Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.
| Date | Status | Amount Spent | Performance | Challenges | Recommendations | Comments |
|---|---|---|---|---|---|---|
| 18 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
As part of project conceptualization, a Project Concept Note has been developed and forwarded to the National Treasury for approval in line with PIM regulations, 2022. Awaiting the National Treasury approval to progress to the next steps.
|
| 18 Feb 2026 | Ongoing | 3,571,488,412.75 | 100.0% |
N/A
|
N/A
|
N/A
|
| 17 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
N/A
|
| 17 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
• Concept Note prepared and submitted to National Treasury for approval
|
| 17 Feb 2026 | Ongoing | 0.00 | 0.0% |
• Resettlement of PAPs
• Delay in getting concurrence from JICA
• Delay in payment of advance payment
|
• Continuous engagements with the Ministry of Roads & Transport and the National Treasury to ensure funding availability throughout project implementation period.
• Ensure adherence to the implementation schedule
|
• Preliminary studies for 3 additional berths at Lamu Port are planned for FY 2026/2027
|
| 17 Feb 2026 | Ongoing | 0.00 | 0.0% |
N/A
|
N/A
|
• Project has not commenced
• Feasibility study has been completed.
• KPA has written to JICA to commence negotiations for financing through National Treasury
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Not commenced.
Preliminary studies for 3 additional berths at Lamu Port are planned for FY 2026/2027.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
N/A
|
N/A
|
Container Terminal 2: Concept note developed awaiting approval.
The Authority has written to JICA to commence negotiations for financing through National Treasury
Berth 19: Contract for civil works signed in March 2025. The Contractor is in the process of mobilizing for work.
|
| 11 Feb 2026 | Ongoing | 0.00 | 10.0% |
Technical & Engineering Challenges in demolishing the existing KOT I
|
The need to undertake through studies prior to commencement of the project.
|
Ongoing
|
| 10 Sep 2025 | Ongoing | 0.00 |
60.0%
Derived from status
|
N/A
|
The project is progressing to the procurement stage for private partners after the approval of the feasibility study.
|
The project is progressing to the procurement stage for private partners after the approval of the feasibility study.
|