Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

25

Issues reported
Reports With Resolutions

25

Action points provided
Total Amount Spent

3,000,000.00

Sum of filtered report expenditure
Average Performance

15.8%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
13
Stalled
12
Completed
0
Completion of Bachuma Livestock Export Zone (LEZ) and Construction and Operation of Lamu LEZ
Cluster: FINANCE AND PRODUCTION | Last Updated: 11 Feb 2026
Stalled High Risk Stalled Ongoing
Budget
3,000,000.00
Spent
3,000,000.00
Absorption
100.0%
Performance
15.8%
Overall Performance
15.8%
Performance
Budget Absorption
100.0%
Spent against total budget
Report Volume
25 entries
Scaled visual of entry count
Challenges
• The project could not start due to fiscal space challenge within the State Department
• The project was affected by lack of budgetary resources
• The lack of activities at the site has created some issues such as destruction of Bio-security wall by the animals especially (Elephants) and also human interference
• Court ruling stopped the procurement of a PPP investor/s
• The process of establishment was hampered by budget realignment.
• None
• No funding
• Lack of budgetary provision
• No budgetary allocation
• no provision of funds
• no adequate provision of funds
• lack of funds
Resolutions
• Expedite alternative sources of funding especially the PPP model to finalize and operationalize.
• PPP Model to be considered in the project
• The process of engaging PPP model was terminated by court, citing lack of public participation. To adhere to the ruling Public participation was redone and procurement process started afresh. A call for Expression of Interest (EOI) was redone in December 2025.
• Re-start the PPP procuring process in line with the court ruling
• Consider PPP model to develop and operate
• None
• SD for Livestock Development to expedite alternative sources of funding including PPP
• To expedite alternative sources of funding including PPP Model
• PPP Model to be considered
• Allocation of budgets
• Timely provision of funds
• timely provision of funds
Comments
• The project was to establish a Bio-Security/ quarantime facility at Bargani in Lamu County to support the livestock exports at Lamu Port. The designs for the facility were done but the financial resource limitation stalled the project implementation.
• The designs for the marshaling yard were completed but the project was affected by non-budgetary provision issues.
• The Finalization and operationalization of Bio secured Livestock Zone established at Bachuma in Taita Taveta County has stalled, however, the PPP Model was introduced. This is to finalize and operationalize the LEZ.
• The procurement of PPP Model of investment ongoing
• The establishment of a bio-secured livestock finishing Disease free holding ground (LEZ)at Bargoni Holding ground has not started. The designs for the LEZ were developed.
• None
• • Requests for Proposals (RFP) were sent to the 4 successful bidders in March 2025 and all were responsive and now pending evaluation. • This is being implemented under the Land Commercialization Initiative (LCI)
• Lack of budget provisions led to the stalling of the project.
• No budgetary allocation
• no provision of funds
• no adequate provision of funds
• lack of funds
Budget Notes
No budget notes recorded.
Raw Report Entries
25 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
11 Feb 2026 Stalled 0.00 0.0% The project could not start due to fiscal space challenge within the State Department Expedite alternative sources of funding especially the PPP model to finalize and operationalize. The project was to establish a Bio-Security/ quarantime facility at Bargani in Lamu County to support the livestock exports at Lamu Port. The designs for the facility were done but the financial resource limitation stalled the project implementation.
11 Feb 2026 Stalled 0.00 5.0% The project was affected by lack of budgetary resources PPP Model to be considered in the project The designs for the marshaling yard were completed but the project was affected by non-budgetary provision issues.
11 Feb 2026 Ongoing 0.00 56.0% The lack of activities at the site has created some issues such as destruction of Bio-security wall by the animals especially (Elephants) and also human interference The process of engaging PPP model was terminated by court, citing lack of public participation. To adhere to the ruling Public participation was redone and procurement process started afresh. A call for Expression of Interest (EOI) was redone in December 2025. The Finalization and operationalization of Bio secured Livestock Zone established at Bachuma in Taita Taveta County has stalled, however, the PPP Model was introduced. This is to finalize and operationalize the LEZ.
11 Feb 2026 Ongoing 0.00 56.0% Court ruling stopped the procurement of a PPP investor/s Re-start the PPP procuring process in line with the court ruling The procurement of PPP Model of investment ongoing
11 Feb 2026 Stalled 0.00 0.0% The process of establishment was hampered by budget realignment. Consider PPP model to develop and operate The establishment of a bio-secured livestock finishing Disease free holding ground (LEZ)at Bargoni Holding ground has not started. The designs for the LEZ were developed.
11 Feb 2026 Ongoing 3,000,000.00 56.0% N/A N/A N/A
10 Feb 2026 Ongoing 0.00 56.0% No funding SD for Livestock Development to expedite alternative sources of funding including PPP • Requests for Proposals (RFP) were sent to the 4 successful bidders in March 2025 and all were responsive and now pending evaluation. • This is being implemented under the Land Commercialization Initiative (LCI)
10 Feb 2026 Ongoing 0.00 56.0% No funding SD for Livestock Development to expedite alternative sources of funding including PPP • Requests for Proposals (RFP) were sent to the 4 successful bidders in March 2025 and all were responsive and now pending evaluation. • This is being implemented under the Land Commercialization Initiative (LCI)
10 Feb 2026 Stalled 0.00 0.0% N/A N/A N/A
10 Feb 2026 Stalled 0.00 0.0% N/A N/A N/A
10 Feb 2026 Stalled 0.00 0.0% N/A N/A N/A
10 Feb 2026 Stalled 0.00 0.0% N/A N/A N/A
10 Feb 2026 Stalled 0.00 0.0% N/A N/A N/A
10 Feb 2026 Stalled 0.00 0.0% N/A N/A N/A
10 Feb 2026 Stalled 0.00 0.0% No funding SD for Livestock Development to expedite alternative sources of funding including PPP Lack of budget provisions led to the stalling of the project.
10 Feb 2026 Ongoing 0.00 0.0% No funding To expedite alternative sources of funding including PPP Model Lack of budget provisions led to the stalling of the project.
09 Feb 2026 Stalled 0.00 0.0% Lack of budgetary provision PPP Model to be considered No budgetary allocation
09 Feb 2026 Stalled 0.00 0.0% Lack of budgetary provision PPP Model to be considered No budgetary allocation
10 Sep 2025 Ongoing 0.00 60.0%
Derived from status
No funding SD for Livestock Development to expedite alternative sources of funding including PPP Lack of budget provisions led to the stalling of the project.
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
25 Feb 2025 Ongoing 0.00 60.0%
Derived from status
No budgetary allocation Allocation of budgets No budgetary allocation
19 Feb 2025 Ongoing 0.00 60.0%
Derived from status
no provision of funds Timely provision of funds no provision of funds
19 Feb 2025 Ongoing 0.00 60.0%
Derived from status
no adequate provision of funds timely provision of funds no adequate provision of funds
19 Feb 2025 Ongoing 0.00 60.0%
Derived from status
lack of funds Timely provision of funds lack of funds