| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
Proposed to be implemented under water sector climate financing and Designs are ready.
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
Proposed to be implemented under water sector climate financing.The project is under Financial Negotiations and awaiting closure between the National Treasury and the Exim Bank of China
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
Proposed to be implemented under water sector climate financing (PPP).Designs Ready
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
N/A
|
N/A
|
The project has detailed designs and it is ready for implementation.
To be funded under EPC&F
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
Lack of funds
|
Expedite provision of funds.
|
Still awaiting funding. Designs Ready.
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
Lack of funds
|
Expedite provision of financing for the project.
|
Proposed to be implemented under water sector climate financing.Preliminary Design Ready
|
| 03 Mar 2026 | Ongoing | 0.00 | 10.0% |
lack of funds
|
N/A
|
Still awaiting funds.Project meant to serve communities in Soy, Likuyani and Tongaren Constituencies.
|
| 03 Mar 2026 | Pipeline | 0.00 | 10.0% |
Lack of funds
|
N/A
|
Still awaiting funds.Ready designs & feasibility
|
| 03 Mar 2026 | Ongoing | 0.00 | 10.0% |
Lack of funds
|
N/A
|
N/A
|
| 03 Mar 2026 | Ongoing | 0.00 | 10.0% |
Lack of funds
|
N/A
|
Still awaiting funding.Project meant to serve communities in Mt Elgon, Sirisia, Kabuchai and Kanduyi Constituencies in Bungoma County.
|