Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance indicators, and raw report history.

Reports Viewed

27

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

27

Issues reported
Reports With Resolutions

27

Action points provided
Total Amount Spent

3,000,000.00

Sum of filtered report expenditure
Average Performance

13.6%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
12
Stalled
15
Completed
0
Completion of Bachuma Livestock Export Zone (LEZ) and Construction and Operation of Lamu LEZ
Cluster: FINANCE AND PRODUCTION | Last Updated: 22 Apr 2026
Stalled High Risk Stalled Ongoing
Budget
3,000,000.00
Spent
3,000,000.00
Absorption
100.0%
Performance
13.6%
Overall Performance
13.6%
Performance
Budget Absorption
100.0%
Spent against total budget
Report Volume
Showing 10 of 27 entries
Scaled visual of entry count
Challenges
• Lack of budget Provision
• Lack of funding
• Slow process of privatization and long process of stakeholder engagement. The facilities is facing vandalism from human and animals.
• The project could not start due to fiscal space challenge within the State Department
• The project was affected by lack of budgetary resources
• The lack of activities at the site has created some issues such as destruction of Bio-security wall by the animals especially (Elephants) and also human interference
• Court ruling stopped the procurement of a PPP investor/s
• The process of establishment was hampered by budget realignment.
• None
• No funding
• Lack of budgetary provision
• No budgetary allocation
• no provision of funds
• no adequate provision of funds
Resolutions
• Provide budget to develop the Marshalling Yard
• Consider the PPP model
• Fast-track the PPP model of engagement
• Expedite alternative sources of funding especially the PPP model to finalize and operationalize.
• PPP Model to be considered in the project
• The process of engaging PPP model was terminated by court, citing lack of public participation. To adhere to the ruling Public participation was redone and procurement process started afresh. A call for Expression of Interest (EOI) was redone in December 2025.
• Re-start the PPP procuring process in line with the court ruling
• Consider PPP model to develop and operate
• None
• SD for Livestock Development to expedite alternative sources of funding including PPP
• To expedite alternative sources of funding including PPP Model
• PPP Model to be considered
• Allocation of budgets
• Timely provision of funds
• timely provision of funds
Comments
• The Project was to establish a Marshalling Yard at the Lamu Port to facilitate export of Livestock, however due to lack of budget provisions the project has stalled
• The Project has not received budget provision for the last four financial years
• The Project has not received funding and process of PPP ongoing. The evaluation of Expression of Interest (EOI) was done in January 2026 but did not yield adequate number of Bids. Re-advertisement done in February 2026 and subsequently Request for Proposal (RFP) done on the 8th of March 2026. The Evaluation of the RFP ongoing.
• The project was to establish a Bio-Security/ quarantime facility at Bargani in Lamu County to support the livestock exports at Lamu Port. The designs for the facility were done but the financial resource limitation stalled the project implementation.
• The designs for the marshaling yard were completed but the project was affected by non-budgetary provision issues.
• The Finalization and operationalization of Bio secured Livestock Zone established at Bachuma in Taita Taveta County has stalled, however, the PPP Model was introduced. This is to finalize and operationalize the LEZ.
• The procurement of PPP Model of investment ongoing
• The establishment of a bio-secured livestock finishing Disease free holding ground (LEZ)at Bargoni Holding ground has not started. The designs for the LEZ were developed.
• None
• • Requests for Proposals (RFP) were sent to the 4 successful bidders in March 2025 and all were responsive and now pending evaluation. • This is being implemented under the Land Commercialization Initiative (LCI)
• Lack of budget provisions led to the stalling of the project.
• No budgetary allocation
• no provision of funds
• no adequate provision of funds
Budget Notes
• No budget provision for the Project
• The Project was not funded in the Financial Year
Raw Report Entries
Showing 10 of 27 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
22 Apr 2026 Stalled 0.00 0.0%
Lack of budget Provision
Provide budget to develop the Marshalling Yard
The Project was to establish a Marshalling Yard at the Lamu Port to facilitate export of Livestock, however due to lack of budget provisions the project has stalled
22 Apr 2026 Stalled 0.00 0.0%
Lack of funding
Consider the PPP model
The Project has not received budget provision for the last four financial years
22 Apr 2026 Stalled 0.00 0.0%
Slow process of privatization and long process of stakeholder engagement. The facilities is facing vandalism from human and animals.
Fast-track the PPP model of engagement
The Project has not received funding and process of PPP ongoing. The evaluation of Expression of Interest (EOI) was done in January 2026 but did not yield adequate number of Bids. Re-advertisement done in February 2026 and subsequently Request for Proposal (RFP) done on the 8th of March 2026. The Evaluation of the RFP ongoing.
11 Feb 2026 Stalled 0.00 0.0%
The project could not start due to fiscal space challenge within the State Department
Expedite alternative sources of funding especially the PPP model to finalize and operationalize.
The project was to establish a Bio-Security/ quarantime facility at Bargani in Lamu County to support the livestock exports at Lamu Port. The designs for the facility were done but the financial resource limitation stalled the project implementation.
11 Feb 2026 Stalled 0.00 5.0%
The project was affected by lack of budgetary resources
PPP Model to be considered in the project
The designs for the marshaling yard were completed but the project was affected by non-budgetary provision issues.
11 Feb 2026 Ongoing 0.00 56.0%
The lack of activities at the site has created some issues such as destruction of Bio-security wall by the animals especially (Elephants) and also human interference
The process of engaging PPP model was terminated by court, citing lack of public participation. To adhere to the ruling Public participation was redone and procurement process started afresh. A call for Expression of Interest (EOI) was redone in December 2025.
The Finalization and operationalization of Bio secured Livestock Zone established at Bachuma in Taita Taveta County has stalled, however, the PPP Model was introduced. This is to finalize and operationalize the LEZ.
11 Feb 2026 Ongoing 0.00 56.0%
Court ruling stopped the procurement of a PPP investor/s
Re-start the PPP procuring process in line with the court ruling
The procurement of PPP Model of investment ongoing
11 Feb 2026 Stalled 0.00 0.0%
The process of establishment was hampered by budget realignment.
Consider PPP model to develop and operate
The establishment of a bio-secured livestock finishing Disease free holding ground (LEZ)at Bargoni Holding ground has not started. The designs for the LEZ were developed.
11 Feb 2026 Ongoing 3,000,000.00 56.0%
N/A
N/A
N/A
10 Feb 2026 Ongoing 0.00 56.0%
No funding
SD for Livestock Development to expedite alternative sources of funding including PPP
• Requests for Proposals (RFP) were sent to the 4 successful bidders in March 2025 and all were responsive and now pending evaluation. • This is being implemented under the Land Commercialization Initiative (LCI)