Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

1203

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

1200

Issues reported
Reports With Resolutions

1201

Action points provided
Total Amount Spent

52,721,859,515.18

Sum of filtered report expenditure
Average Performance

25.1%

Average across filtered report rows
Status Distribution
Pipeline
3
Ongoing
1186
Stalled
0
Completed
14
Construction of 200,000 Affordable Housing Units Annually
Cluster: INFRASTRUCTURE | Last Updated: 25 Feb 2026
Ongoing Medium Risk Ongoing Pipeline Completed
Budget
179,182,196,490.00
Spent
52,721,859,515.18
Absorption
29.4%
Performance
25.1%
Overall Performance
25.1%
Performance
Budget Absorption
29.4%
Spent against total budget
Report Volume
1203 entries
Scaled visual of entry count
Challenges
• None
• Site handover pending
• Site Handover pending
• Change of site
• Delayed access due to relocation
• Concrete batching plant experienced frequent breakdowns affecting output per day. The current land allocated for Wastewater Treatment Plant is not sufficient. Limited space to locate four power rooms proposed by electrical engineer. Low labour mobilization More electricity power outages causing delay of works since there is no backup. Insufficient water on site due to water rationing leading to slow pace of works.
• Non-correspondence of the drawings against actual measurements contributing to slow process
• Site handover Pending
• Slow work progress
• Inadequate supply of water and delayed transportation of materials from Nairobi
• Insufficient water supply and transportation of materials from Nairobi
• Delayed due to inadequate labor
• Low mobilization of labour
• Delayed access to the site due relocation
• Delayed access to site due to relocation
• Change of structural foundations
• Structural issues- Change of foundation to pile foundation
• Electrical cables near Block B present a significant safety hazard, posing a risk of electrocution to workers and causing power disruptions on-site and in the surrounding area.
• Mobilization of plants and labour not fully achieved. There are few machines on site making the work move slow. Unreliable power supply that interrupts casting of raft
• -Waiting for NEMA, NCA & county approval. -Project progress is delayed by juakali sector who has not yet commenced their activities on site. -Slow progress of works by the contractor.
• The previous consultant(Quest) resigned without official handover. The architectural drawings, structural and civil drawings, electrical drawings, mechanical drawings and relevant statutory approvals have not been issued. The new consultant ( EDON ) has not effectively taken over the project sites further slowing works.
• -Interest claims -Offsite infrastructure -NEMA approvals -Part of the site not handed to the developer -Incremental Weather conditions -Mains water and power supply - Gen Z demos affected the supply of material to the site - Relocation of existing powerlines -Extra works in sewer relocation -Delay in removal of spoils on-site by a KURA contractor
• .Sewage emanating from the adjacent scheme houses has flooded the site •Ground beam details /Drawings are yet to be availed by the consultants .Block 4 has stalled due to unresolved encroachment issues Existing sewer line relocation and design incomplete.
• Non-correspondence of the drawings against measurements contributed to slow progress
• Rain interrupted works throughout working hours
• Rain interrupted Works throughout the working hours
• Inadequate Equipments on Site
• Inadequate Equipments on site
• Slow delivery of materials to site. Poor quality of concrete works which led to stoppage of works on 2 blocks for further quality investigation 1 batching plant available on site slows down casting of rafts
• gggggggggggggggggggg
• none
• o
• Non Performance by the contractor
• NA
• Redesign of the site plan
• -
• Unstable ground conditions
• Delay in connectivity of enabling works i.e power and water
• NA • Presence of graves on site necessitating exhumation
• Slow works by the Contractor
• None • Slow progress by the contractor
• • Geotechnical survey that led to redesign of the foundations.
• • Geotechnical survey that led to redesign of the foundations
• NONE
• Project on course
• N/A
• Variations in Contract sum delayed works progress
• Not Applicable
• Delays in the release of funds to the project
• i. Inadequate skilled personnel ii. Low quality of locally supplied materials
• 0% level of construction
• Lack of locally available building materials
• Inadequate water supply to the project
• Lack of Housing Regulations of 2024 led to slow project implementation
Resolutions
• None
• SDHUD to ensure fast site handover process to accelerates work on site
• SDHUD to ensure fast site handover pending to accelerates work
• SDHUD to ensure fast site handover pending to accelerate work
• SDHUD to ensure fast site handover process to accelerate work on site
• SDHUD to make a follow up and hasten site handover process to accelerates works
• SDHUD to help in the identification of the new site to accelerate work
• SDHUD to coordinate fast and efficient relocation to accelerates work
• SDHUD to liase with the contractor on site and ensure all the issues on site are addressed to recover lost time
• SDHUD to ensure all issues raised on site are addressed to hasten works and recover delayed time
• SDHUD to liase with architect team on rectification and review of measurements to accelerates works and recover delayed time
• SDHUD to facilitate fast site handover process to accelerates work and recover delayed time
• SDHUD to ensure fast process of site handover to accelerates work and recover delayed time
• SDHUD to ensure fast site handover process to accelerates work and recover delayed time
• SDHUD to ensure fast site handover process to accelerate work and recover lost time
• SDHUD to ensure fast site handover process to accelerates works and recover delayed lost time
• SDHUD to ensure fast handover process to accelerate work and recover delayed time
• SDHUD to ensure fast site handover process to accelerates works and recover delayed time
• SDHUD to fasten site handover process to accelerates works and recover lost time
• SDHUD to ensure fast site handover process so as to accelerates work and recover lost time
• Main contractor to mobilize materials and labor to recover lost time
• Main Contractor should mobilize more materials and labor to recover lost time
• Contractor to ensure adequate supply of water and availability of the required materials on site
• Contractor to ensure adequate water supply and availability of materials on site
• Contractor to mobilize enough labor to hasten work on site
• Contractor to mobilize the availability of labor to hasten work on site
• SDHUD to accelerates work to recover lost time
• Contractor to address the structural foundation issues to hasten work on site
• Contractor to hasten the issues of structural foundation
• Contractor to ensure safety is observed on site by proper maintenance of electricity issues
• SDHUD to accelerates works to recover lost time
• SDHUD to ensure Contractor fast track work on site
• SDHUD to accelerate work to recover lost time
• SDHUD to accelarates works to recover lost time
• SDHUD to accelarates work to recover lost time
• SDHUD to accelerate works to recover lost time
• SDHUD to ensure Contractor mobilizes the availability of equipments on site
• SDHUD to ensure Contractor mobilize the required equipments on site
• SDHUD to ensure Contractor accelerates works to recover lost time
• SDHUD to ensure contractor accelerate works to recover lost time
• ggggggggggggggggggggggggggg
• none
• o
• SDHUD to ensure contractor hand over the project
• SDHUD to ensure contractor handover the project
• nonpe
• SDHUD to ensure the contractor accelerate works
• -
• NA
• SDHUD to ensure Acceleration of works by contractor
• SDHUD to ensure the contractor accelerates works
• SDHUD to ensure contractor accelerate works
• Fast tract completion
• Fastrack completion
• SDHUD to fast track connection of power and water
• SDHUD to ensure completion is fast tracked
• SDHUD to Fastrack connection of water and power
• The project retendered
• SDHUD to ensure contractor mobilise optimally
• SDHUD to ensure contractor accelerate of works
• SDHUD to Ensure contractor mobilize recourses optimally
• SDHUD to ensure the contactor accelerate works
• SDHUD to ensure accelerated works to recover the lost time
• SDHUD to ensure contractor accelerate the works
• The SDHUD to ensure developer accelerate works
• SDHUD to Ensure the contractor accelerate works to recover the lost time
• SDHUD to Ensure contractor accelerate works
• SDHUD to ensure acceleration of works
• SDHUD to ensure to contractor mobilize optimally
• SDHUD to ensure contractor has continued with the accelerated works
• SDHUD to ensure Contractor fast track finishes works
• SDHUD to ensure accelaration of works to recover the lost time
• Acceleration of works by contractor
• Acceleration of works to compensate the time lost
• The SDHUD to ensure the contractor accelerate works
• The SDHUD to ensure the contractor accelerate works to recover lost time
• SDHUD to ensure Acceleration of works by Contractor
• Fastrack
• Fastrack completion of projects
• NONE
• N/A
• Under procurement
• Not Applicable
• The Office of the Attorney General to fast-track the finalization of the Affordable Housing Regulations to enable the Affordable Housing Board to disburse funds for the project
• i. State Department for TVET to build capacity of the local community in quality workmanship ii. The contractor to build the capacity of the local suppliers
• State Department for Housing and Urban Development to establish an efficient approval system in the implementation of the Affordable Housing Project.
• State Department for Water and Sanitation to provide adequate water supply to the project
• The Attorney General to fast-track finalization of Affordable Housing Regulation.
Comments
• Construction Works Ongoing
• Preliminary site work ongoing
• Preliminary site work on site ongoing
• None
• Construction Woks Ongoing
• Construction work ongoing
• Construction works ongoing
• Construction Work Ongoing
• Construction work Ongoing
• gggggggggggggg
• none
• Project Substantially complete
• ongoing
• Preliminary works ongoing
• Completed
• project completed-Final inspection done
• Project substantially complete
• Project completed
• Finishing works ongoing
• Construction ongoing
• construction ongoing
• Final inspection done
• Final Inspection done
• preliminary works
• awarded
• o
• project substantially complete
• finishing works
• Finishing works ongoin
• The project is substantially complete
• project ongoing
• Construction Ongoing
• Construction works ongoing Project on track
• Construction ongoing Acceleration of works by contractor
• • Weather conditions causing overflowing of the adjacent river • Additional scope of external works • Delay in connectivity of enabling works i.e power and water • Slow progress by the contractor
• Construction works ongoing Slow works by contractor
• Project ongoing
• Construction works ongoing • Slow progress by the contractor
• Delays in hand over of the site
• Project on course
• Project is on course
• Under Procurement
• preliminaries construction works started
• Project almost complete
• 60 constituency affordable housing units under construction
• The project is ongoing
• • Additional scope of external works and weather conditions. • Delay in connectivity of enabling works i.e power and water.
• • Unstable ground conditions • Additional scope of external works and weather conditions • Delay in connectivity of enabling works i.e power and water • Slow progress by the contractor
• • Additional scope of external works and weather conditions • Delay in connectivity of enabling works i.e power and water.
• Project awarded
• • no response from bidders
• Contract awarded
• Project ongoing Slow progress by the contractor
• Project ongoing Inconsistent material supply and inadequate machinery
• • Geotechnical survey that led to redesign of the foundations
• Project ongoing Inadequate labour and material mobilisation by contractor
• Slow progress by the contractor
• Project ongoing Geographical survey took longer than planned
• Handed over on 20th January 2025 • Geotechnical survey • Additional Geotech due to existing caves. • Redesign of the site plan
• Project Ongoing "Low mobilisation of resources and labour
• Construction works ongoing The project was converted to developer model
• "Mobilization of plants and labour not fully achieved. There are few machines on site making the work move slow. Unreliable power supply that interrupts casting of rafts"
• Construction works ongoing poor mobilization by contractor
• Construction works ongoing contractor has accelerated works
• Construction works ongoing finishes works ongoing units fully sold out
• Construction works ongoing The contractor has accelerated works to recover the lost time
• Construction works ongoing. Existing sewer line on site causing delays in construction of some blocks.
• • Delays in contractor raising performance bond affecting project commencement
• Construction works ongoing progress on target
• Construction works ongoing Slow progress by contractor
• Construction works ongoing. • Slow progress by the contractor
• Construction works ongoing Project partially complete
• Construction works ongoing • Additional scope of external works and weather conditions • Delay in connectivity of enabling works i.e power and water • Slow progress by the contractor
• Construction works ongoing • Presence of graves on site necessitating exhumation
• Project on track
• under procurement
• Construction works ongoing The project was redesign causing some delay to accommodate more housing
• Water main passing through the site has caused delays in construction
• Construction works ongoing Target achieved
• Project Ongoing • Slow progress by the contractor
• 605 Project completed and sale ongoing
• Construction works ongoing Delays in handover of the site to contractor
• Project Ongoing
• NA
• Finishes works ongoing
• Ongoing
• -
• Finishes works ongoing, final inspection done
• Construction works ongoing.
• 52%- Construction Ongoing
• 50.34% level of construction
• 1% - Show house done
• 12% - Construction Ongoing
• Variations in Contract sum delayed works progress
• Contract awarded. Advance payment made
• 1% - Initial Stage
• Under Negotiations
• 24% - Construction Ongoing
• COntract awarded
• Contract Awarded
• Construction ongoin
• Kilimani Police
• Stalled
• Under procurement
• Handed over on 20th January 2025
• Projects ongoing
• Kehancha
• 60 constituency affordable housing units construction
• Project oncourse
• P
• Project almost completion
• Project almost completed
• construction works ongoing
• N/A
• Under negotiations
• 100% level of completion
• 1% level of completion
• 9% level of completion
• 2% level of completion
• 10% level of completion
• 4% level of completion
• 0% level of completion
• 23% level of completion
• 12% level of completion
• 20% level of completion
• 18% level of completion
• 24% level of completion
• 65% level of completion
• 60% level of completion
• 72% level of completion
• 100 % level of completion. Sale of housing units ongoing
• 83% level of completion
• 3% level of completion
• 21% level of completion
• 8% level of completion
• 11% level of completion
• 10.5% level of completion
• 17% level of completion
• 15% level of completion
• 5% level of construction
• 0% level of construction
• 58% level of construction
• 21% level of construction
• 1% level of construction
• 2% level of construction
• 10% level of construction
• 17% level of construction
• 7% level of construction
• 14% level of construction
• 11% level of construction
• 30% level of construction
• 9% level of construction
• 4% level of construction
• 26% level of construction
• 15% level of construction
• 24% level of construction
• 6% level of construction
• 3% level of construction
• 72% level of construction
• 59% level of construction
• 49.96% level of construction
• 73% level of construction
• 66% level of construction
• 54% level of construction
• 31% level of construction
• 65% level of construction
• 57% level of construction
• 42% level of construction
• 68% level of construction
• 55% level of construction
• 38% level of construction
• 91% level of construction
• 75% level of construction
• 74% level of construction
• 45% level of construction
• 44% level of construction
• % level of construction
• 47% level of construction
• 39% level of construction
• 40% level of construction
• 18% level of construction
• 37% level of construction
• 25% level of construction
• 16% level of construction
• 83% level of construction
• 70% level of construction
• 88% level of construction achieve
• 63% level of construction
• 88% level of construction achieved
• 70% level of construction achieved
• 46% level of completion
• 24% level of construction achieved
• 25% level of construction achieved
• Finishes to show-house ongoing
• Delay caused by water passing through the site
• Delay due to sewer line on site
• Delay due to variation in contract sum
• Contract under negotiation
Budget Notes
• commitments
• o
• 00
• advance payment
• The project if financed through the developer model.
Raw Report Entries
1203 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
25 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 1,045,675,844.00 5.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 1,045,675,844.00 5.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 567,768,044.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 206,978,868.00 15.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 10.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 10.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 11.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 186,487,760.00 54.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 243,348,301.00 76.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 99.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 73.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 103,455,441.00 99.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 13.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 13.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 354,754,300.00 2.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 128,017,112.00 18.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 128,017,112.00 18.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover process to accelerates work on site Construction Works Ongoing
25 Feb 2026 Ongoing 567,768,044.00 0.0% Site handover pending SDHUD to ensure fast site handover pending to accelerates work Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover pending to accelerate work Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover process to accelerates work on site Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover process to accelerate work on site Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Preliminary site work ongoing
25 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Preliminary site work ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 461,469,603.00 20.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 461,469,603.00 20.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 425,410,166.00 3.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 425,410,166.00 3.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 5.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 5.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
25 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 479,513,166.00 9.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 479,513,166.00 9.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site Handover pending SDHUD to make a follow up and hasten site handover process to accelerates works Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 4.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 10.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 7.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 10.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 335,372,735.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 335,372,734.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 5.0% Change of site SDHUD to help in the identification of the new site to accelerate work Construction Works Ongoing
24 Feb 2026 Ongoing 162,729,254.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 8.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 20.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 149,872,525.00 10.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 149,872,524.00 10.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 499,810,661.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 13.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 52,082,039.00 60.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 13,247,540.00 49.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 56.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 40.0% Delayed access due to relocation SDHUD to coordinate fast and efficient relocation to accelerates work Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 25.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 5.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 2,079,540.00 50.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 8.0% Concrete batching plant experienced frequent breakdowns affecting output per day. The current land allocated for Wastewater Treatment Plant is not sufficient. Limited space to locate four power rooms proposed by electrical engineer. Low labour mobilization More electricity power outages causing delay of works since there is no backup. Insufficient water on site due to water rationing leading to slow pace of works. SDHUD to liase with the contractor on site and ensure all the issues on site are addressed to recover lost time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 7.0% Concrete batching plant experienced frequent breakdowns affecting output per day. The current land allocated for Wastewater Treatment Plant is not sufficient. Limited space to locate four power rooms proposed by electrical engineer. Low labour mobilization More electricity power outages causing delay of works since there is no backup. Insufficient water on site due to water rationing leading to slow pace of works. SDHUD to ensure all issues raised on site are addressed to hasten works and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 587,534,105.00 2.0% Non-correspondence of the drawings against actual measurements contributing to slow process SDHUD to liase with architect team on rectification and review of measurements to accelerates works and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 13,247,540.00 0.0% Site handover pending SDHUD to facilitate fast site handover process to accelerates work and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 8.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 8.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site Handover pending SDHUD to ensure fast process of site handover to accelerates work and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover process to accelerates work and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site Handover pending SDHUD to ensure fast site handover process to accelerate work and recover lost time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover process to accelerates works and recover delayed lost time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site Handover pending SDHUD to ensure fast handover process to accelerate work and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to ensure fast site handover process to accelerates works and recover delayed time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Preliminary site work on site ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 4.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% Site handover pending SDHUD to fasten site handover process to accelerates works and recover lost time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 176,874,054.00 0.0% Site handover Pending SDHUD to ensure fast site handover process so as to accelerates work and recover lost time Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 1,045,675,844.00 20.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 1,045,675,844.00 20.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 20.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 585,658,866.00 5.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 585,658,866.00 5.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
24 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 190,820,297.00 6.0% Slow work progress Main contractor to mobilize materials and labor to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 190,820,297.00 6.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 1.0% Slow work progress Main Contractor should mobilize more materials and labor to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 11.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 22,087,542.00 13.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 95,000,000.00 8.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 550,242,803.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 550,242,803.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 530,000,000.00 2.0% N/A N/A N/A
23 Feb 2026 Ongoing 530,000,000.00 2.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 137,063,261.00 6.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 0.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 1,112,771,944.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 1,112,771,944.00 11.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 78,717,290.00 4.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 2.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 80,130,563.00 63.0% Inadequate supply of water and delayed transportation of materials from Nairobi Contractor to ensure adequate supply of water and availability of the required materials on site Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 42.0% Insufficient water supply and transportation of materials from Nairobi Contractor to ensure adequate water supply and availability of materials on site Construction Works Ongoing
23 Feb 2026 Ongoing 106,989,936.00 56.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 35.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 22,631,085.00 6.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 136,542,264.00 55.0% Delayed due to inadequate labor Contractor to mobilize enough labor to hasten work on site Construction Works Ongoing
23 Feb 2026 Ongoing 151,438,365.00 47.0% Low mobilization of labour Contractor to mobilize the availability of labor to hasten work on site Construction Works Ongoing
23 Feb 2026 Ongoing 243,348,301.00 76.0% Delayed access to the site due relocation SDHUD to accelerates work to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 64.0% Delayed access to site due to relocation SDHUD to accelerates work to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 48,584,817.00 42.0% Change of structural foundations Contractor to address the structural foundation issues to hasten work on site Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 39.0% Structural issues- Change of foundation to pile foundation Contractor to hasten the issues of structural foundation Construction Works Ongoing
23 Feb 2026 Ongoing 53,961,576.00 8.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 219,243,421.00 0.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 35,851,935.00 0.0% Electrical cables near Block B present a significant safety hazard, posing a risk of electrocution to workers and causing power disruptions on-site and in the surrounding area. Contractor to ensure safety is observed on site by proper maintenance of electricity issues Construction Works Ongoing
23 Feb 2026 Ongoing 158,204,766.00 55.0% Mobilization of plants and labour not fully achieved. There are few machines on site making the work move slow. Unreliable power supply that interrupts casting of raft SDHUD to accelerates works to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 26.0% Mobilization of plants and labour not fully achieved. There are few machines on site making the work move slow. Unreliable power supply that interrupts casting of raft SDHUD to accelerates work to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 60.0% -Waiting for NEMA, NCA & county approval. -Project progress is delayed by juakali sector who has not yet commenced their activities on site. -Slow progress of works by the contractor. SDHUD to ensure Contractor fast track work on site Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 6.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 21.0% The previous consultant(Quest) resigned without official handover. The architectural drawings, structural and civil drawings, electrical drawings, mechanical drawings and relevant statutory approvals have not been issued. The new consultant ( EDON ) has not effectively taken over the project sites further slowing works. SDHUD to accelerates work to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 7.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 701,331,075.00 5.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 7.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 701,331,075.00 5.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 1,185,087,766.00 13.0% -Interest claims -Offsite infrastructure -NEMA approvals -Part of the site not handed to the developer -Incremental Weather conditions -Mains water and power supply - Gen Z demos affected the supply of material to the site - Relocation of existing powerlines -Extra works in sewer relocation -Delay in removal of spoils on-site by a KURA contractor SDHUD to accelerates works to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 13.0% -Interest claims -Offsite infrastructure -NEMA approvals -Part of the site not handed to the developer -Incremental Weather conditions -Mains water and power supply - Gen Z demos affected the supply of material to the site - Relocation of existing powerlines -Extra works in sewer relocation -Delay in removal of spoils on-site by a KURA contractor SDHUD to accelerates works to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 1,024,395,413.00 13.0% .Sewage emanating from the adjacent scheme houses has flooded the site •Ground beam details /Drawings are yet to be availed by the consultants .Block 4 has stalled due to unresolved encroachment issues Existing sewer line relocation and design incomplete. SDHUD to accelerate work to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 3.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 49.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 627,446,900.00 23.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 72.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 281,242,500.00 70.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 330,255,750.00 89.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 85.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 13.0% Non-correspondence of the drawings against measurements contributed to slow progress SDHUD to accelarates works to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 587,534,105.00 2.0% Non-correspondence of the drawings against measurements contributed to slow progress SDHUD to accelarates work to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 9,695,531.00 57.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 53,168,185.00 48.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 23.0% Rain interrupted works throughout working hours SDHUD to accelerate works to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 90,481,330.00 15.0% Rain interrupted Works throughout the working hours SDHUD to accelarates works to recover lost time Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 34.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 21.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 249,646,370.00 2.0% N/A N/A Construction Woks Ongoing
23 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 680,044,943.00 49.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 187,843,447.00 21.0% Inadequate Equipments on Site SDHUD to ensure Contractor mobilizes the availability of equipments on site Construction Works Ongoing
23 Feb 2026 Ongoing 161,383,096.00 6.0% Inadequate Equipments on site SDHUD to ensure Contractor mobilize the required equipments on site Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 45.0% N/A N/A Construction Woks Ongoing
23 Feb 2026 Ongoing 827,402,429.00 20.0% N/A N/A Construction Works Ongoing
23 Feb 2026 Ongoing 0.00 10.0% N/A N/A Construction work ongoing
23 Feb 2026 Ongoing 0.00 1.0% N/A N/A Construction works ongoing
23 Feb 2026 Ongoing 198,300,948.00 21.0% Slow delivery of materials to site. Poor quality of concrete works which led to stoppage of works on 2 blocks for further quality investigation 1 batching plant available on site slows down casting of rafts SDHUD to ensure Contractor accelerates works to recover lost time Construction Work Ongoing
23 Feb 2026 Ongoing 0.00 11.0% Slow delivery of materials to site. Poor quality of concrete works which led to stoppage of works on 2 blocks for further quality investigation 1 batching plant available on site slows down casting of rafts SDHUD to ensure contractor accelerate works to recover lost time Construction work Ongoing
22 Feb 2026 Pipeline 6,775,575.00 56.0% gggggggggggggggggggg ggggggggggggggggggggggggggg gggggggggggggg
22 Feb 2026 Ongoing 59,117,549.00 41.0% N/A N/A N/A
22 Feb 2026 Ongoing 284,340,115.00 35.0% N/A N/A N/A
22 Feb 2026 Ongoing 0.00 62.0% N/A N/A N/A
22 Feb 2026 Ongoing 0.00 47.0% N/A N/A N/A
22 Feb 2026 Ongoing 2,079,540.00 99.0% N/A N/A Project Substantially complete
21 Feb 2026 Ongoing 0.00 41.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 40.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 37.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 9.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 6.0% N/A N/A ongoing
21 Feb 2026 Ongoing 0.00 1.0% N/A N/A Preliminary works ongoing
21 Feb 2026 Ongoing 0.00 78.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 67.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 51.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 50.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 65.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 57.0% N/A N/A N/A
21 Feb 2026 Completed 0.00 100.0% N/A N/A Completed
21 Feb 2026 Ongoing 0.00 73.0% N/A N/A N/A
21 Feb 2026 Ongoing 0.00 66.0% N/A N/A N/A
21 Feb 2026 Completed 0.00 100.0% N/A N/A project completed-Final inspection done
21 Feb 2026 Ongoing 0.00 99.0% N/A N/A Project substantially complete
21 Feb 2026 Completed 0.00 100.0% N/A N/A Project completed
21 Feb 2026 Ongoing 0.00 98.0% N/A N/A Finishing works ongoing
20 Feb 2026 Ongoing 0.00 3.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 3.0% N/A N/A N/A
20 Feb 2026 Ongoing 78,717,290.00 10.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 5.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 90.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 80.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 80.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 9.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 63.0% N/A N/A N/A
20 Feb 2026 Ongoing 300,000,000.00 1.0% N/A N/A N/A
20 Feb 2026 Ongoing 389,629,511.00 31.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 12.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 2.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 1.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 2.0% N/A N/A N/A
20 Feb 2026 Ongoing 898,026,988.34 11.0% N/A N/A N/A
20 Feb 2026 Ongoing 22,087,541.93 13.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 6.0% N/A N/A N/A
20 Feb 2026 Ongoing 238,920,840.65 13.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 9.0% N/A N/A N/A
20 Feb 2026 Ongoing 249,646,370.24 2.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 1.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 6.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 1.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 45.0% N/A N/A N/A
20 Feb 2026 Ongoing 827,402,429.00 20.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 10.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 1.0% N/A N/A N/A
20 Feb 2026 Ongoing 206,978,868.36 15.0% N/A N/A N/A
20 Feb 2026 Ongoing 104,681,342.15 5.0% N/A N/A N/A
20 Feb 2026 Ongoing 161,918,332.00 47.0% N/A N/A N/A
20 Feb 2026 Ongoing 198,300,947.42 21.0% N/A N/A N/A
20 Feb 2026 Ongoing 319,393,530.00 44.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 11.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 49.0% N/A N/A N/A
20 Feb 2026 Ongoing 101,389,252.73 65.0% N/A N/A N/A
20 Feb 2026 Ongoing 64,630,216.65 52.0% N/A N/A N/A
20 Feb 2026 Ongoing 967,976,533.33 30.0% N/A N/A N/A
20 Feb 2026 Ongoing 241,994,134.00 27.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 21.0% N/A N/A N/A
20 Feb 2026 Ongoing 38,089,071.56 21.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 33.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 17.0% N/A N/A N/A
20 Feb 2026 Ongoing 77,870,603.36 41.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 39.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 28.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 23.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 37.0% N/A N/A N/A
20 Feb 2026 Ongoing 135,775,733.95 25.0% N/A N/A N/A
20 Feb 2026 Ongoing 209,763,827.00 49.0% N/A N/A N/A
20 Feb 2026 Ongoing 60,023,327.44 27.0% N/A N/A N/A
20 Feb 2026 Ongoing 187,843,447.00 21.0% N/A N/A N/A
20 Feb 2026 Ongoing 161,383,096.00 6.0% N/A N/A N/A
20 Feb 2026 Ongoing 49,860,127.87 59.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 30.0% N/A N/A N/A
20 Feb 2026 Ongoing 240,553,276.30 53.0% N/A N/A N/A
20 Feb 2026 Ongoing 50,876,840.00 46.0% N/A N/A N/A
20 Feb 2026 Ongoing 270,192,654.23 63.0% N/A N/A N/A
20 Feb 2026 Ongoing 363,163,234.00 60.0% N/A N/A N/A
20 Feb 2026 Ongoing 979,156,944.62 51.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 40.0% N/A N/A N/A
20 Feb 2026 Ongoing 282,459,883.64 77.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 64.0% N/A N/A N/A
20 Feb 2026 Ongoing 35,851,934.82 0.0% N/A N/A N/A
20 Feb 2026 Ongoing 45,991,507.58 40.0% N/A N/A N/A
20 Feb 2026 Ongoing 71,348,255.00 74.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 63.0% N/A N/A N/A
20 Feb 2026 Ongoing 0.00 35.0% N/A N/A Construction ongoing
20 Feb 2026 Ongoing 0.00 28.0% N/A N/A Construction ongoing
20 Feb 2026 Ongoing 0.00 69.0% N/A N/A Construction ongoing
20 Feb 2026 Ongoing 0.00 52.0% N/A N/A construction ongoing
20 Feb 2026 Ongoing 0.00 75.0% N/A N/A N/A
20 Feb 2026 Ongoing 28,073,611.63 73.0% N/A N/A N/A
19 Feb 2026 Completed 54,240,276.20 100.0% N/A N/A Final inspection done
19 Feb 2026 Ongoing 0.00 99.0% N/A N/A Finishing works ongoing
19 Feb 2026 Ongoing 9,279,561.44 100.0% N/A N/A Final Inspection done
19 Feb 2026 Ongoing 0.00 99.0% N/A N/A Finishing works ongoing
19 Feb 2026 Ongoing 0.00 2.0% N/A N/A preliminary works
19 Feb 2026 Ongoing 0.00 2.0% N/A N/A awarded
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 354,754,300.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 162,729,254.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 542,038,426.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 137,063,261.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 499,810,661.00 0.0% 0 0 N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% 0 0 N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 95,000,000.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 99.0% N/A SDHUD to ensure contractor hand over the project Project substantially complete
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 96.0% N/A N/A N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 99.0% N/A N/A project substantially complete
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 176,874,054.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 99.0% N/A N/A project substantially complete
19 Feb 2026 Ongoing 0.00 99.0% N/A N/A finishing works
19 Feb 2026 Ongoing 0.00 98.0% N/A N/A N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 99.0% N/A SDHUD to ensure contractor handover the project Project substantially complete
19 Feb 2026 Ongoing 34,009,343.00 98.0% N/A N/A Finishing works ongoin
19 Feb 2026 Ongoing 389,629,511.00 31.0% N/A N/A N/A
19 Feb 2026 Ongoing 0.00 12.0% N/A N/A N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 99.0% N/A nonpe The project is substantially complete
19 Feb 2026 Ongoing 500,154,060.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 17,886,289.00 72.0% N/A N/A project ongoing
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o o
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
19 Feb 2026 Ongoing 0.00 0.0% o o N/A
18 Feb 2026 Ongoing 1,024,395,392.00 43.0% Non Performance by the contractor SDHUD to ensure the contractor accelerate works Construction Ongoing
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A awarded
18 Feb 2026 Ongoing 0.00 100.0% N/A - Construction works ongoing Project on track
18 Feb 2026 Ongoing 0.00 25.0% N/A N/A Construction ongoing Acceleration of works by contractor
18 Feb 2026 Ongoing 75,742,801.36 50.0% N/A SDHUD to ensure the contractor accelerate works • Weather conditions causing overflowing of the adjacent river • Additional scope of external works • Delay in connectivity of enabling works i.e power and water • Slow progress by the contractor
18 Feb 2026 Ongoing 297,230,175.00 75.0% N/A SDHUD to ensure Acceleration of works by contractor Construction works ongoing Slow works by contractor
18 Feb 2026 Ongoing 142,324,717.98 85.0% N/A N/A Project ongoing
18 Feb 2026 Ongoing 45,969,803.14 37.0% N/A SDHUD to ensure the contractor accelerates works Construction works ongoing • Slow progress by the contractor
18 Feb 2026 Ongoing 661,547,275.00 100.0% N/A N/A Construction works ongoing Project on track
18 Feb 2026 Ongoing 115,078,430.88 19.0% N/A SDHUD to ensure contractor accelerate works Delays in hand over of the site
18 Feb 2026 Ongoing 51,314,206.74 85.0% N/A Fast tract completion Project on course
18 Feb 2026 Ongoing 38,738,716.45 50.0% N/A Fastrack completion Project is on course
18 Feb 2026 Ongoing 94,027,500.00 0.0% N/A N/A Construction works ongoing
18 Feb 2026 Ongoing 50,817,983.50 0.0% N/A N/A Under Procurement
18 Feb 2026 Ongoing 0.00 0.0% N/A N/A awarded
18 Feb 2026 Pipeline 0.00 0.0% N/A N/A preliminaries construction works started
18 Feb 2026 Ongoing 74,592,271.50 85.0% N/A N/A Project almost complete
18 Feb 2026 Ongoing 78,170,580.01 85.0% N/A N/A Project is on course
18 Feb 2026 Ongoing 56,343,539.51 85.0% N/A N/A 60 constituency affordable housing units under construction
18 Feb 2026 Ongoing 72,385,536.70 85.0% N/A N/A The project is ongoing
18 Feb 2026 Ongoing 62,568,878.00 85.0% N/A SDHUD to fast track connection of power and water • Additional scope of external works and weather conditions. • Delay in connectivity of enabling works i.e power and water.
18 Feb 2026 Ongoing 64,586,105.50 75.0% N/A SDHUD to ensure completion is fast tracked • Unstable ground conditions • Additional scope of external works and weather conditions • Delay in connectivity of enabling works i.e power and water • Slow progress by the contractor
18 Feb 2026 Ongoing 90,456,736.19 85.0% N/A SDHUD to Fastrack connection of water and power • Additional scope of external works and weather conditions • Delay in connectivity of enabling works i.e power and water.
18 Feb 2026 Ongoing 140,875,864.50 96.0% N/A N/A The project is ongoing
18 Feb 2026 Ongoing 208,743,057.73 85.0% N/A N/A Project awarded
18 Feb 2026 Ongoing 69,787,828.43 10.0% N/A N/A Project ongoing
18 Feb 2026 Ongoing 66,674,189.28 3.0% N/A The project retendered • no response from bidders
18 Feb 2026 Ongoing 109,621,710.70 10.0% N/A N/A Contract awarded
18 Feb 2026 Ongoing 204,232,740.31 51.0% N/A SDHUD to ensure the contractor accelerates works Project ongoing Slow progress by the contractor
18 Feb 2026 Ongoing 386,018,266.56 31.0% N/A SDHUD to ensure contractor mobilise optimally Project ongoing Inconsistent material supply and inadequate machinery
18 Feb 2026 Ongoing 199,730,249.26 28.0% N/A SDHUD to ensure contractor accelerate of works • Geotechnical survey that led to redesign of the foundations
18 Feb 2026 Ongoing 95,096,338.90 34.0% N/A SDHUD to Ensure contractor mobilize recourses optimally Project ongoing Inadequate labour and material mobilisation by contractor
18 Feb 2026 Ongoing 168,821,334.63 45.0% N/A SDHUD to ensure the contactor accelerate works Slow progress by the contractor
18 Feb 2026 Ongoing 54,392,757.00 30.0% N/A N/A Project ongoing Geographical survey took longer than planned
18 Feb 2026 Ongoing 55,421,024.50 70.0% Redesign of the site plan SDHUD to ensure accelerated works to recover the lost time Handed over on 20th January 2025 • Geotechnical survey • Additional Geotech due to existing caves. • Redesign of the site plan
18 Feb 2026 Ongoing 112,598,138.00 60.0% N/A SDHUD to ensure contractor accelerate the works Project Ongoing "Low mobilisation of resources and labour
18 Feb 2026 Ongoing 0.00 25.0% N/A The SDHUD to ensure developer accelerate works Construction works ongoing The project was converted to developer model
18 Feb 2026 Ongoing 69,724,600.05 50.0% N/A SDHUD to Ensure the contractor accelerate works to recover the lost time • Geotechnical survey that led to redesign of the foundations
18 Feb 2026 Ongoing 451,394,290.43 50.0% N/A SDHUD to ensure contractor accelerate works Slow progress by the contractor
18 Feb 2026 Ongoing 116,479,875.12 83.0% N/A N/A Construction works ongoing Project on track
18 Feb 2026 Ongoing 158,204,768.00 100.0% - SDHUD to ensure contractor accelerate works "Mobilization of plants and labour not fully achieved. There are few machines on site making the work move slow. Unreliable power supply that interrupts casting of rafts"
18 Feb 2026 Ongoing 0.00 50.0% - SDHUD to Ensure contractor accelerate works Construction works ongoing • Slow progress by the contractor
18 Feb 2026 Ongoing 9,695,531.00 81.0% - SDHUD to ensure acceleration of works Construction works ongoing
18 Feb 2026 Ongoing 62,926,424.00 86.0% - SDHUD to ensure to contractor mobilize optimally Construction works ongoing poor mobilization by contractor
18 Feb 2026 Ongoing 0.00 75.0% - SDHUD to ensure contractor has continued with the accelerated works Construction works ongoing contractor has accelerated works
18 Feb 2026 Ongoing 330,255,744.00 90.0% N/A SDHUD to ensure Contractor fast track finishes works Construction works ongoing finishes works ongoing units fully sold out
18 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing The contractor has accelerated works to recover the lost time
18 Feb 2026 Ongoing 1,185,087,744.00 10.0% N/A SDHUD to ensure accelaration of works to recover the lost time Construction works ongoing. Existing sewer line on site causing delays in construction of some blocks.
17 Feb 2026 Ongoing 313,605,728.60 10.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 120,000,000.00 6.0% N/A N/A • Delays in contractor raising performance bond affecting project commencement
17 Feb 2026 Ongoing 139,858,956.15 94.0% N/A N/A Construction works ongoing progress on target
17 Feb 2026 Ongoing 1,349,294,051.50 64.0% N/A N/A Slow progress by the contractor
17 Feb 2026 Ongoing 149,550,747.10 13.0% Unstable ground conditions N/A Construction works ongoing
17 Feb 2026 Ongoing 573,200,758.87 47.0% N/A N/A Construction works ongoing Slow progress by contractor
17 Feb 2026 Ongoing 50,797,033.80 57.0% N/A N/A Construction works ongoing. • Slow progress by the contractor
17 Feb 2026 Ongoing 118,646,287.81 99.0% N/A N/A Construction works ongoing Project partially complete
17 Feb 2026 Ongoing 135,709,805.10 70.0% Delay in connectivity of enabling works i.e power and water Acceleration of works by contractor Construction works ongoing • Additional scope of external works and weather conditions • Delay in connectivity of enabling works i.e power and water • Slow progress by the contractor
17 Feb 2026 Ongoing 120,177,495.34 26.0% NA • Presence of graves on site necessitating exhumation Acceleration of works to compensate the time lost Construction works ongoing • Presence of graves on site necessitating exhumation
17 Feb 2026 Ongoing 0.00 100.0% N/A N/A Project on track
17 Feb 2026 Pipeline 0.00 10.0% N/A N/A under procurement
17 Feb 2026 Ongoing 0.00 26.0% Slow works by the Contractor The SDHUD to ensure the contractor accelerate works Construction works ongoing The project was redesign causing some delay to accommodate more housing
17 Feb 2026 Ongoing 0.00 100.0% N/A N/A Project on track
17 Feb 2026 Ongoing 0.00 20.0% N/A The SDHUD to ensure the contractor accelerate works to recover lost time Water main passing through the site has caused delays in construction
17 Feb 2026 Ongoing 0.00 100.0% N/A N/A Construction ongoing
17 Feb 2026 Ongoing 0.00 100.0% N/A N/A Construction works ongoing Target achieved
17 Feb 2026 Ongoing 0.00 82.0% None • Slow progress by the contractor SDHUD to ensure Acceleration of works by Contractor Project Ongoing • Slow progress by the contractor
17 Feb 2026 Ongoing 0.00 100.0% • Geotechnical survey that led to redesign of the foundations. N/A ongoing
17 Feb 2026 Ongoing 0.00 60.0% • Geotechnical survey that led to redesign of the foundations N/A Construction works ongoing
17 Feb 2026 Completed 0.00 100.0% N/A N/A 605 Project completed and sale ongoing
17 Feb 2026 Ongoing 0.00 12.0% N/A N/A Construction works ongoing Delays in handover of the site to contractor
17 Feb 2026 Ongoing 0.00 80.0% N/A N/A Project Ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Project ongoing
17 Feb 2026 Completed 0.00 85.0% N/A N/A 605 Project completed and sale ongoing
17 Feb 2026 Ongoing 0.00 10.0% N/A N/A N/A
17 Feb 2026 Ongoing 0.00 46.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 188,725,900.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 85.0% N/A N/A Finishes works ongoing
17 Feb 2026 Ongoing 52,082,038.72 85.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 13,247,540.47 10.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 85.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 85.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 85.0% N/A N/A Finishes works ongoing
17 Feb 2026 Ongoing 0.00 85.0% N/A N/A Finishes works ongoing
17 Feb 2026 Ongoing 0.00 85.0% N/A N/A Finishes works ongoing
17 Feb 2026 Ongoing 34,009,343.00 85.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 17,886,289.00 85.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 10.0% N/A N/A Ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 38,089,071.56 10.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 219,243,421.40 10.0% N/A N/A Construction ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 60,224,666.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 45,991,507.58 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 90,481,330.00 10.0% N/A N/A Construction works ongoing
17 Feb 2026 Ongoing 151,438,365.00 50.0% N/A N/A Construction works ongoing
16 Feb 2026 Completed 0.00 100.0% N/A N/A Construction works ongoing
16 Feb 2026 Ongoing 53,168,185.00 50.0% N/A N/A Construction works ongoing
16 Feb 2026 Ongoing 28,780,083.98 50.0% N/A N/A Construction works ongoing
16 Feb 2026 Ongoing 161,383,096.00 50.0% - - -
16 Feb 2026 Ongoing 627,446,900.00 50.0% - - Construction works ongoing
16 Feb 2026 Ongoing 54,240,276.20 85.0% - - Finishes works ongoing
16 Feb 2026 Ongoing 11,804,920.00 50.0% N/A N/A Construction works ongoing
16 Feb 2026 Ongoing 0.00 99.0% - - Finishes works ongoing
16 Feb 2026 Ongoing 21,159,985.30 85.0% - - Finishes works ongoing
16 Feb 2026 Ongoing 103,455,440.96 85.0% N/A N/A Finishing works ongoing
16 Feb 2026 Ongoing 9,279,561.44 85.0% N/A N/A Finishes works ongoing, final inspection done
16 Feb 2026 Ongoing 243,348,304.00 85.0% - - Construction ongoing
16 Feb 2026 Ongoing 22,631,084.00 10.0% - - Construction works ongoing
16 Feb 2026 Ongoing 59,117,548.00 50.0% - - Construction works ongoing.
16 Feb 2026 Ongoing 53,961,576.00 10.0% - - Construction ongoing
16 Feb 2026 Ongoing 80,130,560.00 50.0% - - Construction works ongoing
16 Feb 2026 Ongoing 186,487,760.00 50.0% - - Construction works ongoing
16 Feb 2026 Ongoing 87,707,184.00 85.0% - - Construction works ongoing
16 Feb 2026 Ongoing 106,989,936.00 50.0% - - Construction works ongoing
16 Feb 2026 Ongoing 48,584,816.00 50.0% - - Construction ongoing
16 Feb 2026 Ongoing 136,542,272.00 50.0% - - Construction works ongoing
02 Feb 2026 Ongoing 0.00 50.0% - - -
02 Feb 2026 Ongoing 0.00 50.0% - - Construction works ongoing
02 Feb 2026 Ongoing 0.00 50.0% - - Construction works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Finishing works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Finishing works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Construction works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Construction works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Finishes works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Finishing works ongoing
02 Feb 2026 Ongoing 0.00 85.0% - - Construction works ongoing
02 Feb 2026 Ongoing 0.00 50.0% - - Construction works ongoing
26 Jan 2026 Completed 0.00 85.0% N/A N/A Project completed
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 85.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
23 Nov 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
23 Nov 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
23 Nov 2025 Ongoing 0.00 10.0% N/A N/A under procurement
25 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project is on course
25 Sep 2025 Ongoing 0.00 85.0% N/A N/A 52%- Construction Ongoing
25 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
24 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
24 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
24 Sep 2025 Ongoing 0.00 10.0% N/A Fastrack completion Project on course
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
24 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
24 Sep 2025 Ongoing 0.00 50.0% N/A N/A 50.34% level of construction
24 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
12 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A 1% - Show house done
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A 12% - Construction Ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Completed 0.00 85.0% N/A N/A 605 Project completed and sale ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A N/A
11 Sep 2025 Completed 0.00 85.0% N/A N/A 605 Project completed and sale ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Completed 0.00 85.0% N/A N/A 605 Project completed and sale ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A 0
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Variations in Contract sum delayed works progress
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Variations in Contract sum delayed works progress
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A N/A
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded. Advance payment made
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded. Advance payment made
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded. Advance payment made
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing.
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing.
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing.
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A 1% - Initial Stage
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Under Negotiations
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A 24% - Construction Ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Under Negotiations
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Under Negotiations
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A N/A
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A COntract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract Awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Water main passing through the site has caused delays in construction
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Water main passing through the site has caused delays in construction
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Water main passing through the site has caused delays in construction
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction ongoin
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Kilimani Police
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Kilimani Police
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction works ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Construction Ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Stalled
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Under procurement
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Under procurement
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project Ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Handed over on 20th January 2025
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Handed over on 20th January 2025
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Handed over on 20th January 2025
11 Sep 2025 Ongoing 0.00 10.0% 0 N/A Handed over on 20th January 2025
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Contract awarded
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Projects ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Kehancha
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A The project is ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A 60 constituency affordable housing units under construction
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A 60 constituency affordable housing units under construction
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A 60 constituency affordable housing units construction
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A 60 constituency affordable housing units under construction
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 10.0% N/A N/A Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A Fastrack completion Project is on course
11 Sep 2025 Ongoing 0.00 50.0% N/A Fast tract completion Project is on course
11 Sep 2025 Ongoing 0.00 10.0% N/A Fastrack Project is on course
11 Sep 2025 Ongoing 0.00 85.0% N/A Fastrack completion of projects Project oncourse
11 Sep 2025 Ongoing 0.00 50.0% N/A Fastrack completion of projects Project oncourse
11 Sep 2025 Ongoing 0.00 50.0% Project on course Fastrack completion P
11 Sep 2025 Ongoing 0.00 50.0% N/A N/A Project on course
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project ongoing
11 Sep 2025 Ongoing 0.00 85.0% N/A N/A Projects ongoing
10 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project almost completion
10 Sep 2025 Ongoing 0.00 85.0% N/A N/A Project almost completed
10 Sep 2025 Ongoing 0.00 85.0% N/A N/A construction works ongoing
10 Sep 2025 Ongoing 0.00 50.0% N/A N/A N/A
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction Ongoing
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
Variations in Contract sum delayed works progress N/A Variations in Contract sum delayed works progress
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A Under procurement Under procurement
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Under negotiations
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded. Advance payment made
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project Ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
Not Applicable Not Applicable Project ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
Not Applicable Not Applicable Project ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A construction ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project ongoing
09 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
08 Sep 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A ongoing
30 Jun 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
30 Jun 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
30 Jun 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
28 Mar 2025 Completed 0.00 100.0%
Derived from status
N/A N/A Completed
28 Mar 2025 Completed 0.00 100.0%
Derived from status
N/A N/A Completed
28 Mar 2025 Completed 0.00 100.0%
Derived from status
N/A N/A 100% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 9% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 2% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 2% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 10% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 4% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 23% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 12% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 12% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 20% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 18% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 24% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 65% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 60% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 72% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 100 % level of completion. Sale of housing units ongoing
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 83% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 83% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 3% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 3% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 21% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 8% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 11% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 10% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Delays in the release of funds to the project The Office of the Attorney General to fast-track the finalization of the Affordable Housing Regulations to enable the Affordable Housing Board to disburse funds for the project 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 12% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
i. Inadequate skilled personnel ii. Low quality of locally supplied materials i. State Department for TVET to build capacity of the local community in quality workmanship ii. The contractor to build the capacity of the local suppliers 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 10% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 10.5% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 4% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 17% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 15% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of completion
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 5% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 58% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 21% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 2% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 2% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
0% level of construction N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 10% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 58% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 17% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 2% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 7% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 14% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 11% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 30% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 11% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 17% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 2% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 9% level of construction
27 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 17% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 0% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 4% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 10% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 26% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 15% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 1% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 24% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 6% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 3% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 72% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 59% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 49.96% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 73% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 59% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 66% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 54% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 31% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 65% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 57% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 42% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 68% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 55% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 38% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 91% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 75% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 91% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of locally available building materials State Department for Housing and Urban Development to establish an efficient approval system in the implementation of the Affordable Housing Project. 26% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 74% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 45% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Inadequate water supply to the project State Department for Water and Sanitation to provide adequate water supply to the project 44% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A % level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 54% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Inadequate water supply to the project State Department for Water and Sanitation to provide adequate water supply to the project 44% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 47% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 39% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 15% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 40% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 18% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 15% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 37% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 25% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 16% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 83% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 58% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 40% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 70% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 88% level of construction achieve
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 63% level of construction
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 88% level of construction achieved
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 70% level of construction achieved
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 46% level of completion
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A 24% level of construction achieved
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Construction works ongoing
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Lack of Housing Regulations of 2024 led to slow project implementation The Attorney General to fast-track finalization of Affordable Housing Regulation. 25% level of construction achieved
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Finishes to show-house ongoing
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Delay caused by water passing through the site
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Delay due to sewer line on site
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Under negotiations
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Under negotiations
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Under negotiations
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Under negotiations
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Under negotiations
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Delay due to variation in contract sum
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract awarded
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract under negotiation
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract under negotiation
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract under negotiation
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Contract under negotiation
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing
21 Feb 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Ongoing