Detailed Public Reports

Grouped reporting data by project, including merged challenges, resolutions, comments, budget notes, performance, and raw report history.

Reports Viewed

35

Raw report records returned
Projects

1

Grouped project records
Reports With Challenges

35

Issues reported
Reports With Resolutions

35

Action points provided
Total Amount Spent

171,851,910.00

Sum of filtered report expenditure
Average Performance

24.3%

Average across filtered report rows
Status Distribution
Pipeline
0
Ongoing
34
Stalled
0
Completed
1
Civil Aviation Development and Management
Cluster: INFRASTRUCTURE | Last Updated: 25 Feb 2026
Ongoing Medium Risk Ongoing Completed
Budget
18,649,322,236.00
Spent
171,851,910.00
Absorption
0.9%
Performance
24.3%
Overall Performance
24.3%
Performance
Budget Absorption
0.9%
Spent against total budget
Report Volume
35 entries
Scaled visual of entry count
Challenges
• None
• Delays due to E-GP system for procurement process
• Land issues
• Capacity constraints
• Cancelled PIP Application
• Project not scheduled for FY 2024/2025
• A demolition plan and methodology had been established but slowed down awaiting concessioning process of the airport. It is now clear that it is not possible to achieve the targeted milestones in 2024/2025. The project has been budgeted for FY 2025/2026.
• Termination of the concession process to Adani Airport Group has led to nil achievement
Resolutions
• None
• E-GP Exception to accelerate the procurement process
• Land is not available within the airport, it is recommended that a suitabe site is identified for acquisition
• Resume the work immediately
• Expedite the application of PIP
Comments
• Currently JKIA terminal building optimization is being undertaken
• This indicator expressed as an absolute number is not the most appropriate measure for Air Navigation Services (ANS), as ANS performance is assessed based on the availability of navigation and communication systems in accordance with ICAO Standards and Recommended Practices (SARPs), which require a minimum availability of 97% to ensure there is no loss of service time (in seconds); accordingly, the appropriate Key Performance Indicator (KPI) is the percentage availability of navigation systems, against which we achieved 98%, exceeding the ICAO requirement.
• Project not scheduled to commence in FY 2025/26 due to non-allocation of land
• 5% was allocated to JKIA masterplan - the Interim Report has been submitted by the consultant 10% was allocated to detailed design and Procurement 85% was allocated to actual construction
• Construction completed. The Tower building was handed over to KCAA on 15th December 2025.
• KCAA and KAA are still in talks regarding the suitable location
• It is scheduled to be launched in December, 2025
• On track of completion
• Different equipment are tracked per individual contract eg radar equipment are tracked by contract
• Nothing is taking place
• Engagements are still ongoing and are at the tail end.
• Project not scheduled for FY 2024/2025
• Project completion rate is on schedule and will be completed within the contract period.
• The number of projects is cumulative. 1) Very High Frequency (VHF) area cover radio systems for Mua hills radar station and Lokichoggio airport 2) Digital Aerodrome Traffic Information System (D-ATIS) in JKIA, MIA, EIA and Kisumu. 3) VHF relay station for Moi International Airport 4) A 40 KVA solar power system at Lokichoggio Airport 5) Back Up Fiber Optic Links for KCAA Stations 6) Very High Frequency Direction Finder at EIA. 7) Voice Logging System at JKIA, MIA, EIA, Kisumu Airport and Malindi Airport. 8) Radio Link JKIA – ACC & DRC Project completion rate is on schedule and will be completed within the contract period.
• This project has been put on hold awaiting the direction of the new terminal building due to capacity constraints
• PIP application for JKIA was cancelled
• None
• Project completion rate is on schedule and will be completed within the contract period
• The number of projects is cumulative. 1. Very High Frequency (VHF) area cover radio systems for Mua hills radar station and Lokichoggio airport 2. Digital Aerodrome Traffic Information System (D-ATIS) in JKIA, MIA, EIA and Kisumu. 3. VHF relay station for Moi International Airport 4. A 40 KVA solar power system at Lokichoggio Airport 5. Back Up Fiber Optic Links for KCAA Stations 6. Very High Frequency Direction Finder at EIA
• A demolition plan and methodology had been established but slowed down awaiting concessioning process of the airport. It is now clear that it is not possible to achieve the targeted milestones in 2024/2025. The project has been budgeted for FY 2025/2026.
• Termination of the concession process to Adani Airport Group has led to nil achievement
Budget Notes
No budget notes recorded.
Raw Report Entries
35 entries
Date Status Amount Spent Performance Challenges Recommendations Comments
25 Feb 2026 Ongoing 0.00 10.0% N/A N/A Currently JKIA terminal building optimization is being undertaken
25 Feb 2026 Ongoing 43,005,971.00 10.0% Delays due to E-GP system for procurement process E-GP Exception to accelerate the procurement process This indicator expressed as an absolute number is not the most appropriate measure for Air Navigation Services (ANS), as ANS performance is assessed based on the availability of navigation and communication systems in accordance with ICAO Standards and Recommended Practices (SARPs), which require a minimum availability of 97% to ensure there is no loss of service time (in seconds); accordingly, the appropriate Key Performance Indicator (KPI) is the percentage availability of navigation systems, against which we achieved 98%, exceeding the ICAO requirement.
25 Feb 2026 Ongoing 0.00 0.0% Land issues Land is not available within the airport, it is recommended that a suitabe site is identified for acquisition Project not scheduled to commence in FY 2025/26 due to non-allocation of land
24 Feb 2026 Ongoing 128,845,939.00 10.0% N/A N/A 5% was allocated to JKIA masterplan - the Interim Report has been submitted by the consultant 10% was allocated to detailed design and Procurement 85% was allocated to actual construction
23 Feb 2026 Completed 0.00 85.0% N/A N/A Construction completed. The Tower building was handed over to KCAA on 15th December 2025.
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A KCAA and KAA are still in talks regarding the suitable location
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A KCAA and KAA are still in talks regarding the suitable location
18 Nov 2025 Ongoing 0.00 85.0% N/A N/A It is scheduled to be launched in December, 2025
18 Nov 2025 Ongoing 0.00 85.0% N/A N/A On track of completion
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Different equipment are tracked per individual contract eg radar equipment are tracked by contract
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Different equipment are tracked per individual contract eg radar equipment are tracked by contract
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Nothing is taking place
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Engagements are still ongoing and are at the tail end.
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Nothing is taking place
18 Nov 2025 Ongoing 0.00 10.0% N/A N/A Engagements are still ongoing and are at the tail end.
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project not scheduled for FY 2024/2025
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project completion rate is on schedule and will be completed within the contract period.
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A The number of projects is cumulative. 1) Very High Frequency (VHF) area cover radio systems for Mua hills radar station and Lokichoggio airport 2) Digital Aerodrome Traffic Information System (D-ATIS) in JKIA, MIA, EIA and Kisumu. 3) VHF relay station for Moi International Airport 4) A 40 KVA solar power system at Lokichoggio Airport 5) Back Up Fiber Optic Links for KCAA Stations 6) Very High Frequency Direction Finder at EIA. 7) Voice Logging System at JKIA, MIA, EIA, Kisumu Airport and Malindi Airport. 8) Radio Link JKIA – ACC & DRC Project completion rate is on schedule and will be completed within the contract period.
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Capacity constraints Resume the work immediately This project has been put on hold awaiting the direction of the new terminal building due to capacity constraints
05 Aug 2025 Ongoing 0.00 60.0%
Derived from status
Cancelled PIP Application Expedite the application of PIP PIP application for JKIA was cancelled
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Project not scheduled for FY 2024/2025 N/A Project not scheduled for FY 2024/2025
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Project not scheduled for FY 2024/2025 N/A Project not scheduled for FY 2024/2025
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project completion rate is on schedule and will be completed within the contract period
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A Project completion rate is on schedule and will be completed within the contract period
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A The number of projects is cumulative. 1. Very High Frequency (VHF) area cover radio systems for Mua hills radar station and Lokichoggio airport 2. Digital Aerodrome Traffic Information System (D-ATIS) in JKIA, MIA, EIA and Kisumu. 3. VHF relay station for Moi International Airport 4. A 40 KVA solar power system at Lokichoggio Airport 5. Back Up Fiber Optic Links for KCAA Stations 6. Very High Frequency Direction Finder at EIA
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A The number of projects is cumulative. 1. Very High Frequency (VHF) area cover radio systems for Mua hills radar station and Lokichoggio airport 2. Digital Aerodrome Traffic Information System (D-ATIS) in JKIA, MIA, EIA and Kisumu. 3. VHF relay station for Moi International Airport 4. A 40 KVA solar power system at Lokichoggio Airport 5. Back Up Fiber Optic Links for KCAA Stations 6. Very High Frequency Direction Finder at EIA
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
A demolition plan and methodology had been established but slowed down awaiting concessioning process of the airport. It is now clear that it is not possible to achieve the targeted milestones in 2024/2025. The project has been budgeted for FY 2025/2026. N/A A demolition plan and methodology had been established but slowed down awaiting concessioning process of the airport. It is now clear that it is not possible to achieve the targeted milestones in 2024/2025. The project has been budgeted for FY 2025/2026.
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
A demolition plan and methodology had been established but slowed down awaiting concessioning process of the airport. It is now clear that it is not possible to achieve the targeted milestones in 2024/2025. The project has been budgeted for FY 2025/2026. N/A A demolition plan and methodology had been established but slowed down awaiting concessioning process of the airport. It is now clear that it is not possible to achieve the targeted milestones in 2024/2025. The project has been budgeted for FY 2025/2026.
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
N/A N/A N/A
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Termination of the concession process to Adani Airport Group has led to nil achievement N/A Termination of the concession process to Adani Airport Group has led to nil achievement
26 Mar 2025 Ongoing 0.00 60.0%
Derived from status
Termination of the concession process to Adani Airport Group has led to nil achievement N/A Termination of the concession process to Adani Airport Group has led to nil achievement