Search by project using a Select2-powered dropdown and view a citizen-friendly summary of project progress, budget absorption, challenges, actions taken, outcomes, and detailed reporting history.
Raw report records returned by the selected filters.
Grouped public projects available in this detailed view.
Reports where implementation challenges were captured.
Reports containing responses, actions, or recommendations.
Summed expenditure across all filtered report entries.
Average performance score from the filtered records.
Share of report records with recorded challenges.
Share of report records with resolutions or recommendations.
Use the Select2 project search, status filter, or keyword search to quickly locate public project reports.
Implementation status mix across the filtered public report records.
Try another project name, status, cluster, challenge, recommendation, or comment.
A simplified view of what is affecting implementation, what is being done, and the latest public-facing outcome.
Issues slowing or affecting delivery
Responses and recommendations captured
Latest reported progress notes
"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"
1. Monitoring of snags 2. Implement an accelerated operationalization plan
Completed
"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"
"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"
Ongoing
"Project is complete and handed over Defects Liability period is on going: 24th March to 24th September 2026"
1. Monitoring of snags 2. Implement an accelerated operationalization plan
Completed
"1. Low material mobilization 2. Low labour mobilization 3. Constant equipment breakdown 4. Financial constraints 5. Delay in facilitation of geotechnical survey"
"Termination Notice to be issued once Performance Bond is renewed Contract to be reassigned"
Ongoing
"1.Low procurement of materials have materials in the recent past has led to slowed progress. 2.Low labour mobilisation resulting from delayed procurement of materials. 3.Pending confirmation of the procedure for procurement of Client supplied items."
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
Ongoing
Raw report history is kept here for users who need the full records.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 23 Jul 2026 | Completed | 0.00 | 100.0% |
"Project is complete and handed over
Defects Liability period is on going: 24th March to 24th September 2026"
|
1. Monitoring of snags 2. Implement an accelerated operationalization plan
|
N/A
|
| 23 Jul 2026 | Ongoing | 0.00 | 10.0% |
"1. Low material mobilization
2. Low labour mobilization
3. Constant equipment breakdown
4. Financial constraints
5. Delay in facilitation of geotechnical survey"
|
"Termination Notice to be issued once Performance Bond is renewed
Contract to be reassigned"
|
N/A
|
| 23 Jul 2026 | Completed | 0.00 | 100.0% |
"Project is complete and handed over
Defects Liability period is on going: 24th March to 24th September 2026"
|
1. Monitoring of snags 2. Implement an accelerated operationalization plan
|
N/A
|
| 23 Jul 2026 | Ongoing | 0.00 | 10.0% |
"1. Low material mobilization
2. Low labour mobilization
3. Constant equipment breakdown
4. Financial constraints
5. Delay in facilitation of geotechnical survey"
|
"Termination Notice to be issued once Performance Bond is renewed
Contract to be reassigned"
|
N/A
|
| 23 Jul 2026 | Ongoing | 0.00 | 56.0% |
"1.Low procurement of materials have materials in the recent past has led to slowed progress.
2.Low labour mobilisation resulting from delayed procurement of materials.
3.Pending confirmation of the procedure for procurement of Client supplied items."
|
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
|
N/A
|
| 23 Jul 2026 | Ongoing | 0.00 | 56.0% |
"1.Low procurement of materials have materials in the recent past has led to slowed progress.
2.Low labour mobilisation resulting from delayed procurement of materials.
3.Pending confirmation of the procedure for procurement of Client supplied items."
|
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
|
N/A
|
| 23 Jul 2026 | Ongoing | 38,672,095.00 | 11.0% |
"1. Delayed approval of alternative
construction technology (precast concrete)
2. Sloping terrain on the new site necessitated a redesign
"
|
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
|
N/A
|
| 23 Jul 2026 | Ongoing | 38,672,095.00 | 11.0% |
"1. Delayed approval of alternative
construction technology (precast concrete)
2. Sloping terrain on the new site necessitated a redesign
"
|
PIT to hold a management meeting to whip Contractor to implement the revised program of works and methodology of the catch-up plan
|
N/A
|
| 23 Jul 2026 | Ongoing | 0.00 | 40.0% |
1. Low mobilization of materials
2. Low mobilization of labor
3. Extended periods of no site activity
4. Appraisal still under review
|
Termination Notice to be issued once Performance Bond is renewed
Contract to be assigned
|
N/A
|
| 23 Jul 2026 | Ongoing | 15,136,316.00 | 19.0% |
1.Low labour, materials and equipment mobilisation by the MC
2. Poor planning and coordination of work on site
3. MC failed to pay the workers resulting in strikes
|
Termination Notice issued
Project to be reassigned
|
N/A
|