Public Implementation Report

Detailed Public Reports

Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.

R
Reports Viewed
1,619

Raw report records returned by the selected filters.

P
Projects
1

Grouped public projects available in this detailed view.

!
With Challenges
1,618

Reports where implementation challenges were captured.

With Resolutions
1,619

Reports containing responses, actions, or recommendations.

KES
Total Amount Spent
82,230,755,367.47

Summed expenditure across all filtered report entries.

%
Average Performance
26.7%

Average performance score from the filtered records.

C
Challenge Rate
99.9%

Share of report records with recorded challenges.

A
Action Rate
100.0%

Share of report records with resolutions or recommendations.

Find a Project Report

Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.

1 Projects Visible
Quick Projects

Status Distribution

Implementation status mix across the filtered public report records.

1,619 Total Records
Pipeline
3.4% share
55
Ongoing
94.9% share
1,536
Stalled
0.0% share
0
Completed
1.7% share
28

No matching project report found

Try another project name, status, cluster, challenge, recommendation, or comment.

CO

Construction of 200,000 Affordable Housing Units Annually

Cluster: INFRASTRUCTURE | Last Updated: 23 Jul 2026
Completed Medium Risk Completed Ongoing Pipeline
Budget
179,182,196,490.00
Spent
82,230,755,367.47
Absorption
45.9%
Performance
26.7%
Overall Performance
26.7%
Score
Budget Absorption
45.9%
Shows the proportion of reported expenditure against the available project budget.
Report Volume
10 of 1,619 Entries
Indicates the number of raw reporting records available for this project.

Public Story Board

A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.

Challenges 10 Actions 10 Coverage 100.0%
!
Key Challenges

Issues slowing or affecting delivery

"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"
"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"
"1.Low procurement of materials have materials in the recent past has led to slowed progress. 2.Low labour mobilisation resulting from delayed procurement of materials. 3.Pending confirmation of the procedure for procurement of Client supplied items."
"1. Delayed approval of alternative construction technology (precast concrete) 2. Sloping terrain on the new site necessitated a redesign "
Low mobilization of materials 2. Low mobilization of labor 3. Extended periods of no site activity 4. Appraisal still under review
Low labour, materials and equipment mobilisation by the MC 2. Poor planning and coordination of work on site 3. MC failed to pay the workers resulting in strikes
Low labor, materials and equipment mobilization by the MC 2. Poor planning and coordination of work on site 3. MC failed to pay the workers resulting in strikes
Works behind schedule/ Revision of architectural drawings
Actions / Resolutions

Responses and recommendations captured

Monitoring of snags 2. Implement an accelerated operationalization plan
"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
Termination Notice to be issued once Performance Bond is renewed Contract to be assigned
Termination Notice issued Project to be reassigned
Consultant to fast -track approvals.
PM to fast-track Contract signing and facilitation of PAPs vise AO on the way forward
PIT to hold management meeting to whip contractor and enforce site instructions.
Comments / Outcomes

Latest reported progress notes

ongoing
project completed
project completed and sold out
Works are behind schedule
Project Completed and Handed Over
Construction Works Ongoing
Preliminary site work ongoing
Preliminary site work on site ongoing
Challenge → Action → Outcome Flow
5 Highlighted
!
Challenge
23 Jul 2026

"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"

Action
Resolution / recommendation

1. Monitoring of snags 2. Implement an accelerated operationalization plan

Outcome
Completed

Completed

!
Challenge
23 Jul 2026

"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"

Action
Resolution / recommendation

"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"

Outcome
Ongoing

Ongoing

!
Challenge
23 Jul 2026

"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"

Action
Resolution / recommendation

1. Monitoring of snags 2. Implement an accelerated operationalization plan

Outcome
Completed

Completed

!
Challenge
23 Jul 2026

"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"

Action
Resolution / recommendation

"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"

Outcome
Ongoing

Ongoing

!
Challenge
23 Jul 2026

"1.Low procurement of materials have materials in the recent past has led to slowed progress. 2.Low labour mobilisation resulting from delayed procurement of materials. 3.Pending confirmation of the procedure for procurement of Client supplied items."

Action
Resolution / recommendation

PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan

Outcome
Ongoing

Ongoing

Detailed Data Table

Raw report history is kept here for users who need the full records.

Showing 10 of 1,619
Date Status Amount Spent Performance Challenges Recommendations Comments
23 Jul 2026 Completed 0.00 100.0%
"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"
1. Monitoring of snags 2. Implement an accelerated operationalization plan
N/A
23 Jul 2026 Ongoing 0.00 10.0%
"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"
"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"
N/A
23 Jul 2026 Completed 0.00 100.0%
"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"
1. Monitoring of snags 2. Implement an accelerated operationalization plan
N/A
23 Jul 2026 Ongoing 0.00 10.0%
"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"
"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"
N/A
23 Jul 2026 Ongoing 0.00 56.0%
"1.Low procurement of materials have materials in the recent past has led to slowed progress. 2.Low labour mobilisation resulting from delayed procurement of materials. 3.Pending confirmation of the procedure for procurement of Client supplied items."
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
N/A
23 Jul 2026 Ongoing 0.00 56.0%
"1.Low procurement of materials have materials in the recent past has led to slowed progress. 2.Low labour mobilisation resulting from delayed procurement of materials. 3.Pending confirmation of the procedure for procurement of Client supplied items."
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
N/A
23 Jul 2026 Ongoing 38,672,095.00 11.0%
"1. Delayed approval of alternative construction technology (precast concrete) 2. Sloping terrain on the new site necessitated a redesign "
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
N/A
23 Jul 2026 Ongoing 38,672,095.00 11.0%
"1. Delayed approval of alternative construction technology (precast concrete) 2. Sloping terrain on the new site necessitated a redesign "
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
N/A
23 Jul 2026 Ongoing 0.00 40.0%
1. Low mobilization of materials 2. Low mobilization of labor 3. Extended periods of no site activity 4. Appraisal still under review
Termination Notice to be issued once Performance Bond is renewed Contract to be assigned
N/A
23 Jul 2026 Ongoing 15,136,316.00 19.0%
1.Low labour, materials and equipment mobilisation by the MC 2. Poor planning and coordination of work on site 3. MC failed to pay the workers resulting in strikes
Termination Notice issued Project to be reassigned
N/A