in the progressing on well with the construction
The county additinal allocation of revenue bill had not been passed thus no funds were released in the 2nd quarter.
The project is ongoing and the target is 47 counties. However 14 were prioritized as per the IBEC Meeting.. The 14 are almost complete apart from Meru which is through and ready for launch and onboarding investors. This financial year 20 more will be onboarded.
Target not fully met due budgetary constraints. During the FY 2023/24 we disbursed Kshs. 1.52 Billion Instead of Kshs. 4.5 billion. In the FY 2024/25 the counties implementing CAIPs increased to 21. However during the IBEC meeting it was agreed that we focus on high performing counties in terms of completion rate of 35%. The counties meeting the criteria were 13. By the end of FY 2024/25 we disbursed full amount of Kshs 250 million to 10 counties. The amount spend is what the 14 counties have so far paid to contractors
targetted for in quarter 4
CAIPS construction is on progress
Not targeted in the quarter
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
23 Jun 2026

The progress is slow in some counties

Action
Resolution / recommendation

funding required for the remaining 13 CAIPS

Outcome
Ongoing

First and second Phase (34) counties fully funded by National government

!
Challenge
06 May 2026

Some counties the contractors are slow

Action
Resolution / recommendation

The counties to do more supervision of the project

Outcome
Ongoing

The construction varies in percentage in different counties. The priority counties are almost complete with percentages ranging from 61%-99%. The phase two counties are also in the progressing on well with the construction

!
Challenge
11 Feb 2026

Delay of release of funds

Action
Resolution / recommendation

Parliament to fast track the pass the bill

Outcome
Ongoing

The county additinal allocation of revenue bill had not been passed thus no funds were released in the 2nd quarter.

!
Challenge
11 Feb 2026

Delay in relase of funds

Action
Resolution / recommendation

Fast tract the passage of county additional allocation of revenue bill.

Outcome
Ongoing

The project is ongoing and the target is 47 counties. However 14 were prioritized as per the IBEC Meeting.. The 14 are almost complete apart from Meru which is through and ready for launch and onboarding investors. This financial year 20 more will be onboarded.

!
Challenge
11 Feb 2026

Some counties had no allocation of kshs 250M from their budget

Action
Resolution / recommendation

Prioritize Funding the remaining counties

Outcome
Ongoing

Target not fully met due budgetary constraints. During the FY 2023/24 we disbursed Kshs. 1.52 Billion Instead of Kshs. 4.5 billion. In the FY 2024/25 the counties implementing CAIPs increased to 21. However during the IBEC meeting it was agreed that we focus on high performing counties in terms of completion rate of 35%. The counties meeting the criteria were 13. By the end of FY 2024/25 we disbursed full amount of Kshs 250 million to 10 counties. The amount spend is what the 14 counties have so far paid to contractors

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 12
Date Status Amount Spent Performance Challenges Recommendations Comments
23 Jun 2026 Ongoing 0.00 0.0%
The progress is slow in some counties
funding required for the remaining 13 CAIPS
First and second Phase (34) counties fully funded by National government
06 May 2026 Ongoing 8,500,000,000.00 50.0%
Some counties the contractors are slow
The counties to do more supervision of the project
The construction varies in percentage in different counties. The priority counties are almost complete with percentages ranging from 61%-99%. The phase two counties are also in the progressing on well with the construction
11 Feb 2026 Ongoing 4,175,480,064.00 0.0%
Delay of release of funds
Parliament to fast track the pass the bill
The county additinal allocation of revenue bill had not been passed thus no funds were released in the 2nd quarter.
11 Feb 2026 Ongoing 0.00 21.0%
Delay in relase of funds
Fast tract the passage of county additional allocation of revenue bill.
The project is ongoing and the target is 47 counties. However 14 were prioritized as per the IBEC Meeting.. The 14 are almost complete apart from Meru which is through and ready for launch and onboarding investors. This financial year 20 more will be onboarded.
11 Feb 2026 Ongoing 4,334,617,600.00 71.0%
Some counties had no allocation of kshs 250M from their budget
Prioritize Funding the remaining counties
Target not fully met due budgetary constraints. During the FY 2023/24 we disbursed Kshs. 1.52 Billion Instead of Kshs. 4.5 billion. In the FY 2024/25 the counties implementing CAIPs increased to 21. However during the IBEC meeting it was agreed that we focus on high performing counties in terms of completion rate of 35%. The counties meeting the criteria were 13. By the end of FY 2024/25 we disbursed full amount of Kshs 250 million to 10 counties. The amount spend is what the 14 counties have so far paid to contractors
10 Feb 2026 Ongoing 0.00 0.0%
N/A
N/A
targetted for in quarter 4
10 Feb 2026 Ongoing 11,152,000,000.00 10.0%
N/A
N/A
N/A
10 Feb 2026 Ongoing 0.00 0.0%
N/A
N/A
CAIPS construction is on progress
10 Feb 2026 Ongoing 0.00 0.0%
Delays in disbursent of funds
Counties to fast tract the construction of CAIPs
Not targeted in the quarter
26 Feb 2025 Ongoing 0.00 60.0% Derived from status
budgetary allocation
Timely provision
Delay in budgetary allocation