Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
2,470

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
2,466

Reports where implementation challenges were captured.

With Resolutions
2,466

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
1,215,078,094.00

Summed expenditure across all filtered report entries.

%
Average Performance
18.5%

Average performance score from the filtered records.

C
Challenge Rate
99.8%

Share of report records with recorded challenges.

A
Action Rate
99.8%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

2,470 Total Records
Pipeline
0.0% share
0
Ongoing
90.1% share
2,225
Stalled
4.0% share
99
Completed
5.9% share
146

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

CO

Construction of 6,000 km Roads

Cluster: INFRASTRUCTURE | Last Updated: 06 May 2026
Ongoing Medium Risk Ongoing Completed Stalled
Budget
236,145,787,710.00
Spent
1,215,078,094.00
Absorption
0.5%
Performance
18.5%
Overall Performance
18.5%
Score
Budget Absorption
0.5%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 2,470 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 10 Actions 10 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection.
Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection.
Insecurity within the project area. Land acquisition and compensation. Potential community demands along the alignment.
Logging activities & Overloading along Gatakaini – Njabini (B20) road coupled with rainy conditions neccesitating repeated maintainance operations. Inefficiency in management of Site on the Side of the Contractor.
Agreements delayed
Lack of funds
Nonr
No funds
Actions / Resolutions

Responses and recommendations captured

Coordination with the National Land Commission.
Engagement of a security liason and Kenya Defense Forces. Engagement with the National Land Commission to ensure timely transmission of funds to project affected persons.
KeNHA to deploy an axle load enforcement unit in the area Contractor reminded to enforce structured pre-activity reviews for each work section
Fasttrack process of procurement
Exchequer release
Exchequer
Project completed during the previous financial year
Project completed in the previous financial year
Comments / Outcomes

Latest reported progress notes

Ongoing
Delayed payments causing slowdown in progress.
Slow execution of works by the contractor
Slow execution of works by the contractor.
Under procurement
Completed
Future Project
Complete
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
06 May 2026

• Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection.

Action
Resolution / recommendation

• Coordination with the National Land Commission.

Outcome
Ongoing

Ongoing

!
Challenge
06 May 2026

• Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection.

Action
Resolution / recommendation

• Coordination with the National Land Commission.

Outcome
Ongoing

Ongoing

!
Challenge
25 Feb 2026

-none

Action
Resolution / recommendation

-none

Outcome
Ongoing

Ongoing

!
Challenge
25 Feb 2026

-none

Action
Resolution / recommendation

-none

Outcome
Ongoing

Delayed payments causing slowdown in progress.

!
Challenge
25 Feb 2026

-none

Action
Resolution / recommendation

-none

Outcome
Ongoing

Ongoing

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 2,470
Date Status Amount Spent Performance Challenges Recommendations Comments
06 May 2026 Ongoing 0.00 0.0%
• Delay in payment of Persons Affected Projects since National Lands Commission was waiting to issue awards after inspection.
• Coordination with the National Land Commission.
N/A
06 May 2026 Ongoing 0.00 0.0%
• Delay in payment of Project Affected Persons since National Land Commission was waiting to issue awards after inspection.
• Coordination with the National Land Commission.
N/A
25 Feb 2026 Ongoing 78,855,360.00 10.0%
-none
-none
Ongoing
25 Feb 2026 Ongoing 148,539,332.00 10.0%
-none
-none
Delayed payments causing slowdown in progress.
25 Feb 2026 Ongoing 26,352,746.00 10.0%
-none
-none
Ongoing
25 Feb 2026 Ongoing 108,299,228.00 10.0%
-none
-none
Ongoing
23 Feb 2026 Ongoing 79,320,240.00 10.0%
-none
-none
Ongoing
23 Feb 2026 Ongoing 118,439,346.00 10.0%
-none
-none
Ongoing
23 Feb 2026 Ongoing 107,703,779.00 10.0%
-none
-none
Ongoing
23 Feb 2026 Ongoing 0.00 10.0%
-none
-none
Slow execution of works by the contractor